Question

Consider the capital budgeting decision to be made with the following data about 2 competing projects....

Consider the capital budgeting decision to be made with the following data about 2 competing projects. Project A has an NPV of $12 500, and IRR of 10% and a payback period of 3 years. Project B has an NPV of $12 000, but an IRR of 13% and a payback period of 2 years 10 months. Which project(s) would be chosen on an independent basis?

Select one:

a. Project B

b. Neither Project A nor Project B

c. Project A and Project B

d. Project A

Homework Answers

Answer #1

The answer will be “c” – Project A and Project B

Explanation: Here the projects are independent and not mutually exclusive. Hence both the projects can be selected if they meet the capital budgeting criteria.

NPV of both projects are positive and hence both projects can be selected. IRR of both projects are in double digits and since the hurdle rate is not provided we can assume that both the projects have IRR which is greater than hurdle rate. Also the desired payback is not given and hence we can assume that payback of both projects are less than the desired payback period.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Consider the capital budgeting decision to be made with the following data about 2 competing projects....
Consider the capital budgeting decision to be made with the following data about 2 competing projects. Project A has an NPV of $12 500, and IRR of 10% and a payback period of 3 years. Project B has an NPV of $12 000, but an IRR of 13% and a payback period of 2 years 10 months. Which project(s) would be chosen on an independent basis? Select one: a. Project A and Project B b. Neither Project A nor Project...
CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's...
CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$27,000 $9,000 $9,000 $9,000 $9,000 $9,000 Project N -$81,000 $25,200 $25,200 $25,200 $25,200 $25,200 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers to two...
CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's...
CAPITAL BUDGETING CRITERIA A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$18,000 $6,000 $6,000 $6,000 $6,000 $6,000 Project N -$54,000 $16,800 $16,800 $16,800 $16,800 $16,800 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers to two...
Homework - Capital Budgeting 1.The Hyatt Group Inc., has identified the following two mutually exclusive projects:...
Homework - Capital Budgeting 1.The Hyatt Group Inc., has identified the following two mutually exclusive projects: ​Cash Flows​Cash Flows Year​Project A​Project B 0​-$10,000​_$10,000 1​ 200​ 5,000 2​ 500​ 6,000 3​ 8,200​ 500 4​ 4,800​ 500 a. What is the IRR of each of these projects? If you apply the IRR decision rule, which project should the company accept? Is this decision necessarily correct? b. If the required rate of return is 9 percent, what is the NPV of each of...
Cooper Electronics uses NPV profiles to visually evaluate competing projects. Key data for the two projects...
Cooper Electronics uses NPV profiles to visually evaluate competing projects. Key data for the two projects under consideration is given in the following table. Using these data, graph, on the same set of axes, the NPV profiles for each project using discount rates of 0%, 8%, and the IRR. Initial investment (CF0) Terra Firma $30 000 $25 000 Year (t) Operating cash inflows 1 $7 000 $6 000 2 10 000 9 000 3 12 000 9 000 4 10...
1. Consider the following information for projects K and W to answer the following 2 (A...
1. Consider the following information for projects K and W to answer the following 2 (A & B) questions: Project K: NPV = $1,500. IRR = 20% Project W: NPV = $2,500. IRR = 15% A) Assume Project K and Project W are independent projects with a WACC = 10%. Which of the following is true? a. Both Projects K and W should be enacted since both have a positive NPV. b. Neither Project K or W should be enacted...
You are a financial analyst for Hittle Company. The director of capital budgeting has asked you...
You are a financial analyst for Hittle Company. The director of capital budgeting has asked you to analyze two proposed capital investments, Projects X and Y. Each project has a cost of $10,000, and the cost of capital for each project is 10 percent. The payback cutoff period is 3 years. The projects’ expected net cash flows are as follows: Expected Net Cash Flows Year Project X 0 ($10,000) 1 6,500 2 3,000 3 3,000 4 1,000 Project Y ($10,000)...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$500 $45 $45 $45 $160 $160 Project 2 -$450 $300 $300 $60 $60 $60 Which project would you recommend? Select the correct answer. a. Both Projects 1 and 2, since both projects have NPV's > 0. b. Project 1, since the NPV1 > NPV2. c. Both Projects 1 and 2, since both...
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax...
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$9,000 $3,000 $3,000 $3,000 $3,000 $3,000 Project N -$27,000 $8,400 $8,400 $8,400 $8,400 $8,400 Calculate NPV for each project. Do not round intermediate calculations. Round your answers to the nearest cent. Project M:    $   Project N:    $   Calculate IRR for each project. Do not round intermediate calculations. Round your answers to...
12. Conclusions about capital budgeting The decision process Before making capital budgeting decisions, finance professionals often...
12. Conclusions about capital budgeting The decision process Before making capital budgeting decisions, finance professionals often generate, review, analyze, select, and implement long-term investment proposals that meet firm-specific criteria and are consistent with the firm 's strategic goals. Companies often use several methods to evaluate the project's cash flows and each of them has its benefits and disadvantages. Based on your understanding of the capital budgeting evaluation methods, which of the following conclusions about capital budgeting are valid? Check all...