Question

The table below lists the independent projects that your company is considering to invest: Project   Initial...

The table below lists the independent projects that your company is considering to invest:
Project   Initial investment (USD)   NPV (USD)   IRR (%)
A   150000   35803   12.94
B   510000   57040   12.41
C   230000   59392   13.08
D   450000   47742   12.44
E   370000   -34559   10.42
F   110000   32830   13.04
G   510000   143507   12.38
The required return is 11.0 percent. If there is an investment budget ceiling of $1,000,000, what is the total net present value of investment opportunuties missed (the sum of NPVs of the feasible projects that your company couldn't invest) due to budget limit?
      
47742
      
95195
      
107134
      
104782
      
83545

Homework Answers

Answer #1
Project Initial
Investment
NPV NPV as % of Initial Investment
[NPV/Initial Investment]
Ranking Based
on % Return
[Highest to Lowest]
Acceptance in the
order of Ranks[upto total initial investment of 1000000]
Initial
Investment
NPV
A 150000 35803 0.238686667 4 Accept 150000 35803
B 510000 57040 0.111843137 5
C 230000 59392 0.258226087 3 Accept 230000 59392
D 450000 47742 0.106093333 6
F 110000 32830 0.298454545 1 Accept 110000 32830
G 510000 143507 0.281386275 2 Accept 510000 143507
Total NPV =
Sum of NPVs
376314 Total 1000000 271532

E has Negative NPV and IRR is also Lower than Required Rate of Return. Therefore, E is Not a Feasible Project All.

Projects Lost due to Captial Constraint = Project B and D.

NPV lost = NPV of B + NPV of D = 57040 + 47742 = $104782

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT