Project Max has an NPV of $875,000 and will last 13 years. Project Span has an NPV of $1,225,000 and will last 17 years. Both projects have a required rate of return of 15%. Assuming that these projects can be replicated over and over again once completed, and that only one of the two can be accepted, which project would you recommend?

Homework Answers

Answer #1
Answer
Project Max
NPV $    875,000.00
Period 13 Years
Required rate 15%
Equivalent Annual Benefit NPV/ Annuity Factor
875000/(((1-(1.15)^-13))/0.15)
$    156,721.65
Project Span
NPV $ 1,225,000.00
Period 17 Years
Required rate 15%
Equivalent Annual Benefit NPV/ Annuity Factor
1225000/(((1-(1.15)^-17))/0.15)
$    202,574.41
Since EAB of Project span ($202,574) is more than project Max($156,721)
Project Span should be Accepted
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Project A has an IRR of 15%. Project B has an IRR of 13%. Both projects...
Project A has an IRR of 15%. Project B has an IRR of 13%. Both projects have a cost of capital of 12%. Which of the following statements would be correct? A. Both projects have a positive NPV. True or False? Explain B. Project A must have a higher NPV than Project B, True or False? Explain. C. If Project B has a higher NPV when cost of capital is 8%, then Project B must also have higher NPV if...
CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's...
CAPITAL BUDGETING CRITERIA A firm with a 13% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$27,000 $9,000 $9,000 $9,000 $9,000 $9,000 Project N -$81,000 $25,200 $25,200 $25,200 $25,200 $25,200 Calculate NPV for each project. Round your answers to the nearest cent. Do not round your intermediate calculations. Project M    $ Project N    $ Calculate IRR for each project. Round your answers to two...
Calculate the NPV of a project that has an outlay of $200,000 and has annual net...
Calculate the NPV of a project that has an outlay of $200,000 and has annual net cash flows of $50000 per year over 6 years. The project has a salvage value (disposal value) of 10% of its original value. The required rate of return for projects of similar risk is 0.1. Note that the rate of return is quoted as a decimal, e.g. 12% p.a. is written as .12 in the question above. Your answer must be accurate to the...
Project A has an internal rate of return (IRR) of 15 percent. Project B has an...
Project A has an internal rate of return (IRR) of 15 percent. Project B has an IRR of 14 percent. Both projects have a required return of 12 percent. Which of the following statements is most correct? a. Both projects have a positive net present value (NPV). b. Project A must have a higher NPV than project B. c. If the required return were less than 12 percent, Project B would have a higher IRR than Project A. d. Project...
Project A has a net present value of $1,500, a payback period of 2 years, and...
Project A has a net present value of $1,500, a payback period of 2 years, and an internal rate of return of 12%.  Project B has a net present value of $1,800, a payback period of 4 years, and an internal rate of return of 10%.  Project C has a netpresent value of $1,750, a payback period of 3 years, and an internal rate of return of 11%.  If the projects are mutually exclusive, which project should be undertaken? A. Project A because...
You are considering a project that you think might create value for your firm. The finance...
You are considering a project that you think might create value for your firm. The finance department has told you that the required rate of return is 13% and only projects with a NPV of $3000 or greater will be accepted. You do your calculations and find that the IRR of the project would be exactly 13%. Will the finance department accept this project? Select one: a. Yes b. No c. One cannot determine without calculating the NPV of the...
Questions 13-16 refer to the following information. There are two independent investment projects for the Galactic...
Questions 13-16 refer to the following information. There are two independent investment projects for the Galactic Empire. Project A (build TIE Fighters) costs the Empire $300,000 to set up, and it will provide annual cash inflows of $70,000 for 7 years. Project B (build Death Star) costs the Empire $1,000,000 to set up, and it will provide annual cash inflows of $255,000 for 6 years. The Empire’s cost of capital (i.e., the required return on investment) is 10% annually, and...
NPV and IRR   Benson Designs has prepared the following estimates for a​ long-term project it is...
NPV and IRR   Benson Designs has prepared the following estimates for a​ long-term project it is considering. The initial investment is ​$84 comma 600​, and the project is expected to yield​ after-tax cash inflows of ​$9 comma 000per year for 15years. The firm has a cost of capital of 13​%. a.  Determine the net present value​ (NPV) for the project. b.  Determine the internal rate of return​ (IRR) for the project. c.  Would you recommend that the firm accept or...
A company has the option to invest in project A, project B, or neither (the projects...
A company has the option to invest in project A, project B, or neither (the projects are mutually exclusive and the company has no other investment options). Project A requires an initial investment of $100,000 today and provides cash flows of $35,000 a year for five years. The project will also return back $20,000 in capital in year six. Project B requires a $135,000 investment today and will have cash flows of $40,000 a year for 5 years. The firm’s...
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax...
A firm with a 14% WACC is evaluating two projects for this year's capital budget. After-tax cash flows, including depreciation, are as follows: 0 1 2 3 4 5 Project M -$9,000 $3,000 $3,000 $3,000 $3,000 $3,000 Project N -$27,000 $8,400 $8,400 $8,400 $8,400 $8,400 Calculate NPV for each project. Do not round intermediate calculations. Round your answers to the nearest cent. Project M:    $   Project N:    $   Calculate IRR for each project. Do not round intermediate calculations. Round your answers to...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT