0 1 2 3 4
Project S -$1,000 $882.23 $260 $15 $5
Project L -$1,000 $5 $240 $400 $817.44

The company's WACC is 10.5%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal place

Homework Answers

Answer #1

Calculating IRR of both Project using EXCEL FUNCTION:-

IRR of Project S is 12.80%

IRR of Project L is 12.00%

As WACC is 10.50% which is less than IRR in both case. Thus, the better Project is the one providing higher Internal Rate of Return(IRR) which is Project A

IRR of Better Project is 12.80%

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows:...
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $872.40 $260 $15 $10 Project L -$1,000 $10 $260 $400 $762.96 The company's WACC is 10.5%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows:...
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $874.19 $260 $5 $5 Project L -$1,000 $0 $240 $400 $792.04 The company's WACC is 9.5%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places. %
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows:...
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $870.33 $260 $5 $10 Project L -$1,000 $0 $240 $400 $844.26 The company's WACC is 8.5%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows:...
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows:    0 1 2 3 4 Project S -$1,000 $871.66 $250 $15 $5 Project L -$1,000 $5 $260 $400 $753.16 The company's WACC is 9.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows:...
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $875.62 $240 $15 $15 Project L -$1,000 $10 $260 $380 $762.25 The company's WACC is 9.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows:...
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $878.96 $260 $10 $10 Project L -$1,000 $0 $260 $420 $745.01 The company's WACC is 10.5%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places. ____%
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows:...
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $892.99 $240 $15 $15 Project L -$1,000 $10 $250 $400 $779.50 The company's WACC is 10.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.   %
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows:...
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $869.52 $250 $15 $10 Project L -$1,000 $0 $260 $400 $780.94 The company's WACC is 9.5%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.   %
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows:...
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $889.32 $240 $10 $5 Project L -$1,000 $0 $250 $400 $770.57 The company's WACC is 9.5%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places. ____%
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows:...
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 Project S -$1,000 $858.80 $260 $15 $15 Project L -$1,000 $5 $250 $380 $861.23 The company's WACC is 9.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places.   %=