Calculate the profitability index for the below projects and indicate your order of choices.
Project
Present Value
Investment
A
$175,000
$125,000
B
$160,000
$110,000
C
$180,000
$130,000
Select one:
a. B, C and A
b. C, A and B
c. B, A and C
d. A, C and B
Profitability index = Present value of. cashflows/initial investment
Calculation of profitability index of project A:
Given present value of cashflows= $175,000
Initial investment = $125,000
Profitability index = $175,000/$125,000
. = 1.4
Calculation of profitability index of project B:
Given present value of cashflows = $160,000
Initial investment = $110,000
Profitability index = 1.45
Calculation of profitability index of project B:
Given present value of cashflows= $180,000
Intial investment = $130,000
Profitability index = $180,000/$130,000
. = 1.38
These projects profitability index is more than one, so we should choose the projects in the way that it should yield more value to the company. Project with high profitability index gives more value to the company so order of the projects is B (PI 1.45), A(1.40), C (1.38)
So option 'C' is correct.