Question

Capital Budgeting BioMed Engineering is considering two mutually exclusive investments. The projects' expected net cash flows...

Capital Budgeting

BioMed Engineering is considering two mutually exclusive investments. The projects' expected net cash flows are as follows:                                                                                                      

                        Expected Net Cash Flows                                                                                   

            Time     Project A          Project B                                                                       

            0          ($405)                ($705)                                                               

            1          ($285)              $200                                                                 

            2          ($205)              $205                                                                 

            3          ($105)              $210                                                                 

            4          $605                 $215                                                                 

            5          $650                 $220                                                                 

            6          $925                 $225                                                                 

            7          ($200)              $230                                                                 

In your report, identify which project would be selected (assuming they are mutually exclusive) for each investment criterion. Note that cash outflows (costs) are given in parenthesis. Employ the Excel file to answer the following questions

Part 1: Net Present Value

  1. Use the Excel NPV function to calculate the NPV for each project at a cost of capital equal to 8%. Note the range of values in the NPV function should not include the initial cost (CF0). Make sure to add this separately. (7 points)
  2. Use the Excel NPV function to calculate the NPV for each project at a cost of capital equal to 16%. Note the range of values in the NPV function should not include the initial cost (CF0). Make sure to add this separately. (7 points)
Part 1:
A) Net Present Value at 8% Cost of Capital
Cost of capital = 8% NPV A =
Cost of capital = 8% NPV B =
B) Net Present Value Project at 16% Cost of Capital
Cost of capital  = 16% NPV A =
Cost of capital  = 16% NPV B =

Homework Answers

Answer #1

NPV needs to be calculated using NPV function in EXCEL

=NPV(rate,Year1 to year7 cashflows)-Year0 cashflow

A. NPV of Project A,8%=NPV(8%,Year1 to Year7 cashflows)-405=$425.29

NPV of project B,8%=NPV(8%,Year1 to Year7 cashflows)-705=$406.40

NPV of Project A>NPV of Project B, hence Project A has to be selected at 8% cost of capital

B. NPV of Project A,16%=NPV(16%,Year1 to Year7 cashflows)-405=$82.20

NPV of project B,16%=NPV(16%,Year1 to Year7 cashflows)-705=$151.52

NPV of Project B>NPV of Project A, hence Project B has to be selected at 16% cost of capital

project A project B
Year0 -405 -705
Year1 -285 200
Year2 -205 205
Year3 -105 210
Year4 605 215
Year5 650 220
Year6 925 225
Year7 -200 230
8% NPV 425.29 406.40
16% NPV 82.20 151.52
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Gardial Fisheries is considering two mutually exclusive investments. The projects' expected net cash flows are as...
Gardial Fisheries is considering two mutually exclusive investments. The projects' expected net cash flows are as follows: Expected Net Cash Flows Time Project A Project B 0 ($375) ($575) 1 ($300) $190 2 ($200) $190 3 ($100) $190 4 $600 $190 5 $600 $190 6 $926 $190 7 ($200) $0 a. If each project's cost of capital is 12%, which project should be selected? If the cost of capital is 18%, what project is the proper choice? @ 12% cost...
If mutually exclusive projects with normal cash flows are being analyzed, the net present value (NPV)...
If mutually exclusive projects with normal cash flows are being analyzed, the net present value (NPV) and internal rate of return (IRR) methods   agree. Projects Y and Z are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. Year Project Y Project Z 0 –$1,500 –$1,500 1 $200 $900 2 $400 $600 3 $600 $300 4 $1,000 $200    If the weighted average cost of capital (WACC) for each project is 14%, do the NPV and...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $15,000 and its expected cash flows would...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $15,000 and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L costs $45,000 and its expected cash flows would be $9,900 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Both Projects S and L, since both projects have NPV's > 0....
Cummings Products Company is considering two mutually exclusive investments whose expected net cash flows are as...
Cummings Products Company is considering two mutually exclusive investments whose expected net cash flows are as follows: EXPECTED NET CASH FLOWS Year Project A Project B 0 -$320 -$360 1 -387 134 2 -193 134 3 -100 134 4 600 134 5 600 134 6 850 134 7 -180 134 What is each project's IRR? Do not round intermediate calculations. Round your answers to two decimal places Calculate the two projects' NPVs, if you were told that each project's cost...
Gore Global is considering the two mutually exclusive projects below. The cash flows from the projects...
Gore Global is considering the two mutually exclusive projects below. The cash flows from the projects are summarized below. Year ManBearPig Project Cash Flow Flying Car Cash Flow 0 -$100,000    -$200,000    1 25,000 50,000 2 25,000 50,000 3 50,000 80,000 4 50,000 100,000 The two projects have the same risk. At what cost of capital would the two projects have the same net present value (NPV)? A. 10.03% B. -24.45% C. 2.86% D. 13.04% E. 15.90%
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $17,000, and its expected cash flows would...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $17,000, and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L costs $30,000, and its expected cash flows would be $8,750 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Explain. Which project would you recommend? Explain.
(Capital Budgeting Criteria: Mutually Exclusive Projects) Project S costs $17,000 and its expected cash flows would...
(Capital Budgeting Criteria: Mutually Exclusive Projects) Project S costs $17,000 and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L costs $28,500 and its expected cash flows would be $11,250 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend? Select the correct answer. a. Project L, since the NPVL > NPVS. b. Both Projects S and L, since both projects have IRR's > 0....
Consider the following cash flows for two mutually exclusive capital investment projects. The required rate of...
Consider the following cash flows for two mutually exclusive capital investment projects. The required rate of return is 15%. Use this Year         Project A Cash Flow        Project B Cash Flow 0                         -$40,000                           -$30,000 1                              12,000                            9,000 2                              12,000                             9,000 3                              12,000                             9,000 4                              10,800      8,100 5                              10,800                              8,100 6                              5,400      8,100 7. What is the profitability index of project B? a) 1.03 b) 1.06 c) .94 d) 1.09 e) 1.117 8. Calculate the net present value of project A. a) $1,564.25 b) $1,227.71 c) $3,802 d) $2,709,21 e) $331.40
Capital budgeting criteria: mutually exclusive projects Project S costs $15,000 and its expected cash flows would...
Capital budgeting criteria: mutually exclusive projects Project S costs $15,000 and its expected cash flows would be $5,500 per year for 5 years. Mutually exclusive Project L costs $40,500 and its expected cash flows would be $10,800 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend? Select the correct answer. I. Both Projects S and L, since both projects have NPV's > 0. II. Project L, since the NPVL > NPVS....
Capital budgeting criteria: mutually exclusive projects Project S costs $11,000 and its expected cash flows would...
Capital budgeting criteria: mutually exclusive projects Project S costs $11,000 and its expected cash flows would be $4,000 per year for 5 years. Mutually exclusive Project L costs $32,000 and its expected cash flows would be $14,700 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend? Select the correct answer. I. Neither S or L, since each project's NPV < 0. II. Project L, since the NPVL > NPVS. III. Project...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT