Question

A project has the following total (or net) cash flows.                __________________________________________            &nbs

A project has the following total (or net) cash flows.

               __________________________________________

              Year          Total (or net) cash flow

               _________________________________________

1 $20,000
2 30,000
3 50,000
4 60,000
_________________________________________

The required rate of return on the project is 15 percent. The initial investment (or initial cost or initial outlay) of the project is $80,000.
a) Find the net present value (NPV) of the project.
b) Find the profitability index (PI) of the project.
c) Calculate the modified internal rate of return (MIRR) of the project.

Homework Answers

Answer #1

Formulae

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A project has the following total (or net) cash flows.                ________________________________________             
A project has the following total (or net) cash flows.                ________________________________________                 Year         Total (or net) cash flow                ________________________________________ 1 $50,000 2 70,000 3 80,000 4 100,000 _______________________________________    The required rate of return on the project is 13 percent. The initial investment (or initial cost or initial outlay) of the project is $100,000. a) Find the (regular) payback period of the project. b) Compute the discounted payback period of the project.
A project has the following total (or net) cash flows.                ________________________________________             
A project has the following total (or net) cash flows.                ________________________________________                 Year         Total (or net) cash flow                ________________________________________ 1 $50,000 2 70,000 3 80,000 4 100,000 _______________________________________    The required rate of return on the project is 13 percent. The initial investment (or initial cost or initial outlay) of the project is $100,000. a) Find the (regular) payback period of the project. b) Compute the discounted payback period of the project.
2. A company is considering a project that has the following cash flows: C0 = -3,000,...
2. A company is considering a project that has the following cash flows: C0 = -3,000, C1 = +900, C2 = +500, C3 = +1,100, and C4 = +1,900, with a risk-adjusted discount rate of 8%. A) Calculate the Net Present Value (NPV), Internal Rate of Return (IRR), Modified Internal Rate of Return (MIRR), and Profitability Index (PI) of this project. B) If you were the manager of the firm, will you accept or reject the project based on the...
6B4 A project has an initial outlay of $3,480. It has a single payoff at the...
6B4 A project has an initial outlay of $3,480. It has a single payoff at the end of year 3 of $9,922. What is the net present value (NPV) of the project if the company’s cost of capital is 11.97 percent? 6C4 Find the modified internal rate of return (MIRR) for the following series of future cash flows if the company is able to reinvest cash flows received from the project at an annual rate of 11.59 percent.The initial outlay...
You are considering building a shopping mall. The initial investment is ?$1.43. million. The cash flows...
You are considering building a shopping mall. The initial investment is ?$1.43. million. The cash flows are?$410,000 for year? 1,200,000 for year?2, $200,000 for year? 3, and ?$170,000 for year 4. What are the net present value? (NPV) and profitability index? (PI) of the project if the cost of capital is 12?%? Compute the internal rate of return? (IRR) for the project.
Telesis Corp is considering a project that has the following cash flows: Year Cash Flow 0...
Telesis Corp is considering a project that has the following cash flows: Year Cash Flow 0 -$1,000 1 400 2 300 3 500 4 400 The company’s weighted average cost of capital (WACC) is 10%. What are the project’s payback period (Payback), internal rate of return (IRR), net present value (NPV), and profitability index (PI)? A. Payback = 3.5, IRR = 10.22%, NPV = $1260, PI=1.26 B. Payback = 2.6, IRR = 21.22%, NPV = $349, PI=1.35 C. Payback =...
1. A project has an initial outlay of $1,732. The project will generate annual cash flows...
1. A project has an initial outlay of $1,732. The project will generate annual cash flows of $783 over the 4-year life of the project and terminal cash flows of $258 in the last year of the project. If the required rate of return on the project is 4%, what is the net present value (NPV) of the project? Note: Enter your answer rounded off to two decimal points. Do not enter $ or comma in the answer box. 2.A...
The IRR evaluation method assumes that cash flows from the project are reinvested at the same...
The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project’s IRR. Consider the following situation: Blue Llama Mining Company is analyzing a project that requires an initial investment of $450,000. The project’s expected cash flows are: Year Cash...
The profitability index (PI) of a project is 1.1, and the initial investment (cost) is $10,000...
The profitability index (PI) of a project is 1.1, and the initial investment (cost) is $10,000 . What do you know about the project's net present value (NPV) and its internal rate of return (IRR)?
Your company is considering an expansion into a new product line. The project cash flows are...
Your company is considering an expansion into a new product line. The project cash flows are as follows:        Year                     Project A                                0                     -$60,000                                1                         44,000                                    2                          20,000                                     3                          14,000                    The required return for this project is 10%.          What is the NPV for the project? What is the IRR for the project? What...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT