Question

​RiverRocks, Inc., is considering a project with the following projected free cash​ flows: Year 0 1...

​RiverRocks, Inc., is considering a project with the following projected free cash​ flows:

Year

0

1

2

3

4

Cash Flow

​(in millions)

−$50.6

$10.9

$19.8

$19.4

$14.6

The firm believes​ that, given the risk of this​ project, the WACC method is the appropriate approach to valuing the project.​ RiverRocks' WACC is

12.1%.

Should it take on this​ project? Why or why​ not?

The timeline for the​ project's cash flows​ is: ​(Select the best choice​ below.)

A.The timeline starts at Year 0 and ends at Year 4. It shows cash flows of -$ 50.6 in Year 0, -$ 10.9 in Year 1, -$ 19.8 in Year 2, -$ 19.4 in Year 3, and -$ 14.6 in Year 4. The cash flow amounts are in millions of dollars.

Cash Flows (millions)

−$50.6

−$10.9

−$19.8

−$19.4

−$14.6

Year

0

1

2

3

4

B.The timeline starts at Year 0 and ends at Year 4. It shows cash flows of $ 50.6 in Year 0, -$ 10.9 in Year 1, -$ 19.8 in Year 2, -$ 19.4 in Year 3, and -$ 14.6 in Year 4. The cash flow amounts are in millions of dollars.

Cash Flows (millions)

$50.6

−$10.9

−$19.8

−$19.4

−$14.6

Year

0

1

2

3

4

C.The timeline starts at Year 0 and ends at Year 4. It shows cash flows of negative $ 50.6 in Year 0, $ 10.9 in Year 1, $ 19.8 in Year 2, $ 19.4 in Year 3, and $ 14.6 in Year 4. The cash flow amounts are in millions of dollars.

Cash Flows (millions)

−$50.6

$10.9

$19.8

$19.4

$14.6

Year

0

1

2

3

4

Your answer is correct.

D.The timeline starts at Year 0 and ends at Year 4. It shows cash flows of $ 50.6 in Year 0, $ 10.9 in Year 1, $ 19.8 in Year 2, $ 19.4 in Year 3, and $ 14.6 in Year 4. The cash flow amounts are in millions of dollars.

Cash Flows (millions)

$50.6

$10.9

$19.8

$19.4

$14.6

Year

0

1

2

3

4

The net present value of the project is

​$nothing

million. 

Homework Answers

Answer #1

1. Option C is correct.

2. Use NPV method to arrive at whether the project has to be selected or rejected.

Use NPV function in EXCEL to find the value. If NPV is positive (>0), project has to selected or else it has to be rejected.

=NPV(rate,year1 to Year4 cashflows)-Year0 cashflow

=NPV(12.1%,year1 to Year4 cashflows)-50.6

NPV=-$2.10 million

NPV is negative, hence project has to be rejected

WACC 12.10%
Cashflows
Year0 -50.6
Year1 10.9
Year2 19.8
Year3 19.4
Year4 14.6
NPV -2.10
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
​RiverRocks, Inc., is considering a project with the following projected free cash​ flows: Year 0 1...
​RiverRocks, Inc., is considering a project with the following projected free cash​ flows: Year 0 1 2 3 4 Cash Flow ​(in millions) −$49.3 $10.6 $20.8 $19.7 $15.8 The firm believes​ that, given the risk of this​ project, the WACC method is the appropriate approach to valuing the project.​RiverRocks' WACC is 11.5%. Should it take on this​ project? Why or why​ not? The timeline for the​ project's cash flows​ is: ​(Select the best choice​ below.) A.The timeline starts at Year...
​RiverRocks, Inc., is considering a project with the following projected free cash​ flows: Year 0 1...
​RiverRocks, Inc., is considering a project with the following projected free cash​ flows: Year 0 1 2 3 4 Cash Flow ​(in millions) −$50.2 $9.1 $19.9 $20.8 $14.2 The firm believes​ that, given the risk of this​ project, the WACC method is the appropriate approach to valuing the project.​ RiverRocks' WACC is 11.4 %. What is the net present value of this project in millions??
RiverRocks, Inc., is considering a project with the following projected free cash​ flows: Year 0 1...
RiverRocks, Inc., is considering a project with the following projected free cash​ flows: Year 0 1 2 3 4 Cash Flow ​(in millions) negative $ 50.8−$50.8 $ 9.3$9.3 $ 19.6$19.6 $ 19.3$19.3 $ 14.1$14.1 The firm believes​ that, given the risk of this​ project, the WACC method is the appropriate approach to valuing the project.​ RiverRocks' WACC is 12.6 %12.6%. Should it take on this​ project? Why or why​ not? The net present value of the project is ​$negative 4.791−4.791...
A stand-alone capital project has the following projected cash flows: Year 0 1 2 3 Cash...
A stand-alone capital project has the following projected cash flows: Year 0 1 2 3 Cash flow ($4,000) $1,500 $1,200 $2,395 If the firm's cost of capital is 14%, which of the following statements is true? a.the IRR is greater than the cost of capital and the project should be undertaken b.the project should be rejected because the IRR is 12%, which is less than the project's cost of capital c.the IRR is less than 12% and the project should...
ABC Corporation is considering a project that provides the following cash flows steam: Year 0 1...
ABC Corporation is considering a project that provides the following cash flows steam: Year 0 1 2 3 4 5 Cash flows -$1,000 $375 $425 $250 $110 $100 If WACC is 10%, what is NPV and should the company accept the project? Find IRR, MIRR, payback, and discounted payback period. Considering the following projects. Project Year 0 1 2 3 4 A Cash flows -$100 $35 $35 $35 $35 B Cash flows -$100 $60 $50 $40 $30 Project A has...
ABC Corporation is considering a project that provides the following cash flows steam: Year 0 1...
ABC Corporation is considering a project that provides the following cash flows steam: Year 0 1 2 3 4 5 Cash flows -$1,000 $375 $425 $250 $110 $100 If WACC is 10%, what is NPV, and should the company accept the project? Find IRR, MIRR, payback, and discounted payback period.
Gio's Restaurants is considering a project with the following expected cash? flows: Year Project Cash Flow?...
Gio's Restaurants is considering a project with the following expected cash? flows: Year Project Cash Flow? (millions) 0 ?$(210?) 1 100 2 72 3 100 4 90 If the? project's appropriate discount rate is 11percent, what is the? project's discounted payback? period? The? project's discounted payback period is ____ years? Round to 2 decimal places
A company has a project with the following cash flows (in Millions). The WACC for the...
A company has a project with the following cash flows (in Millions). The WACC for the company is 7.5%. year cash flow 1 $(20,000.00) 0 $2,000.00 2 $ 5,000.00 3 $12,000.00 4 $12,000.00 5 $9,000.00 What is the IRR of this project? A. 10.13% B. 17.55% C. 22.66% D. This project does not have normal cash flows so IRR cannot be calculated
A company is considering a project that has the following cash flows: -1200 in year 0,...
A company is considering a project that has the following cash flows: -1200 in year 0, 400 in year 1, 425 in year 2, 450 in year 3, and 475 in year 4. The WACC is 14%. What is the project’s NPV? A $45.84 B $41.25 C $50.93 D $56.59 E $62.88
Consider a project with the following cash flows: Year 0 -> -$1500 Year 1 -> $200...
Consider a project with the following cash flows: Year 0 -> -$1500 Year 1 -> $200 Year 2 -> $350 Year 3 -> $710 Year 4 -> $500 Year 5 -> $3000 WACC = 6% What is the discounted payback period?
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT