Question

Which of the following statements about capital investment analysis is most correct? A Although a useful...

Which of the following statements about capital investment analysis is most correct?

A Although a useful accounting concept, breakeven analysis has no role in capital investment analysis.
B Net present value (NPV) measures a project’s rate of return, while internal rate of return (IRR) measures a project’s dollar return.
C An NPV of zero indicates that the project is expected to return the amount of the initial investment, but it will not provide a return on that investment.
D On most projects, the NPV and IRR measures will give conflicting results, so managers must use judgment as to which measure to use.
E Payback measures the length of time it takes to recover the initial investment in the project.

Homework Answers

Answer #1

Answer is Option E.

Payback is the time time taken to re-earn the invested amount by the future cash inflows.

Option A is incorrect. breakeven analysis is used for capital investment analysis, specifically to determine the amount of cash flows in future.

Option B is incorrect. NPV is dollar return whereas IRR is the rate of return.

Option C is incorrect. There would be some return generated, but that might not be sufficient to cover the cost of capital incurred.

Option D is incorrect. In case of a conflict, NPV should be used a decision making tool.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Which one of the following statements about inflation is correct? A. The real rate of return...
Which one of the following statements about inflation is correct? A. The real rate of return accurately indicates how an investment opportunity will change the investor's purchasing power. B. The greater the inflation rate is, the stronger the purchasing power of a currency becomes. C. Deflation is highly desired because it immediately stimulates consumption in an economy. D. When the expected inflation increases, the nominal interest rates decline. Which of the following statements about capital budgeting tools are correct? I....
Which of the following statements about capital budgeting decision methods is most correct? NPV is superior...
Which of the following statements about capital budgeting decision methods is most correct? NPV is superior since it is the most conceptually correct method. IRR is superior since it measures the rate of return on a capital investment. PI is superior since it measures the present value benefit per dollar of capital invested. PB is superior since it is quick and easy to use and understand. None of the three methods is considered superior to the others.
Which of the following is statements related to capital budgeting is not true? A project is...
Which of the following is statements related to capital budgeting is not true? A project is considered acceptable if its NPV is greater zero. A project whose NPV is greater than its IRR is should be accepted. Both the NPV method and the IRR method of evaluating capital investment projects are widely considered to be superior to the payback method. An NPV of zero signifies that the project's cash flows are just sufficient to repay the invested capital and to...
In taking capital budgeting decisions, financial managers are advised to use more than one capital budgeting...
In taking capital budgeting decisions, financial managers are advised to use more than one capital budgeting technique for consistency, reliability and accuracy in capital budget decisions. Although the Net Present Value (NPV) capital budgeting technique is required in most capital budgeting discussion processes, it may sometimes have conflicting decision with Internal Rate of Return (IRR) under certain conditions. Briefly state the conditions under which NPV and IRR results in conflicting decisions and how the financial manager can resolve this conflict?
The IRR measures which of the following? a. The return earned on the initial investment. b....
The IRR measures which of the following? a. The return earned on the initial investment. b. The average return earned over time on the funds invested. c. The discount rate at which NPV is zero. d. The overall return if the project’s funds are invested at the cost of capital.
Consider the following cash flows for two mutually exclusive capital investment projects. The required rate of...
Consider the following cash flows for two mutually exclusive capital investment projects. The required rate of return is 16%. Use this information for the next 3 questions. Year Project A Cash Flow Project B Cash Flow 0 ($50,000) ($20,000) 1 15,000 6,000 2 15,000 6,000 3 15,000 6,000 4 13,500 5,400 5 13,500 5,400 6 6,750 5,400 Which of the following statements is true concerning projects A and B? a) Due to time disparity, IRR indicates that project A should...
1. Which of the following statements is correct? a. A project with conventional cash flows is...
1. Which of the following statements is correct? a. A project with conventional cash flows is one with an initial cash outflow followed by one or more cash inflows. b. The NPV method determines how much the future value of cash inflows exceeds the present value of costs. c. All the answers are correct. d. When two projects are independent, accepting one project implicitly eliminates the other. e. Conventional cash flow patterns could lead to conflicting decisions by NPV and...
1. Which of the following statements is CORRECT? A. One problem of the IRR method is...
1. Which of the following statements is CORRECT? A. One problem of the IRR method is that it does not consider all cash flows of a project. B. One problem of the IRR method is that it does not take into account the time value of money. C. One problem of the IRR method is that it does not consider the reinvestment of cash inflows. D. One problem of the IRR method is that a dollar received today is valued...
Capital Budgeting Analysis : A firm is planning a new project that is projected to yield...
Capital Budgeting Analysis : A firm is planning a new project that is projected to yield cash flows of - $595,000 in Year 1, $586,000 per year in Years 2 through 5, and $578,000 in Years 6 through 11. This investment will cost the company $2,580,000 today (initial outlay). We assume that the firm's cost of capital is 11%. (1) Draw a timeline to show the cash flows of the project. (2) Compute the project’s payback period, net present value...
A company estimates that its required rate of return is 18 percent on its capital investments....
A company estimates that its required rate of return is 18 percent on its capital investments. It is considering the following independent projects. Select all that are true. Question 5 options: It should accept Project C, which requires an initial investment of $1,000,000 and generates an IRR of 19 percent. Project F, which has $439 NPV, must have an IRR that is higher than 18%. It should accept Project A, which requires an initial investment of $145,000 and has a...