Question

YEAR   PROJECT A CASH FLOW   PROJECT B CASH FLOW 0 -110,000 -110,000 1 30,000 0 2...

YEAR   PROJECT A CASH FLOW   PROJECT B CASH FLOW
0 -110,000 -110,000
1 30,000 0
2 30,000 0
3 30,000 0
4 30,000 0
5 30,000 230,000

(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: If the appropriate discount rate on these projects is 12 ​percent, which would be chosen and​ why?

Homework Answers

Answer #1

A:

Present value of annuity=Annuity[1-(1+interest rate)^-time period]/rate

=$30,000[1-(1.12)^-5]/0.12

=$30,000*3.604776202

=$108,143.29

NPV=Present value of inflows-Present value of outflows

=$108,143.29-$110,000

=($1856.71)(Approx)(Negative).

B:

Present value of inflows=cash inflow*Present value of discounting factor(rate%,time period)

=230,000/1.12^5

=230,000*0.567426855

=$130508.18

NPV=Present value of inflows-Present value of outflows

=$130508.18-$110,000

=$20508.18(Approx).

Hence B must be selected having higher and positive NPV.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
You have been assigned the task of evaluating two mutually exclusive projects with the following projected...
You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: Year Project A cash flow Project B cash flow 0 ​$(110,000​) ​$(110,000​) 1    30,000            00 2    30,000            00 3    30,000            00 4    30,000            00 5   30,000   230,000 If the appropriate discount rate on these projects is 8​%, which would be chosen and​ why?
​(Mutually exclusive projects and​ NPV)  You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and​ NPV)  You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: Year Project A Cash Flow Project B Cash Flow 0 ​$(102,000​) ​$(102,000​) 1    30,000            00 2   30,000            00 3   30,000            00 4    30,000            00 5    30,000   210,000 If the appropriate discount rate on these projects is 11 ​percent, which would be chosen and​ why? The NPV of Project B is $nothing.​(Round to the nearest​ cent.)
(Mutually exclusive projects and​ NPV)  You have been assigned the task of evaluating two mutually exclusive...
(Mutually exclusive projects and​ NPV)  You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: Year Project A Cash Flow Project B Cash Flow 0 ​$(90,000​) ​$(90,000​) 1    32,000            0 2    32,000            0 3    32,000            0 4    32,000            0 5    32,000   240,000 If the appropriate discount rate on these projects is 9 ​percent, which would be chosen and​ why? The NPV of Project A is ​$ _______. ​(Round to the nearest​ cent.)
You have been assigned the task of evaluating two mutually exclusive projects with the following projected...
You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows:If the appropriate discount rate on these projects is 11 ​percent, which would be chosen and​ why? YEAR   PROJECT A CASH FLOW   PROJECT B CASH FLOW 0   -105,000   -105,000 1   37,000   0 2   37,000   0 3   37,000   0 4   37,000   0 5   37,000   230,000
Before whoever decides to answer the following problems, please DO NOT use excel. I have posted...
Before whoever decides to answer the following problems, please DO NOT use excel. I have posted this question already, and the expert answered using excel to solve this problem. I am not good with excel at all so I did not understand what was given. Would rather have the problem worked out showing the formula and work broken down and written out. Thank you in advance. You have been assigned the task of evaluating two mutually exclusive projects with the...
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0...
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0 –$ 61,000 –$ 76,000 1 41,000 40,000 2 36,000 49,000 3 31,000 52,000    The cash flows of Project A are expressed in real terms while those of Project B are expressed in nominal terms. The appropriate nominal discount rate is 12 percent and the inflation rate is 3 percent.    Calculate the NPV for each project. (Do not round intermediate calculations and round...
Consider the following two mutually exclusive projects: Year 0 Cash Flow(X) - $19,200 Cash Flow(Y) -$19,200...
Consider the following two mutually exclusive projects: Year 0 Cash Flow(X) - $19,200 Cash Flow(Y) -$19,200 Year 1 Cash Flow(X) 8,650 Cash Flow(Y) 9,700 Year 2 Cash Flow(X) 8,700 Cash Flow(Y) 7,600 Year 3 Cash Flow (X) 8,600 Cash Flow (Y) 8,500 A.) Calculate the IRR for each project. Project X ___% Project Y ___% B.) What is the crossover rate for these two projects? C.) What is the NPV of Projects X and Y at discount rates of 0...
3. A project has an initial cost of $30,000 and a 3-year life. The company uses...
3. A project has an initial cost of $30,000 and a 3-year life. The company uses straight-line depreciation to a book value of zero over the life of the project. The projected average net income from the project is $1,766.67 per year for the next 3 years, respectively. What is the accounting rate of return based on average investment? A. 11.78 percent B. 14.69 percent C. 8.72 percent D. 11.04 percent 4. You are considering two mutually exclusive projects with...
A company has the following mutually exclusive projects. Year     Project A          Project B 0         -$15,300      &
A company has the following mutually exclusive projects. Year     Project A          Project B 0         -$15,300           -$10,700 1              8,700                5,300 2              7,400                4,300 3              3,100                4,800 ------------------------------------------------ a. Suppose the company's payback cutoff is two years. Which of these two projects should be chosen? b. Suppose the company uses the NPV rule to rank these two projects. Which projects should be chosen if the appropriate discount rate is 15 percent? ( show your work)
Novell, Inc., has the following mutually exclusive projects.    Year Project A Project B   0 –$27,000...
Novell, Inc., has the following mutually exclusive projects.    Year Project A Project B   0 –$27,000    –$30,000      1 15,500    16,500      2 12,000    10,500      3 3,600    12,000       a-1. Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 3 decimal places, e.g., 32.161.)        a-2. If the company's payback period is two years, which, if either, of these projects should be chosen? Project A Project...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT