Question

The net present value of a project is $260000 at the discount rate of 14.0 percent....

The net present value of a project is $260000 at the discount rate of 14.0 percent. Which of the following could be the IRR of this project?
a)11.6
b)12.29
c)11.6
d)11.96
e)16.6

Homework Answers

Answer #1

The NPV of a project is the difference between the Present value of the future cash flows discounted at the rate of return and the initial cash outflow.

Also The IRR is the particular rate of return at which the NPV is zero

Now here when the rate of return is 14% the NpV is $260000

In order to reduce the NPv to zero we need to increase the discount rate so the present values of cash inflows will decrease sufficiently for the NPV to become zero.

So the IRR must be a rate above 14%

In the options only 16.6 is above 14%

So the correct choice is option e) 16.6

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
11. The discount rate that makes the net present value of an investment exactly equal to...
11. The discount rate that makes the net present value of an investment exactly equal to zero is the: A) Payback period. B) Internal rate of return. C) Average accounting return. D) Profitability index. E) Discounted payback period. 12. The internal rate of return (IRR) rule can be best stated as: A) An investment is acceptable if its IRR is exactly equal to its net present value (NPV). B) An investment is acceptable if its IRR is exactly equal to...
What is the net present value of a project with the following cash flows if the...
What is the net present value of a project with the following cash flows if the discount rate is 10 percent? Year 0               1                2               3              4 Cash Flow -$32,000    $9,000     $10,000    $15,200      $7,800 A. $1,085.25 B. $1,193.77 C. $3,498.28 D. $4,102.86 E. $4,513.15
The internal rate of return is the discount rate at which the net present value is...
The internal rate of return is the discount rate at which the net present value is Select one: a. positive. b. There is no relationship between these two concepts. c. equal to zero. d. negative.
9 the following are true/false 4)When the IRR serves as the discount rate, the net present...
9 the following are true/false 4)When the IRR serves as the discount rate, the net present value =$0 14) The first step when solving for the modified IRR (MIRR) is to calculate the present value of the cash inflows. 16) It is not fair to say that all capital budgeting methods have an accept-reject criterion. 17) a project costing $1000 and returning $450 annually for three will have a npv> $0 if the discount rate is =15% 18) If the...
Project A has an internal rate of return (IRR) of 15 percent. Project B has an...
Project A has an internal rate of return (IRR) of 15 percent. Project B has an IRR of 14 percent. Both projects have a required return of 12 percent. Which of the following statements is most correct? a. Both projects have a positive net present value (NPV). b. Project A must have a higher NPV than project B. c. If the required return were less than 12 percent, Project B would have a higher IRR than Project A. d. Project...
Calculate the Net Present Worth (or Net Present Value), and benefit-cost (B/C) ratio of the following...
Calculate the Net Present Worth (or Net Present Value), and benefit-cost (B/C) ratio of the following project, assuming an 8% discount rate. Also determine the project’s Internal Rate of Return (IRR). Year Cash Flow ($) 0 -400.00 5 -100.00 15 +500.00 30 +2,500.00
Project A has a net present value of $1,500, a payback period of 2 years, and...
Project A has a net present value of $1,500, a payback period of 2 years, and an internal rate of return of 12%.  Project B has a net present value of $1,800, a payback period of 4 years, and an internal rate of return of 10%.  Project C has a netpresent value of $1,750, a payback period of 3 years, and an internal rate of return of 11%.  If the projects are mutually exclusive, which project should be undertaken? A. Project A because...
The i thermal rate of return is: The discount rate that makes the net present value...
The i thermal rate of return is: The discount rate that makes the net present value of a project equal to the initial cash outlay. Equivalent to the discount rate that makes the net present value equal to one. Tedious to compute without the use of either a Financial calculator or a computer. Highly dependent upon the current interest rates offered in the marketplace. A better methodology than net present value when dealing with unconventional cash flows.
Net present value _____________. Select one: a. Requires the firm set an arbitrary cutoff point for...
Net present value _____________. Select one: a. Requires the firm set an arbitrary cutoff point for determining whether an investment is acceptable b. Is equal to zero when the discount rate used is less than the IRR c. Is simplified by the fact that future cash flows are easy to estimate d. Is equal to the initial investment in a project e. Compares project cost to the present value of the project benefits
Net Present Value Versus Internal Rate of Return For discount factors use Exhibit 12B-1 and Exhibit...
Net Present Value Versus Internal Rate of Return For discount factors use Exhibit 12B-1 and Exhibit 12B-2. Skiba Company is thinking about two different modifications to its current manufacturing process. The after-tax cash flows associated with the two investments follow: Year Project I Project II 0 $(100,000) $(100,000) 1 —           63,857 2   134,560     63,857 Skiba's cost of capital is 12%. Required: 1. Compute the NPV and the IRR for each investment. Round present value calculations and your final NPV answers...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT