Question

A company is considering a project which has an initial startup cost of $783,534. The firm...

A company is considering a project which has an initial startup cost of $783,534. The firm maintains a debt-to-equity ratio of 1.10. The flotation cost of debt is 8.45% and the flotation cost of external equity is 12.63%. The firm has sufficient internally generated equity to cover the equity cost of this project. What is the initial cost of the project including the flotation costs? $797,759 $818,215 $838,670 $859,125 $879,581

Homework Answers

Answer #1

Total Capital = $ 783534

Debt-equity ratio= 1.10

Let us suppose we raise $ 2.10 then we would have to raise $ 1 from Equity and $ 1.10 from debt.

Equity portion = total capital to be raised * Equity ratio/( Equity + Debt)

= 783534 * 1/(1+1.10) = 783534/2.10 = $ 373111.40

Same way debt portion = 783534 * 1.10/(1+1.10) = $ 410422.60

Now since our equity is internally generated there will not be any floatation cost for equity, But the debt would have the floatation cost.

Floatation cost of debt is 8.45%

So Debt to be raised = Amount required for investment * (1+Floatation cost %)

= 410422.60 * (1+8.45%)

= $ 445103.30

So total cost of the project is

373111.40 + 445103.30

$ 818214.71 or $ 818215

So 2nd option is the correct answer.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A company is considering a project which has an initial startup cost of $783,534. The firm...
A company is considering a project which has an initial startup cost of $783,534. The firm maintains a debt-to-equity ratio of 1.10. The flotation cost of debt is 8.45% and the flotation cost of external equity is 12.63%. The firm has sufficient internally generated equity to cover the equity cost of this project. What is the initial cost of the project including the flotation costs? $797,759 $818,215 $838,670 $859,125 $879,581
A company is considering a project which has an initial startup cost of $787,050. The firm...
A company is considering a project which has an initial startup cost of $787,050. The firm maintains a debt-to-equity ratio of 1.15. The flotation cost of debt is 8.66% and the flotation cost of external equity is 12.86%. The firm has sufficient internally generated equity to cover the equity cost of this project. What is the initial cost of the project including the flotation costs? $802,919 $823,507 $844,095 $864,682 $885,270
A company is considering a project which has an initial startup cost of $781,270. The firm...
A company is considering a project which has an initial startup cost of $781,270. The firm maintains a debt-to-equity ratio of 1.12. The flotation cost of debt is 8.42% and the flotation cost of external equity is 12.62%. The firm has sufficient internally generated equity to cover the equity cost of this project. What is the initial cost of the project including the flotation costs? Question 1 options: $775,222 $795,623 $816,023 $836,424 $856,824
You are considering a project which requires $136,000 in external financing. The flotation cost of equity...
You are considering a project which requires $136,000 in external financing. The flotation cost of equity is 11 % and the cost of debt is 4.5 %. You wish to maintain a debt-equity ratio of.45. What is the initial cost of the project including the flotation costs? Multiple Choice $138,009 $143,367 $155,283 $154,004 $149,422
Comedy, Inc. has a debt-equity ratio of 0.54. The firm is analyzing a new project which...
Comedy, Inc. has a debt-equity ratio of 0.54. The firm is analyzing a new project which requires an initial cash outlay of $430,000 for equipment. The flotation cost is 8.6 percent for equity and 5 percent for debt. What is the initial cost of the project including the flotation costs?
•Your company is considering a project that will cost $1 million. Thefirm’s target D/E ratio is...
•Your company is considering a project that will cost $1 million. Thefirm’s target D/E ratio is .6 The flotation cost for equity is 5%, and the flotation cost for debt is 3%. What is the flotation costs? •fA=
5.A firm has a target debt/equity ratio of 2 and is considering a new investment project....
5.A firm has a target debt/equity ratio of 2 and is considering a new investment project. The project would cost $1M to undertake but the firm has only $250,000 in retained earnings. The remaining $750,000 will be raised by selling bonds. The flotation costs of selling bonds are 5%. The flotation costs of issuing new equity are 12%. The firm has a policy of using only internal financing or debt (or both) for new projects. What is the weighted average...
Alpha Industries is considering a project with an initial cost of $9.7 million. The project will...
Alpha Industries is considering a project with an initial cost of $9.7 million. The project will produce cash inflows of $1.67 million per year for 9 years. The project has the same risk as the firm. The firm has a pretax cost of debt of 6.12 percent and a cost of equity of 11.61 percent. The debt–equity ratio is .77 and the tax rate is 40 percent. What is the net present value of the project?
Alpha Industries is considering a project with an initial cost of $9.1 million. The project will...
Alpha Industries is considering a project with an initial cost of $9.1 million. The project will produce cash inflows of $2.13 million per year for 6 years. The project has the same risk as the firm. The firm has a pretax cost of debt of 6.15 percent and a cost of equity of 11.63 percent. The debt–equity ratio is .78 and the tax rate is 35 percent. What is the net present value of the project?
Alpha Industries is considering a project with an initial cost of $8.4 million. The project will...
Alpha Industries is considering a project with an initial cost of $8.4 million. The project will produce cash inflows of $1.64 million per year for 8 years. The project has the same risk as the firm. The firm has a pretax cost of debt of 5.73 percent and a cost of equity of 11.35 percent. The debt–equity ratio is .64 and the tax rate is 39 percent. What is the net present value of the project?
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT