The table below lists the independent projects that your company
is considering to invest:
Project Initial investment (USD) NPV
(USD) IRR (%)
A 150000 35803 12.94
B 510000 57040 12.41
C 230000 59392 13.08
D 450000 47742 12.44
E 370000 -34559 10.42
F 110000 32830 13.04
G 510000 143507 12.38
The required return is 11.0 percent. If there is an investment
budget ceiling of $1,000,000, what is the total net present value
of investment opportunuties missed (the sum of NPVs of the feasible
projects that your company couldn't invest) due to budget
limit?
47742
95195
107134
104782
83545
Project | Initial Investment |
NPV | NPV as % of
Initial Investment [NPV/Initial Investment] |
Ranking
Based on % Return [Highest to Lowest] |
Acceptance in
the order of Ranks[upto total initial investment of 1000000] |
Initial Investment |
NPV |
A | 150000 | 35803 | 0.238686667 | 4 | Accept | 150000 | 35803 |
B | 510000 | 57040 | 0.111843137 | 5 | |||
C | 230000 | 59392 | 0.258226087 | 3 | Accept | 230000 | 59392 |
D | 450000 | 47742 | 0.106093333 | 6 | |||
F | 110000 | 32830 | 0.298454545 | 1 | Accept | 110000 | 32830 |
G | 510000 | 143507 | 0.281386275 | 2 | Accept | 510000 | 143507 |
Total NPV
= Sum of NPVs |
376314 | Total | 1000000 | 271532 |
E has Negative NPV and IRR is also Lower than Required Rate of Return. Therefore, E is Not a Feasible Project All.
Projects Lost due to Captial Constraint = Project B and D.
NPV lost = NPV of B + NPV of D = 57040 + 47742 = $104782
Get Answers For Free
Most questions answered within 1 hours.