Question

What is the NPV of a project if IRR < discount rate (Assuming that the first...

What is the NPV of a project if IRR < discount rate (Assuming that the first cash flow is negative and all of the cash flows from the project are positive)?

< 0

> 0

= 0

None

Homework Answers

Answer #1

Answer: <0

At IRR, NPV = 0
PV of Cash Inflows = PV of Cash Outflows
IRR gives the rate of return generated by the project.
A project has to be accepted only if it generates the return atleast equal to Cost of Capital.
i.e., A project has to be accepted only if the IRR is equal to or greater than Discount Rate.
If IRR < Discount Rate, the project is generating Return less than the Cost of Capital.
Therefore, NPV will be negative, i.e., NPV<0
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
. Calculate the IRR and NPV for the following cash flows. Assume a 15% discount rate...
. Calculate the IRR and NPV for the following cash flows. Assume a 15% discount rate Year Project 1 Cash flow Project 2 Cash flow 0 -$20,000 -$20,000 1 1,000 12,000 2 3,000 15,000 3 4,000 3,000 4 12,000 4,000 5 15,000 1,000 9. If your tenant pays you rent of $24,000 a year for 10 years, what is the present value of the series of payments discounted at 10% annually? 10. You are going to invest $300,000 in a...
For the following project, calculate: (a) NPV at the end of the project (discount rate 15%)...
For the following project, calculate: (a) NPV at the end of the project (discount rate 15%) (b) IRR at the end of the project. Year (n) 0 1 2 3 4 Capex -$600,000 - - - - Income - $200,000 $200,000 $200,000 $200,000 Undiscounted cash flow P/F (15%) Discounted cash flow IRR - - - - *P/F is the discount factor, converting a future value into a present value
If NPV is positive for a project, then IRR for this same project will be higher...
If NPV is positive for a project, then IRR for this same project will be higher than the required rate of return of this project. (Note this project has a conventional cash flow pattern - outflow in year 0, followed by inflows in the future years of the project). True or False
When NPV and IRR rules result in a conflicting decision regarding acceptance of a project managers...
When NPV and IRR rules result in a conflicting decision regarding acceptance of a project managers could use the MIRR. It assumes reinvestment of projects' cash flows at the WACC, so it produces results consistent with NPV method. Let's try to find the MIRR for the project with the following cash flows: Initial cost of -800 at time zero, CF1 = 400, CF 2 = 570, CF3 = -130. Here we have two negative cash flows and two positive cash...
 LO 3 LO 4 7. Calculating NPV and IRR. A project that provides annual cash...
 LO 3 LO 4 7. Calculating NPV and IRR. A project that provides annual cash flows of $2,620 for eight years costs $9,430 today. Is this a good project if the required return is 8 percent? What if it's 24 percent? At what discount rate would you be indifferent between accepting the project and rejecting it?  LO 4 9. Calculating NPV. For the cash flows in the previous problem, what is the NPV at a discount rate of...
1) If the NPV of a project with one sign reversal is positive, then its IRR:...
1) If the NPV of a project with one sign reversal is positive, then its IRR: Select one: a. must be greater than the required rate of return b. must be less than the required rate of return c. could be greater or less than the required rate of return d. cannot be determined without actual cash flows 2) Which of the following statements is INCORRECT? Select one: a. An acceptable project should have an NPV greater than or equal...
Suppose a project generates positive cash flows for the next 12 years and the project’s NPV...
Suppose a project generates positive cash flows for the next 12 years and the project’s NPV is $110,000 when discount rate is 6%. Also suppose that the IRR=8.7%. Which of the following may be a possible value for NPV when discount rate is 7.4%? A. -$25,000 B. 0 C. $25,000 D. $125,000 E. None of the above
Given the following cash flows for a capital project, calculate the NPV and IRR. The required...
Given the following cash flows for a capital project, calculate the NPV and IRR. The required rate of return is 8 percent. Year 0 1 2 3 4 5 Cash Flows $-37004 $11550 $12750 $16800 $10700 $5350 NPV=4947. IRR=18.0% NPV=4947. IRR=9.9% NPV=9464. IRR=9.9% NPV=9464. IRR=18.0%
9 the following are true/false 4)When the IRR serves as the discount rate, the net present...
9 the following are true/false 4)When the IRR serves as the discount rate, the net present value =$0 14) The first step when solving for the modified IRR (MIRR) is to calculate the present value of the cash inflows. 16) It is not fair to say that all capital budgeting methods have an accept-reject criterion. 17) a project costing $1000 and returning $450 annually for three will have a npv> $0 if the discount rate is =15% 18) If the...
Internal rate of return is calculated by: A. Finding the discount rate that forces the NPV...
Internal rate of return is calculated by: A. Finding the discount rate that forces the NPV of the project to zero. B. Adjusting the initial outlay of the project so that it is equal to the discounted cash flows. C. Adjusting the inflow until the NPV is zero. D. All of the above. E. None of the above.
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT