Question

1.      Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown...

1.      Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown as follows. The required rate of return on projects of both of their risk class is 10 percent, and the maximum allowable payback and discounted payback statistic for the projects are two and a half and three and a half years, respectively.

Time

0

1

2

3

Project A Cash Flow

?1,000

300

400

700

Project B Cash Flow

?500

200

400

300

Use the NPV decision rule to evaluate these projects; which one(s) should be accepted or rejected?

A.      ACCEPT BOTH A AND B

B.       ACCEPT NEITHER A NOR B

C.       ACCEPT A, REJECT B

D.      REJECT A, ACCEPT B

Homework Answers

Answer #1

Present value of inflows=cash inflow*Present value of discounting factor(rate%,time period)

A:

Present value of inflows=300/1.1+400/1.1^2+700/1.1^3

=$1129.23

NPV=Present value of inflows-Present value of outflows

=$1129.23-$1000

=$129.23(Approx)

B:

Present value of inflows=200/1.1+400/1.1^2+300/1.1^3

=$737.79

NPV=Present value of inflows-Present value of outflows

=$737.79-$500

=$237.79(Approx)

Hence since projects are mutually exlcusive;project having highest NPV must be chosen.Hence project B must be accepted and A rejected.(D)

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
1.      Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown...
1.      Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown as follows. The required rate of return on projects of both of their risk class is 10 percent, and the maximum allowable payback and discounted payback statistic for the projects are two and a half and three and a half years, respectively. Time 0 1 2 3 Project A Cash Flow ?1,000 300 400 700 Project B Cash Flow ?500 200 400 300 Use...
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 10 percent, and the maximum allowable payback and discounted payback statistic for the projects are 2.5 and 3.5 years, respectively.   Time: 0 1 2 3   Project A Cash Flow -1,000 300 400 700   Project B Cash Flow -500 200 400 300 Use the payback decision rule to evaluate these projects;...
1.      Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown...
1.      Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown as follows. The required rate of return on projects of both of their risk class is 10 percent, and the maximum allowable payback and discounted payback statistic for the projects are two and a half and three and a half years, respectively. Time 0 1 2 3 Project A Cash Flow ?1,000 300 400 700 Project B Cash Flow ?500 200 400 300 Use...
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 9 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively.   Time: 0 1 2 3   Project A Cash Flow -21,000 11,000 31,000 2,000   Project B Cash Flow -31,000 11,000 21,000 51,000 Use the NPV decision rule to evaluate these...
1.      Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown...
1.      Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown as follows. The required rate of return on projects of both of their risk class is 8 percent, and the maximum allowable payback and discounted payback statistic for the projects are two and three years, respectively. Time 0 1 2 3 Project A Cash Flow ?20,000 10,000 30,000 1,000 Project B Cash Flow ?30,000 10,000 20,000 50,000 Use the MIRR decision rule to evaluate...
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 8 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively.   Time: 0 1 2 3   Project A Cash Flow -30,000 20,000 40,000 11,000   Project B Cash Flow -40,000 20,000 30,000 60,000 Use the NPV decision rule to evaluate these...
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown as...
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown as follows. The required rate of return on projects of both of their risk class is 8 percent, and the maximum allowable payback and discounted payback statistic for the projects are two and three years, respectively. Time 0 1 2 3 Project A Cashflow -20,000 10,000 30,000 1,000 Project B Cashflow -30,000 10,000 20,000 50,000 Calculate the NPV and use the NPV decision rule to...
19. Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown...
19. Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 10 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively.   Time: 0 1 2 3   Project A Cash Flow -32,000 22,000 42,000 13,000   Project B Cash Flow -42,000 22,000 8,000 62,000 Use the payback decision rule to evaluate...
1.     Suppose your firm is considering two independent projects with the cash flows shown as follows....
1.     Suppose your firm is considering two independent projects with the cash flows shown as follows. The required rate of return on projects of both of their risk class is 12 percent, and the maximum allowable payback and discounted payback statistic for the projects are two and a half and three years, respectively. Time 0 1 2 3 Project A Cash Flow ?5,000 1,000 3,000 5,000 Project B Cash Flow ?10,000 5,000 5,000 5,000 Use the payback decision rule to...
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below....
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 12 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively.   Time: 0 1 2 3   Project A Cash Flow -29,000 19,000 39,000 10,000   Project B Cash Flow -39,000 19,000 29,000 59,000 Use the PI decision rule to evaluate these...