Question

Here are the expected net cash flow estimates (in thousands of dollars): Year Project L Project...

Here are the expected net cash flow estimates (in thousands of dollars):

Year

Project L

Project S

0

($100)

($100)

1

20

80

2

80

60

3

90

30

Depreciation, salvage values, net working capital requirements, and tax effects are all included in these cash flows.

The company's chief financial officer made subjective risk assessments of each project and concluded that both projects have risk characteristics similar those of the firm as a whole. Unilate's required rate of return is 6 percent. You must now determine whether one or both of the projects should go forward.

  1. Find the payback periods for Project L and Project S.
  1. What is each project's NPV and IRR?  
  1. Which project would you select and why?
  1. What if project S was riskier than project L and had a required return of 10%. Which project would you select now and why?

Homework Answers

Answer #1

Payback period for project L:

Year Opening Balance Investment CF Closing Balance
0 $               100.00 $               100.00
1 $                  100.00 $                            20.00 $                  80.00
2 $                    80.00 $                            80.00 $                         -  
  • Closing balance = Opening balance +Investment - CF
  • Opening balance = previous year's closing balance
  • Closing balance in year 1 was 80 and Cf in year 2 was 80 so the payback period is 2 years
  • According to this method, project S is better

Payback period for project K:

Year Opening Balance Investment CF Closing Balance
0 $               100.00 $               100.00
1 $                  100.00 $                            80.00 $                  20.00
2 $                    20.00 $                            60.00 $                -40.00

Closing balance in year 1 was 20 and CF in year 2 was 60 so sometime during the year, entire investment was recovered. The proportion of the year = 20/60 = 1/3 or 4 months. So the payback period is 1 year 4 months

NPV of the two projects is calculated below:

Year CF Discount Factor Discounted CF
0 $ -100.00 1/(1+0.06)^0= 1 1*-100= $ -100.00
1 $     20.00 1/(1+0.06)^1= 0.943396226 0.943396226415094*20= $     18.87
2 $     80.00 1/(1+0.06)^2= 0.88999644 0.88999644001424*80= $     71.20
3 $     90.00 1/(1+0.06)^3= 0.839619283 0.839619283032302*90= $     75.57
NPV = Sum of all Discounted CF $     65.63
Year CF Discount Factor Discounted CF
0 $ -100.00 1/(1+0.06)^0= 1 1*-100= -100.00
1 $     80.00 1/(1+0.06)^1= 0.943396226 0.943396226415094*80=       75.47
2 $     60.00 1/(1+0.06)^2= 0.88999644 0.88999644001424*60=       53.40
3 $     30.00 1/(1+0.06)^3= 0.839619283 0.839619283032302*30=       25.19
NPV = Sum of all Discounted CF       54.06

According to this method, project L is better as it has a higher NPV

IRR is the rate at which the NPV = 0 and can be calculated using a financial calculator or excel

Project L IRR comes to 32.12% rounded to 2 decimal places

Year CF Discount Factor Discounted CF
0 $ -100.00 1/(1+0.321155807484115)^0= 1 1*-100= $ -100.00
1 $     20.00 1/(1+0.321155807484115)^1= 0.756912996 0.756912995677857*20= $     15.14
2 $     80.00 1/(1+0.321155807484115)^2= 0.572917283 0.572917283026028*80= $     45.83
3 $     90.00 1/(1+0.321155807484115)^3= 0.433648537 0.43364853697085*90= $     39.03
NPV = Sum of all Discounted CF $        0.00

Project S has an IRR of 38.80%

Year CF Discount Factor Discounted CF
0 $ -100.00 1/(1+0.387997201618571)^0= 1 1*-100=      -100.00
1 $     80.00 1/(1+0.387997201618571)^1= 0.720462548 0.720462547643382*80=          57.64
2 $     60.00 1/(1+0.387997201618571)^2= 0.519066283 0.519066282556792*60=          31.14
3 $     30.00 1/(1+0.387997201618571)^3= 0.373967816 0.373967816326646*30=          11.22
NPV = Sum of all Discounted CF            0.00

Project S with higher IRR should be chosen

When different approaches give different selection then we always go with the NPV decision rule which says we should select project L

d) We actually dont need to calculate the NPV as at 6% only the NPV of S was lower so at 10% it will be even lower and we will still go with project L but to verify, we have calculated the NPV as follows:

Year CF Discount Factor Discounted CF
0 $ -100.00 1/(1+0.1)^0= 1 1*-100=      -100.00
1 $     80.00 1/(1+0.1)^1= 0.909090909 0.909090909090909*80=          72.73
2 $     60.00 1/(1+0.1)^2= 0.826446281 0.826446280991735*60=          49.59
3 $     30.00 1/(1+0.1)^3= 0.751314801 0.751314800901578*30=          22.54
NPV = Sum of all Discounted CF          44.85

As it is lower than that of project L so project L should be selected

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Your boss, the chief financial officer (CFO) for Southern Textiles, has just handed you the estimated...
Your boss, the chief financial officer (CFO) for Southern Textiles, has just handed you the estimated cash flows for two proposed projects. Project L involves adding a new item to the firm’s fabric line. It would take some time to build up the market for this product, so the cash inflows would increase over time. Project S involves an add-on to an existing line, and its cash flows would decrease over time. Both projects have 3-year lives because Southern is...
PAYBACK PERIOD Project L costs $70,000, its expected cash inflows are $15,000 per year for 11...
PAYBACK PERIOD Project L costs $70,000, its expected cash inflows are $15,000 per year for 11 years, and its WACC is 10%. What is the project's payback? Round your answer to two decimal places. b) CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$350 $75 $75 $75 $225 $225 Project 2 -$500 $200 $200 $50 $50 $50 Which project would...
Project L requires an initial outlay at t = 0 of $50,000, its expected cash inflows...
Project L requires an initial outlay at t = 0 of $50,000, its expected cash inflows are $15,000 per year for 9 years, and its WACC is 9%. What is the project's MIRR? Do not round intermediate calculations. Round your answer to two decimal places. = % Project S requires an initial outlay at t = 0 of $12,000, and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay...
Project S costs $19,000 and its expected cash flows would be $6,500 per year for 5...
Project S costs $19,000 and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L costs $32,000 and its expected cash flows would be $8,850 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. a. Project L, since the NPVL > NPVS. b. Both Projects S and L, since both projects have NPV's > 0 . c. Both Projects S and...
Project S costs $12,000 and its expected cash flows would be $5,500 per year for 5...
Project S costs $12,000 and its expected cash flows would be $5,500 per year for 5 years. Mutually exclusive Project L costs $26,000 and its expected cash flows would be $11,500 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have NPV's > 0. b. Project S, since the NPVS > NPVL. c. Neither Project S nor L,...
Project S costs $13,000 and its expected cash flows would be $5,000 per year for 5...
Project S costs $13,000 and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L costs $34,500 and its expected cash flows would be $11,100 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Both Projects S and L, since both projects have NPV's > 0. c. Both Projects S and L,...
Project S costs $19,000 and its expected cash flows would be $6,000 per year for 5...
Project S costs $19,000 and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L costs $38,500 and its expected cash flows would be $14,700 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Project L, since the NPVL > NPVS. c. Both Projects S and L, since both projects have IRR's...
Project S costs $18,000 and its expected cash flows would be $7,000 per year for 5...
Project S costs $18,000 and its expected cash flows would be $7,000 per year for 5 years. Mutually exclusive Project L costs $35,000 and its expected cash flows would be $8,400 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Neither Project S nor L, since each project's NPV < 0. c. Both Projects S and L, since...
Project S costs $13,000 and its expected cash flows would be $7,000 per year for 5...
Project S costs $13,000 and its expected cash flows would be $7,000 per year for 5 years. Mutually exclusive Project L costs $41,500 and its expected cash flows would be $10,500 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have IRR's > 0. b. Project S, since the NPVS > NPVL. c. Both Projects S and L,...
Project S costs $11,000 and its expected cash flows would be $7,000 per year for 5...
Project S costs $11,000 and its expected cash flows would be $7,000 per year for 5 years. Mutually exclusive Project L costs $38,000 and its expected cash flows would be $13,300 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Project L, since the NPVL > NPVS. b. Neither Project S nor L, since each project's NPV < 0. c. Both Projects S and L, since...