Financial Management
Please use formula and get calculation in detail.
Acme industries is considering a proposed project whose estimated NPV is $12million.This estimate assumes that economic conditions will be average. However, the CFO wanted to do a scenario analysis and obtained the following results:
Economic Situation Probability NPV
Recession 5% -$70 million
Below Average 20% -$20 million
Average 50% $12 million
Above Average 20% $20 million
Boom 5% $30 million
Calculate the project’s expected NPV, standard deviation, and coefficient of variation. For the standard deviation please use MS Excel.
The expected NPV calculations are shown in the table below:
The expected NPV is $ 4 million
Economic situation | Probability | NPV(in mil) | Prob * NPV(in mil) |
Recession | 5% | -70 | -3.5 |
Below average | 20% | -20 | -4 |
Average | 50% | 12 | 6 |
Above average | 20% | 20 | 4 |
Boom | 5% | 30 | 1.5 |
Total | 4 |
The expected NPV calculations are shown in the table below:
Economic situation | Probability | NPV(in mil) | NPV - expected NPV | (NPV - expected NPV)^2 | Prob * (NPV - expected NPV)^2 |
Recession | 5% | -70 | -74 | 5476 | 273.8 |
Below average | 20% | -20 | -24 | 576 | 115.2 |
Average | 50% | 12 | 8 | 64 | 32 |
Above average | 20% | 20 | 16 | 256 | 51.2 |
Boom | 5% | 30 | 26 | 676 | 33.8 |
Total | 506 |
Variance of project = 506
Standard deviation of project = 22.5
Coefficient of variation = Standard dev / mean expected NPV
= 22.5/4
= 5.62
Get Answers For Free
Most questions answered within 1 hours.