A company is considering a project which has an initial startup cost of $783,534. The firm maintains a debt-to-equity ratio of 1.10. The flotation cost of debt is 8.45% and the flotation cost of external equity is 12.63%. The firm has sufficient internally generated equity to cover the equity cost of this project. What is the initial cost of the project including the flotation costs? $797,759 $818,215 $838,670 $859,125 $879,581
Total Capital = $ 783534
Debt-equity ratio= 1.10
Let us suppose we raise $ 2.10 then we would have to raise $ 1 from Equity and $ 1.10 from debt.
Equity portion = total capital to be raised * Equity ratio/( Equity + Debt)
= 783534 * 1/(1+1.10) = 783534/2.10 = $ 373111.40
Same way debt portion = 783534 * 1.10/(1+1.10) = $ 410422.60
Now since our equity is internally generated there will not be any floatation cost for equity, But the debt would have the floatation cost.
Floatation cost of debt is 8.45%
So Debt to be raised = Amount required for investment * (1+Floatation cost %)
= 410422.60 * (1+8.45%)
= $ 445103.30
So total cost of the project is
373111.40 + 445103.30
$ 818214.71 or $ 818215
So 2nd option is the correct answer.
Get Answers For Free
Most questions answered within 1 hours.