Question

A flexible budget is geared toward: A. Only a single level of activity B. A range...

A flexible budget is geared toward: A. Only a single level of activity B. A range of activities C. Maximum production D. The whole company's activities

Homework Answers

Answer #1

Answer: D. The whole company's activities.

Reason : Flexible budget is something that adjusts itself to the actual revenue. It considers every activity of the business and adjust the amounts according to the revenue or production levels. Then it is used for comparing with the actual expenses and control to increase efficiency and profitability of the business. for increasing the efficiency, we must consider whole of company's activities in the preparation of flexible budget.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Question 1 The difference between a static budget and a flexible budget is as follows: a...
Question 1 The difference between a static budget and a flexible budget is as follows: a The flexible budget highlights a single activity, while a static budget allows budgeting over a range of activities. b The static budget highlights a single activity level, while the flexible budget shows expected results for several activity levels. c The flexible budget measures expected income throughout a relevant range, while the static budget measures various activity levels for only one relevant range. d There...
1) A budget prepared at a single volume of activity is referred to as a: A)...
1) A budget prepared at a single volume of activity is referred to as a: A) Strategic budget. B) Standard budget. C) Static budget. D) Flexible budget. Answer:  ___________ 2) Select the incorrect statement regarding flexible budgets. A) Flexible budgets often show the estimated revenues and costs at multiple volume levels. B) A flexible budget is used to compare actual to budgeted amounts. C) A flexible budget is also known as a master budget. D) Standard prices and costs are used...
When using a flexible budget, an increase in activity within the relevant range: decreases fixed cost...
When using a flexible budget, an increase in activity within the relevant range: decreases fixed cost per unit. increases variable cost per unit. decreases total costs. decreases total variable costs.
A company's flexible budget for the range of 38,000 units to 48,000 units of production showed...
A company's flexible budget for the range of 38,000 units to 48,000 units of production showed variable overhead costs of $2.00 per unit and fixed overhead costs of $64,000. The company incurred total overhead costs of $142,700 while operating at a volume of 40,000 units. The total controllable cost variance is: I know the answer is C 1300 favorable, but not sure how they came up with that. Multiple Choice a. $2,700 favorable. b. $2,700 unfavorable. c. $1,300 favorable. d....
Actual Results Flexible Budget Variance Flexible Budget Sales Activity Variance Master Budget Units 13,000 ? 2000U...
Actual Results Flexible Budget Variance Flexible Budget Sales Activity Variance Master Budget Units 13,000 ? 2000U ? Sales revenue ? 13,000F ? ? ? Less: <Variable mfg. Costs> $87,750 $91,000 ? $105,000 <Variable mktg/adm.costs> ? $3,250U ? $4,000F 30,000 Contribution margin $52,000 ? ? $6,000U ? What is the master budget contribution margin? Select one: A. $52,000. B. $45,000. C. $47,500. D. $39,000.
ACTIVITY FLEXIBLE BUDGET Cohlmia Company provided information on the following four overhead activities. Activity                       Dri
ACTIVITY FLEXIBLE BUDGET Cohlmia Company provided information on the following four overhead activities. Activity                       DriverFixed              Cost                Variable Rate Maintenance            Machine hours         $40,000         $ 2.50 Machining                 Machine hours          25,000            3.00 Setting up                  Setups                            -                  2,250 Purchasing               Purchase orders        75,000           6.00 Cohlmia has found that the following driver levels are associated with two different levels of production. Driver                                     40,000 units              60,000 units Machine hours                     60,000                       90,000 Setups                                          50                   70 Purchase orders                  10,000                       16,000 Required: Prepare an activity-based flexible budget.
ACTIVITY FLEXIBLE BUDGET Cohlmia Company provided information on the following four overhead activities. Activity                       Driver F
ACTIVITY FLEXIBLE BUDGET Cohlmia Company provided information on the following four overhead activities. Activity                       Driver Fixed              Cost                Variable Rate Maintenance            Machine hours         $40,000          $ 2.50 Machining                 Machine hours         25,000             3.00 Setting up                  Setups                            -                 2,250 Purchasing               Purchase orders       75,000             6.00 Cohlmia has found that the following driver levels are associated with two different levels of production. Driver                                     40,000 units              60,000 units Machine hours                     60,000                        90,000 Setups                                          50                               70 Purchase orders                   10,000                        16,000 Required: Prepare...
Which of the following would not appear on a flexible budget performance report as shown in...
Which of the following would not appear on a flexible budget performance report as shown in the text? A. Variable costs. B. Mixed costs. C. A flexible budget adjusted to the actual level of activity. D. The previous year's actual costs.
Match each activity and resource to its most likely activity level. Activity level options have been...
Match each activity and resource to its most likely activity level. Activity level options have been provided below the chart. Use each only once. ACTIVITY LEVEL Activities and Resources Marketing research – salaries and support for marketing research to identify new products Labor – hourly as needed to meet production levels B Setup labor – set up equipment and software for production runs Utilities – electrical power for operating equipment in the factory Legal Department – salaries and facilities to...
16. A company's planned activity level for next year is expected to be 100,000 machine hours....
16. A company's planned activity level for next year is expected to be 100,000 machine hours. At this level of activity, the company budgeted the following manufacturing overhead costs: Variable Indirect materials Indirect labor Factory supplies $120,000 160,000 20,000 Fixed Depreciation Taxes Supervision $50,000 10,000 40,000 A flexible budget prepared at the 90,000 machine hours level of activity would show total manufacturing overhead costs of A) $270,000. B) $360,000. C) $370,000. D) $300,000.