Question

3. What is the IRR of a project which requires an initial cash outlay of $12,345,...

3. What is the IRR of a project which requires an initial cash outlay of $12,345, and is expected to generate after-tax cash flows of $3,600 a year for three years and then $4,200 a year for two more? years?

a. 14.00%

b. 15.50%      

c. 16.20%      

d. 17.80%

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A firm is considering a replacement project which requires the initial outlay of $300,000 which includes...
A firm is considering a replacement project which requires the initial outlay of $300,000 which includes both an after-tax salvage from the old asset of $12,000 and an additional working capital investment of $8,000. The 12-year project is expected to generate annual incremental cash flows of $54,000 and have an expected terminal value at the end of the project of $20,000. The cost of capital is 15 percent, and its marginal tax rate is 40 percent. Calculate the net present...
Project A requires an initial outlay at t = 0 of $56,841, its expected cash inflows...
Project A requires an initial outlay at t = 0 of $56,841, its expected cash inflows are $11,000 per year for 9 years, and its WACC is 13%. What is the project's IRR? Round your answer to two decimal places. Project P requires an initial outlay at t = 0 of $45,000, its expected cash inflows are $15,000 per year for 9 years, and its WACC is 12%. What is the project's MIRR? Do not round intermediate calculations. Round your...
1.) Project L requires an initial outlay at t = 0 of $50,000, its expected cash...
1.) Project L requires an initial outlay at t = 0 of $50,000, its expected cash inflows are $15,000 per year for 9 years, and its WACC is 14%. What is the project's NPV? Do not round intermediate calculations. Round your answer to the nearest cent. $   2.) Project L requires an initial outlay at t = 0 of $57,430, its expected cash inflows are $10,000 per year for 10 years, and its WACC is 14%. What is the project's...
16 A firm is considering a replacement project which requires the initial outlay of $300,000 w-hich...
16 A firm is considering a replacement project which requires the initial outlay of $300,000 w-hich includes both an after-tax salvage from the old asset of $12,000 and an additional working capital investment of $8,000. The 12-year project is expected to generate annual incremental cash flows of $54,000 and have an expected terminal value at the end of the project of $20,000. The cost of capital is 15 percent, and its marginal tax rate is 40 percent. Calculate the net...
Project L requires an initial outlay at t = 0 of $50,000, its expected cash inflows...
Project L requires an initial outlay at t = 0 of $50,000, its expected cash inflows are $15,000 per year for 9 years, and its WACC is 9%. What is the project's MIRR? Do not round intermediate calculations. Round your answer to two decimal places. = % Project S requires an initial outlay at t = 0 of $12,000, and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay...
Project S requires an initial outlay at t = 0 of $18,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $18,000, and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $43,000, and its expected cash flows would be $12,000 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have NPV's...
Project S requires an initial outlay at t = 0 of $10,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $10,000, and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $50,000, and its expected cash flows would be $13,750 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Project L, since the NPVL > NPVS. b. Project S,...
Project S requires an initial outlay at t = 0 of $10,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $10,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $28,500, and its expected cash flows would be $13,200 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV <...
Project S requires an initial outlay at t = 0 of $12,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $12,000, and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $45,000, and its expected cash flows would be $13,150 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Project L, since the NPVL > NPVS. b. Neither Project...
Project R requires an initial outlay at t = 0 of $14,000, and its expected cash...
Project R requires an initial outlay at t = 0 of $14,000, and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $32,500, and its expected cash flows would be $13,050 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV <...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT