The net present value of a project is $260000 at the discount
rate of 14.0 percent. Which of the following could be the IRR of
this project?
a)11.6
b)12.29
c)11.6
d)11.96
e)16.6
The NPV of a project is the difference between the Present value of the future cash flows discounted at the rate of return and the initial cash outflow.
Also The IRR is the particular rate of return at which the NPV is zero
Now here when the rate of return is 14% the NpV is $260000
In order to reduce the NPv to zero we need to increase the discount rate so the present values of cash inflows will decrease sufficiently for the NPV to become zero.
So the IRR must be a rate above 14%
In the options only 16.6 is above 14%
So the correct choice is option e) 16.6
Get Answers For Free
Most questions answered within 1 hours.