Question

Project L costs $47,333.24, its expected cash inflows are $11,000 per year for 9 years, and...

Project L costs $47,333.24, its expected cash inflows are $11,000 per year for 9 years, and its WACC is 13%. What is the project's IRR? Round your answer to two decimal places.

Homework Answers

Answer #1

Internal rate of return is calculated using a financial calculator by inputting the below:

  • Press the CF button.
  • CF0= -$47,333.24. It is entered with a negative sign since it is a cash outflow.
  • Cash flow for each year should be entered.
  • Press Enter and down arrow after inputting each cash flow.
  • After entering the last cash flow cash flow, press the IRR and CPT button to get the IRR of the project.

The IRR of project is 18%.

In case of any query, kindly comment on the solution.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Project L costs $50,060.50, its expected cash inflows are $11,000 per year for 9 years, and...
Project L costs $50,060.50, its expected cash inflows are $11,000 per year for 9 years, and its WACC is 11%. What is the project's IRR? Round your answer to two decimal places.v
Project L costs $44,581.60, its expected cash inflows are $10,000 per year for 9 years, and...
Project L costs $44,581.60, its expected cash inflows are $10,000 per year for 9 years, and its WACC is 13%. What is the project's IRR? Round your answer to two decimal places. Project L costs $50,000, its expected cash inflows are $12,000 per year for 7 years, and its WACC is 10%. What is the project's payback? Round your answer to two decimal places.
1. Project L costs $60,000, its expected cash inflows are $14,000 per year for 6 years,...
1. Project L costs $60,000, its expected cash inflows are $14,000 per year for 6 years, and its WACC is 9%. What is the project's payback? Round your answer to two decimal places. 2. Project L costs $40,955.09, its expected cash inflows are $9,000 per year for 10 years, and its WACC is 13%. What is the project's IRR? Round your answer to two decimal places.
a. Project L costs $42,220.68, its expected cash inflows are $9,000 per year for 11 years,...
a. Project L costs $42,220.68, its expected cash inflows are $9,000 per year for 11 years, and its WACC is 12%. What is the project's IRR? Round your answer to two decimal places. b.Project L costs $45,000, its expected cash inflows are $13,000 per year for 8 years, and its WACC is 14%. What is the project's MIRR? Round your answer to two decimal places. Do not round your intermediate calculations. c. Project L costs $70,000, its expected cash inflows...
Project L costs $42,791.88, its expected cash inflows are $9,000 per year for 9 years, and...
Project L costs $42,791.88, its expected cash inflows are $9,000 per year for 9 years, and its WACC is 9%. What is the project's IRR? Round your answer to two decimal places.
Project L costs $40,191.97, its expected cash inflows are $9,000 per year for 9 years, and...
Project L costs $40,191.97, its expected cash inflows are $9,000 per year for 9 years, and its WACC is 12%. What is the project's IRR? Round your answer to two decimal places.   %
1.Project K costs $57,890.94, its expected cash inflows are $14,000 per year for 8 years, and...
1.Project K costs $57,890.94, its expected cash inflows are $14,000 per year for 8 years, and its WACC is 9%. What is the project's IRR? Round your answer to two decimal places. 2.Project K costs $35,000, its expected cash inflows are $10,000 per year for 8 years, and its WACC is 9%. What is the project's discounted payback? Round your answer to two decimal places. 3.Project K costs $45,000, its expected cash inflows are $11,000 per year for 10 years,...
Project L costs $50,968.24, its expected cash inflows are $12,000 per year for 8 years, and...
Project L costs $50,968.24, its expected cash inflows are $12,000 per year for 8 years, and its WACC is 9%. What is the project's IRR? Round your answer to two decimal places.
1. Project K costs $45,000, its expected cash inflows are $15,000 per year for 9 years,...
1. Project K costs $45,000, its expected cash inflows are $15,000 per year for 9 years, and its WACC is 11%. What is the project's NPV? Round your answer to the nearest cent. 2. Project K costs $59,542.90, its expected cash inflows are $12,000 per year for 10 years, and its WACC is 14%. What is the project's IRR? Round your answer to two decimal places. 3. Project K costs $75,000, its expected cash inflows are $15,000 per year for...
Project L costs $55,000, its expected cash inflows are $13,000 per year for 9 years, and...
Project L costs $55,000, its expected cash inflows are $13,000 per year for 9 years, and its WACC is 11%. What is the project's payback? Round your answer to two decimal places.