Question

Sloan Transmissions, Inc., has the following estimates for its new gear assembly project: price = $3,100...

Sloan Transmissions, Inc., has the following estimates for its new gear assembly project: price = $3,100 per unit; variable costs = $620 per unit; fixed costs = $4.4 million; quantity = 92,000 units. Suppose the company believes all of its estimates are accurate only to within ±15 percent. What values should the company use for the four variables given here when it performs its best-case scenario analysis? What about the worst-case scenario? Complete the table below.

  

Scenarios Unit Sales Unit Price Unit Variable Cost Fixed Cost
Base
Best
Worst

Homework Answers

Answer #1

Best Case Scenario- This is the best possible scenario, therefore price and quantity will be at the maximum possible level (i.e. +15%) and variable, fixed costs will be at the lowest possible level (i.e. -15%)

Worst Case Scenario- This is the worst possible scenario, therefore price and quantity will be at the minimum possible level (i.e. -15%) and variable, fixed costs will be at the highest possible level (i.e. +15%)

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Sloan Transmissions, Inc., has the following estimates for its new gear assembly project: price = $3,100...
Sloan Transmissions, Inc., has the following estimates for its new gear assembly project: price = $3,100 per unit; variable costs = $620 per unit; fixed costs = $4.4 million; quantity = 92,000 units. Suppose the company believes all of its estimates are accurate only to within ±15 percent. What values should the company use for the four variables given here when it performs its best-case scenario analysis? What about the worst-case scenario?    Scenario Units Sales Unit Price Unit Variable...
Sloan Transmissions, Inc., has the following estimates for its new gear assembly project: price = $1,200...
Sloan Transmissions, Inc., has the following estimates for its new gear assembly project: price = $1,200 per unit; variable costs = $240 per unit; fixed costs = $2.6 million; quantity = 70,000 units. Suppose the company believes all of its estimates are accurate only to within ±10 percent. What values should the company use for the four variables given here when it performs its best-case scenario analysis? What about the worst-case scenario? Scenario Units Sales Unit Price Unit Variable cost...
3. Scenario Analysis [LO2] Sloan Transmissions, Inc., has the following estimates for its new gear assembly...
3. Scenario Analysis [LO2] Sloan Transmissions, Inc., has the following estimates for its new gear assembly project: Price = $1,440 per unit; variable costs = $460 per unit; fixed costs = $3.9 million; quantity = 85,000 units. Suppose the company believes all of its estimates are accurate only to within ±15 percent. What values should the company use for the four variables given here when it performs its best-case scenario analysis? What about the worst-case scenario?
Automatic Transmissions, Inc., has the following estimates for its new gear assembly project: price = $940...
Automatic Transmissions, Inc., has the following estimates for its new gear assembly project: price = $940 per unit; variable cost = $340 per unit; fixed costs = $3.4 million; quantity = 53,000 units. Suppose the company believes all of its estimates are accurate only to within ±15 percent. What values should the company use for the four variables given here when it performs its best-case scenario analysis? What about the worst-case scenario?
Whitewater Transmissions, Inc., has the following estimates for its new gear assembly project: price = $2,020...
Whitewater Transmissions, Inc., has the following estimates for its new gear assembly project: price = $2,020 per unit; variable costs = $800 per unit; fixed costs = $5.7 million; quantity = 111,000 units. Suppose the company believes all of its estimates are accurate only to within ±15%. What values should the company use for the four variables given here when it performs its best-case scenario analysis? What about the worst-case scenario? (Enter the answers in dollars, not millions of dollars,...
Whitewater Transmissions, Inc., has the following estimates for its new gear assembly project: price = $1,720...
Whitewater Transmissions, Inc., has the following estimates for its new gear assembly project: price = $1,720 per unit; variable costs = $500 per unit; fixed costs = $4.2 million; quantity = 96,000 units. Suppose the company believes all of its estimates are accurate only to within ±15%. What values should the company use for the four variables given here when it performs its best-case scenario analysis? What about the worst-case scenario? (Enter the answers in dollars, not millions of dollars,...
Louise Inc. has the following estimates for its new gear assembly project: price = $1,900 per...
Louise Inc. has the following estimates for its new gear assembly project: price = $1,900 per unit; variable costs = $170 per unit; fixed costs = $6,000,000; quantity = 105,000 units. Suppose the company believes all of its estimates are accurate only within + or - 15%. What values should the company use for the four variables given here when it performs its best case scenario analysis? What about the worst case scenario? (Best case scenario: $2,185; $144.5; $5,100,000; 120,750...
Sales are projected at 15,500 hand sanitizer per year over the next four years. It will...
Sales are projected at 15,500 hand sanitizer per year over the next four years. It will cost you $44,000 to install the equipment necessary to start production; you’ll depreciate this cost straight-line to zero over the project’s life. You estimate that, in four years, this equipment can be salvaged for $32,000. Your fixed production costs will be $65,000 per year, price per unit is $7, and your variable production costs should be $1.50 per unit ($0.50 per unit in variable...
Suppose you are considering an investment project that requires $800.000, has a six-year life, and has...
Suppose you are considering an investment project that requires $800.000, has a six-year life, and has a salvage value of $100,000. Sales volume is projected to be 65,000 units per year. Price per unit is $63, variable cost per unit is $42, and fixed costs are $532,000 per year. The depreciation method is a five-year SL and assume MARR 10%. (a) Determine the break-even sales volume. (b) Calculate the cash flows of the base case over six years and its...
We are evaluating a project that costs $732,000, has a six-year life, and has no salvage...
We are evaluating a project that costs $732,000, has a six-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 55,000 units per year. Price per unit is $60, variable cost per unit is $30, and fixed costs are $640,000 per year. The tax rate is 35 percent, and we require a return of 12 percent on this project. Suppose the projections given for price, quantity,...