Question

Can NPV be positive if IRR < cost of capital? Explain.

Can NPV be positive if IRR < cost of capital? Explain.

Homework Answers

Answer #1

NPV:

NPV = PV of Cash Inflows - PV of Cash Outflows
If NPV > 0 , Project can be accepted
NPV = 0 , Indifference point. Project can be accepted/ Rejected.
NPV < 0 , Project will be rejected.

IRR:

IRR is the Rate at which PV of Cash Inflows are equal to PV of Cash Outflows.

IRR = Rate at which least +ve NPV + [ NPV at that Rate / Change in NPV due to 1% inc in disc rate ] * 1%

If IRR > Cost of Capital - Project can be accepted
IRR = Cost of Capital - Indifferebce Point - Project will be accepted / Rejected
IRR < Cost of Capital - Project will be erejected

If IRR < Cost of capital, NPV will be negitive always.

Pls do rate, if the answer is correct and comment, if any further assistance is required.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
1) If the NPV of a project with one sign reversal is positive, then its IRR:...
1) If the NPV of a project with one sign reversal is positive, then its IRR: Select one: a. must be greater than the required rate of return b. must be less than the required rate of return c. could be greater or less than the required rate of return d. cannot be determined without actual cash flows 2) Which of the following statements is INCORRECT? Select one: a. An acceptable project should have an NPV greater than or equal...
Which of the following statements is INCORRECT regarding capital budgeting tools? If the NPV is positive,...
Which of the following statements is INCORRECT regarding capital budgeting tools? If the NPV is positive, the Profitability Index must be greater than 1. If the IRR is greater than the required return, then the NPV will be positive. The discounted payback period will always be smaller than the payback period. The NPV is the best capital budgeting tool, as a general rule.
1(a). (TRUE or FALSE?) A project that has a positive NPV will also have an IRR...
1(a). (TRUE or FALSE?) A project that has a positive NPV will also have an IRR that is greater than the discount rate if the proposed capital budgeting projects are independent. 1(b). (TRUE or FALSE?) Projects with NPVs of positive values will reduce the firm’s value but it just meet the firm’s requirements.
. (NPV,IRR)A company can invest $1,600,000 in a capital budgeting project that will generate the following...
. (NPV,IRR)A company can invest $1,600,000 in a capital budgeting project that will generate the following forecasted cash flows: Year Cash flow 1 $500,000 2 720,000 3 300,000 4 600,000 The company has a 13% cost of capital. a. Calculate the project’s net present value. b. Calculate the project’s internal rate of return. c. Should the firm accept or reject the project? d. What is the value added to the firm if it accepts this proposed investment?
Which of the following is not one of the benefits of using NPV over IRR to...
Which of the following is not one of the benefits of using NPV over IRR to judge a capital budgeting decision? IRR assumes that cash flows generated from the capital budgeting decision can be reinvested at the same rate of return as the project itself, NPV does not. NPV can be used to judge capital budgeting decisions with nonstandard cash flows, whereas IRR cannot. Unlike for IRR, the results from an NPV analysis can be easily compared to other capital...
Given the following cash flows for a capital project, calculate the NPV and IRR. The required...
Given the following cash flows for a capital project, calculate the NPV and IRR. The required rate of return is 8 percent. Year 0 1 2 3 4 5 Cash Flows $-37004 $11550 $12750 $16800 $10700 $5350 NPV=4947. IRR=18.0% NPV=4947. IRR=9.9% NPV=9464. IRR=9.9% NPV=9464. IRR=18.0%
Project A has an IRR of 15%. Project B has an IRR of 13%. Both projects...
Project A has an IRR of 15%. Project B has an IRR of 13%. Both projects have a cost of capital of 12%. Which of the following statements would be correct? A. Both projects have a positive NPV. True or False? Explain B. Project A must have a higher NPV than Project B, True or False? Explain. C. If Project B has a higher NPV when cost of capital is 8%, then Project B must also have higher NPV if...
For mutually exclusive projects, the incremental IRR approach to capital budgeting reconciles the IRR and NPV...
For mutually exclusive projects, the incremental IRR approach to capital budgeting reconciles the IRR and NPV methods because this approach overcomes the problems associated with multiple IRRs or no IRRs. true of false
If NPV is positive for a project, then IRR for this same project will be higher...
If NPV is positive for a project, then IRR for this same project will be higher than the required rate of return of this project. (Note this project has a conventional cash flow pattern - outflow in year 0, followed by inflows in the future years of the project). True or False
The YayForWinterBreak Company wants to calculate the NPV and IRR on the following project: Cost is...
The YayForWinterBreak Company wants to calculate the NPV and IRR on the following project: Cost is $22,000 today, with end-of-year cash flows of $10,000, $10,000, and $6,500, Years 1 through 3 respectively for three years. Assume the cost of capital is 8%. SHOW ALL WORK on the TI BAII Plus Calculator FOR FULL CREDIT. a) (8 pts) NPV? b) (5 pts) IRR? c) (2 pts) Do you accept or reject the project, and why?