Question

Project S requires an initial outlay at t = 0 of $18,000, and its expected cash...

Project S requires an initial outlay at t = 0 of $18,000, and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $43,000, and its expected cash flows would be $12,000 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer.

a. Both Projects S and L, since both projects have NPV's > 0.

b. Project L, since the NPVL > NPVS.

c. Project S, since the NPVS > NPVL.

d. Neither Project S nor L, since each project's NPV < 0.

e. Both Projects S and L, since both projects have IRR's > 0.

Homework Answers

Answer #1

S:

Present value of inflows=cash inflow*Present value of discounting factor(rate%,time period)

=5000/1.12+5000/1.12^2+5000/1.12^3+5000/1.12^4+5000/1.12^5

=18023.88

NPV=Present value of inflows-Present value of outflows

=18023.88-18000

=$23.88(Approx)

L:

Present value of inflows=cash inflow*Present value of discounting factor(rate%,time period)

=12000/1.12+12000/1.12^2+12000/1.12^3+12000/1.12^4+12000/1.12^5

=43257.31

NPV=Present value of inflows-Present value of outflows

=43257.31-43000

=$257.31(Approx)

Hence since projects are mutually exclusive;only project L must be selected having higher NPV.

Hence the correct option is:

b. Project L, since the NPVL > NPVS.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Project S requires an initial outlay at t = 0 of $10,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $10,000, and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $50,000, and its expected cash flows would be $13,750 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Project L, since the NPVL > NPVS. b. Project S,...
Project S requires an initial outlay at t = 0 of $10,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $10,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $28,500, and its expected cash flows would be $13,200 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV <...
Project S requires an initial outlay at t = 0 of $12,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $12,000, and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $45,000, and its expected cash flows would be $13,150 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Project L, since the NPVL > NPVS. b. Neither Project...
Project R requires an initial outlay at t = 0 of $14,000, and its expected cash...
Project R requires an initial outlay at t = 0 of $14,000, and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $32,500, and its expected cash flows would be $13,050 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV <...
Project L requires an initial outlay at t = 0 of $50,000, its expected cash inflows...
Project L requires an initial outlay at t = 0 of $50,000, its expected cash inflows are $15,000 per year for 9 years, and its WACC is 9%. What is the project's MIRR? Do not round intermediate calculations. Round your answer to two decimal places. = % Project S requires an initial outlay at t = 0 of $12,000, and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay...
Project S costs $18,000 and its expected cash flows would be $7,000 per year for 5...
Project S costs $18,000 and its expected cash flows would be $7,000 per year for 5 years. Mutually exclusive Project L costs $35,000 and its expected cash flows would be $8,400 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Neither Project S nor L, since each project's NPV < 0. c. Both Projects S and L, since...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $15,000 and its expected cash flows would...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $15,000 and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L costs $45,000 and its expected cash flows would be $9,900 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Both Projects S and L, since both projects have NPV's > 0....
(Capital Budgeting Criteria: Mutually Exclusive Projects) Project S costs $17,000 and its expected cash flows would...
(Capital Budgeting Criteria: Mutually Exclusive Projects) Project S costs $17,000 and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L costs $28,500 and its expected cash flows would be $11,250 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend? Select the correct answer. a. Project L, since the NPVL > NPVS. b. Both Projects S and L, since both projects have IRR's > 0....
Capital budgeting criteria: mutually exclusive projects Project S costs $15,000 and its expected cash flows would...
Capital budgeting criteria: mutually exclusive projects Project S costs $15,000 and its expected cash flows would be $5,500 per year for 5 years. Mutually exclusive Project L costs $40,500 and its expected cash flows would be $10,800 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend? Select the correct answer. I. Both Projects S and L, since both projects have NPV's > 0. II. Project L, since the NPVL > NPVS....
Capital budgeting criteria: mutually exclusive projects Project S costs $11,000 and its expected cash flows would...
Capital budgeting criteria: mutually exclusive projects Project S costs $11,000 and its expected cash flows would be $4,000 per year for 5 years. Mutually exclusive Project L costs $32,000 and its expected cash flows would be $14,700 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend? Select the correct answer. I. Neither S or L, since each project's NPV < 0. II. Project L, since the NPVL > NPVS. III. Project...