Question

The NPV of a project decreases with discount rate r. When r=10%, NPV=$10 million; when r=11%,...

The NPV of a project decreases with discount rate r. When r=10%, NPV=$10 million; when r=11%, NPV= -$5 million. The IRR of this project must be ________.

Group of answer choices

a. Above 11%.

b. Below 10%.

c. Not enough information.

d. Between 10% and 11%.

Homework Answers

Answer #1
Answer:

Calculation of IRR

Formula = Lower rate +            NPV at lower rate                   x (Higher rate - Lower rate)
NPV at lower rate - NPV at higher rate
NPV at Lower rate 0.10000 NPV at higher rate 0.11000
NPV 10.00 (in $, million) NPV -5.00 (in $, million)
IRR= 10% + 10.0000 x (10-11)%
15.0000
IRR= 10% + 0.6667*1%
IRR= 10% + 0.6667%
IRR= 10.67%
So, from the above calculation, it can seen that the IRR of the project must be d. between 10% and 11%.
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Which of the statements below is true? a. The graphic plot of project NPV against discount...
Which of the statements below is true? a. The graphic plot of project NPV against discount rate is called the NPV profile b. NPV profile is always downward sloping, i.e., NPV decreases with higher discount rate c. At the intercept point of the NPV profile with the horizontal axis, the project IRR is zero. d. All of the above e. None of the above
You are evaluating an investment project and learn the following: The project’s NPV at a discount...
You are evaluating an investment project and learn the following: The project’s NPV at a discount rate of 20% is +$35,879 The project’s NPV at a discount rate of 24% is +$12,356 The project’s NPV at a discount rate of 26% is -$1,923 Based on (i)-(iii) above you know the project’s IRR must be: a) Less than 20% b) Greater than 26% c) Between 20% and 24% d) Between 24% and 26%
As the discount rate decreases, the IRR of a project: Select one: a. increases b. is...
As the discount rate decreases, the IRR of a project: Select one: a. increases b. is unaffected c. decreases d. This cannot be determined without the discount rate.
You are considering two mutually exclusive projects. Project A has an IRR of 10% Project B...
You are considering two mutually exclusive projects. Project A has an IRR of 10% Project B has an IRR of 8% The crossover rate is 6% Which project will have the greatest NPV if the Required Return is 4% Group of answer choices Project A and B would have the same NPV There is not enough information to answer this question. Project B Project A
A project has an NPV of £12,632 when a discount rate of 12% is used and...
A project has an NPV of £12,632 when a discount rate of 12% is used and the same project has an NPV of (£6,935) when a discount rate of 24% is used. The approximate internal rate of return of the project is: Select one: a. 18.5% b. 15.16% c. 20.5% d. 19.75% An investment project costs $10,500 and will generate $4,000 in annual cash flows for five years. What is the exact internal rate of return (IRR)? Select one: a....
Answer Question 1-3 Project A has the following projected cash flows: Year           Cash Flow 0                -11,23
Answer Question 1-3 Project A has the following projected cash flows: Year           Cash Flow 0                -11,235 1                4,400 2                4,400 3                4,400 4                4,400 5                7,400 Q1) The NPV of the above project is $_____. Assume a discount rate of 6%. a)9541 b)20776 c)17623 d)6388 Q2) The IRR for the above project is __ %. a)21.09 b)26.76 c)33.95 d)31.25 Q3)Which of the following statement is correct? a)If the discount rate increases, the IRR will decrease. b)If the discount rate increases, the NPV will stay the same. c)If...
For the following project, calculate: (a) NPV at the end of the project (discount rate 15%)...
For the following project, calculate: (a) NPV at the end of the project (discount rate 15%) (b) IRR at the end of the project. Year (n) 0 1 2 3 4 Capex -$600,000 - - - - Income - $200,000 $200,000 $200,000 $200,000 Undiscounted cash flow P/F (15%) Discounted cash flow IRR - - - - *P/F is the discount factor, converting a future value into a present value
You have just used the NPV method to determine that with a cost of capital of...
You have just used the NPV method to determine that with a cost of capital of 10% a particular project is easily rejected. What else do you know for sure? Group of answer choices The project will have an IRR greater than 10% The project will have an IRR less than 10% Not enough information to answer The project will have an IRR of exactly 10%
. Calculate the IRR and NPV for the following cash flows. Assume a 15% discount rate...
. Calculate the IRR and NPV for the following cash flows. Assume a 15% discount rate Year Project 1 Cash flow Project 2 Cash flow 0 -$20,000 -$20,000 1 1,000 12,000 2 3,000 15,000 3 4,000 3,000 4 12,000 4,000 5 15,000 1,000 9. If your tenant pays you rent of $24,000 a year for 10 years, what is the present value of the series of payments discounted at 10% annually? 10. You are going to invest $300,000 in a...
11) Your company is choosing between two MUTUALLY EXCLUSIVE projects that have a required rate of...
11) Your company is choosing between two MUTUALLY EXCLUSIVE projects that have a required rate of return of 8.25%. You have gathered the following data. Which of the project(s) should be accepted? IRR NPV Project A 6.40% $ 22.6 million Project B 8.50% $ 16.1 million A) Accept neither project, as both have a required return that is above the IRR. B) Accept project B with the higher IRR. C) Accept project A with the higher NPV. D) Accept both...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT