A project has cash flows of –$148,400, $42,500, $83,200, and $42,600 for Years 0 to 3, respectively. The required rate of return is 6 percent. Based on the internal rate of return of _____ percent for this project, you should _____ the project. Multiple Choice
6.96; accept
6.55; accept
6.96; reject
6.55; reject
8.12; accept
First we will calculate npv at 2 discount rates
Year | cash flows | discount @ 6% | discount @ 7% | DCF@6% | DCF@7% |
0 | -148400 | 1 | 1 | -148400 | -148400 |
1 | 42500 | 0.94339 | 0.9345 | 40094.075 | 39716.25 |
2 | 83200 | 0.8899 | 0.8734 | 74039.68 | 72666.88 |
3 | 42600 | 0.8396 | 0.8162 | 35766.96 | 34770.12 |
npv | 1500.715 | -1246.75 |
irr can be calculated using interpolation method
formula is
Lower rate +[ NPV at lower rate / (NPV at lower rate - NPV at higher rate)] * ( Higher rate - Lowe rate)
6%+(1500.715)/(1500.715+1246.75) =6.5462
so irr is 6.5462
answer is 6.55 accept
as irr is moore than required return we should accept the project
Get Answers For Free
Most questions answered within 1 hours.