The budget exhibit that provides justification for a particular project under RDT&E program element is the:
A. R-3
B. R-4
C. R-1
D. R-2a
The budget exhibit that provides that provides justification for a particular project under each program element is :-
1.) R-2a
The R-2 provides summary funding information, program justification and budget justification for each RDT & E program element. For a program element with more than one project, a similar form R-2 A is prepared for each project.
the rest of exhibits referred have some other attributes