Question

A firm that purchases electricity from the local utility is considering installing a steam generator. A...

A firm that purchases electricity from the local utility is considering installing a steam generator. A large generator costs $320,000 whereas a small generator costs $230,000. The cost of operating the generator would be $200,000 per year for the large and $230,000 for the small. Either generator will last for five years. The cost of capital is 15%. For each generator option, assume immediate installation, with purchase and operating costs in the current year and operating costs continuing for the next four years. Assume payments under both options at the start of each year (i.e., immediate, one year from now,..., four years from now). What is the net present value of the more attractive generator? Please round your answer to the nearest dollar. Report the NPV of cost as a negative number.

Homework Answers

Answer #1

Option 1: Large generator

Year 0 (immediate cost) = 320,000 +200,000 = 520,000

Cost in the next 4 years = 200,000

Net present value = 520,000 + 200,000/1.09 + 200,000/1.09^2 + 200,000/1.09^3 + 200,000/1.09^4 =1,167,943.98

Net present value = -$1,167,943.98 (because this is a cost)

Option 2: Small generator

Year 0 (immediate cost) = 230,000 +230,000 = 460,000

Cost in the next 4 years = 230,000

Net Present value = 460,000 + 230,000/1.09 + 230,000/1.09^2 + 230,000/1.09^3 + 230,000/1.09^4 = 1,205,135.57

Net present value = -$1,205,135.57(because this is a cost)

As we can see the NPV of costs for the large generator (Option 1) is lower than the costs of small generator. Hence the large generator would be a more attractive option.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A firm that purchases electricity from the local utility is considering installing a steam generator. A...
A firm that purchases electricity from the local utility is considering installing a steam generator. A large generator costs $280,000 whereas a small generator costs $200,000. The cost of operating the generator would be $200,000 per year for the large and $220,000 for the small. Either generator will last for five years. The cost of capital is 11%. For each generator option, assume immediate installation, with purchase and operating costs in the current year and operating costs continuing for the...
A firm that purchases electricity from the local utility is considering installing a steam generator. A...
A firm that purchases electricity from the local utility is considering installing a steam generator. A large generator costs $280,000 whereas a small generator costs $140,000. The cost of operating the generator would be $200,000 per year for the large and $220,000 for the small. Either generator will last for five years. The cost of capital is 9%. For each generator option, assume immediate installation, with purchase and operating costs in the current year and operating costs continuing for the...
Finance (Net Present Value): 1. A firm that purchases electricity from the local utility for $400,000...
Finance (Net Present Value): 1. A firm that purchases electricity from the local utility for $400,000 per year is considering installing a steam generator at a cost of $290,000. The cost of operating this generator would be $280,000 per year, and the generator will last for five years. If the firm buys the generator, it does not need to purchase any electricity from the local utility. The cost of capital is 15%. For the local utility option, consider five years...
A firm is considering installing occupancy sensors in its eight conference rooms. Each room presently has...
A firm is considering installing occupancy sensors in its eight conference rooms. Each room presently has four 4-lamp fluorescent fixtures with standard F40T12 (full spectrum 40-W, 1.5-inch in tube diameter) lamps. The fixture draws 188 watts (lamps plus ballasts). The lamps operate 10 hours/day, Monday through Friday. With the proposed system, sensors will automatically turn off the lights whenever the room is unoccupied for more than 5 minutes. The firm estimates that this will reduce the lamp operating hours to...
An electrical utility is experiencing a sharp power demand in a certain local area, and you...
An electrical utility is experiencing a sharp power demand in a certain local area, and you consider two alternatives. Each is designed to provide enough capacity during the next 25 years, and both will consume the same amount of fuel, so fuel cost is not considered in the analysis. The first alternative: Increase the generating capacity now so that the ultimate demand can be met without additional expenditures later. An investment of $25 million would be needed, and the plant...
Suppose an electric utility is considering whether to install a wind farm with 30 megawatts (mw)...
Suppose an electric utility is considering whether to install a wind farm with 30 megawatts (mw) of capacity or a natural gas generator that would produce the same amount of annual electricity. An engineering study showed that the site for the wind farm would produce a load factor of 25 percent. (Actual generation would be 25 percent of capacity on average over the course of a year.) The natural gas plant could be operated with a load factor of 50...
1. Ying works for an private electricity utility that needs to decide between two options for...
1. Ying works for an private electricity utility that needs to decide between two options for a turbine that will be constructed in 2024. 2025 will be the first year of operation. She must decide which option will cost less to construct. Past capital cost estimates are available for both options. The cost of Option A, a Whirr Turbine, was estimated to be $9 million in 2012 dollars. The cost of Option B, a Zap Turbine, was estimated to be...
B. A regional electric utility currently relies on natural gas for power generation. It has 200...
B. A regional electric utility currently relies on natural gas for power generation. It has 200 Mw of natural gas capacity that is running on an average of 30 percent efficiency. It is studying options for supplying additional power to its customers. It has all of the following options: Coal:   A 50 megawatt (Mw) coal plant with a capital cost of $50 million and operating costs of $5 million per year plus the cost of coal. The coal plant would...
1. A regulated investor-owned electric utility currently generates 12 million Mwh per year with a total...
1. A regulated investor-owned electric utility currently generates 12 million Mwh per year with a total rate base, including transmission and distribution assets, of $10 billion. Its operating costs are $200 million annually. If the regulatory agency allows a 10 percent rate of return on the rate base, what is the regulated price of electricity, and the utility's annual earnings? 2. The utility projects its annual electricity demand to grow by an additional 7 million Mwh to 19 Mwh per...
Your firm is considering a fast-food concession at the World's Fair in College Station. The cash...
Your firm is considering a fast-food concession at the World's Fair in College Station. The cash flow pattern is somewhat unusual because you must build the stands, operate them for 2 years, and then tear the stands down at the     end of the third year to restore the sites to their original condition (the stand sits idle for one year). Your firm requires a 15% pre-tax return on capital. Your firm anticipates having a marginal tax rate of 20% for...