Question

please shows work for the following questions: 2. You also have a second project that will...

please shows work for the following questions:

2. You also have a second project that will also cost 1750 to invest in today, and will generate cash inflows of 300, 500, 590, and 1000 at the end of each of the next four years. If the discount rate is 10%, what is the MIRR and should you accept the project based on the MIRR?

3. You have a third project that will cost 1700 to invest in today, will generate cash flows of 50, 100, 200, and 250 at the end of each of the next four years, with cash flows continuing to grow at a constant rate of 3% starting with the fourth cash flow and continuing forever. If the discount rate is 15%, what is the NPV and should you accept the project based on the NPV?$

Homework Answers

Answer #1

2.We use the formula:  
A=P(1+r/100)^n
where
A=future value
P=present value  
r=rate of interest
n=time period.

Future value of inflows=300*(1.1)^3+500*(1.1)^2+590*(1.1)+1000

=2653.3

MIRR=[Future value of inflows/Present value of outflows]^(1/time period)-1

=[2653.3/1750]^(1/4)-1

=10.97%(Approx)

Hence since MIRR is greater than discount rate;project should be accepted.

3.Value after year 4=(Cash flow for year 4*Growth rate)/(Discount rate-Growth rate)

=(250*1.03)/(0.15-0.03)

=2145.8333(Approx)

Present value of inflows=cash inflow*Present value of discounting factor(rate%,time period)

=50/1.15+100/1.15^2+200/1.15^3+250/1.15^4+2145.8333/1.15^4

=$1620.42(Approx)

NPV=Present value of inflows-Present value of outflows

=1620.42-1700

=$-79.58(Approx)(Negative)

Hence since NPV is negative;project must be rejected.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
4. You have a fourth project that will cost 1700 to invest in one year from...
4. You have a fourth project that will cost 1700 to invest in one year from now, will generate a cash inflow of 150 starting in year three and continuing forever. If the discount rate is 8%, what is the NPV and should you accept the project based on the NPV? Please show all of your work
5. You are considering a project that costs $500 to invest in today, and will pay...
5. You are considering a project that costs $500 to invest in today, and will pay you $100 next year. The cash inflow will grow at a constant rate of 3% per year after year 1, and you will receive cash inflows for 20 years (total including the first year CF). Your discount rate is 16%. What is the NPV of the project? Also, what would the NPV be if the cash inflows continued forever? Show your work.
A capital investment project requires an initial investment of $100 and generates positive cash flows, $50...
A capital investment project requires an initial investment of $100 and generates positive cash flows, $50 and $100, at the end of the first and second years, respectively. (There is no cash flow after the second year) The firm uses a hurdle rate of 15% for projects of similar risk. Determine whether you should accept or reject the project based on NPV. Determine whether you should accept or reject the project based on IRR. Determine whether you should accept or...
You plan to invest $100,000 in a project that will generate $10,000 at t=2 and then...
You plan to invest $100,000 in a project that will generate $10,000 at t=2 and then subsequent payments forever with each one g% bigger than the previous payment. Assume the discount rate is 12.1%. What is the minimum constant rate g that the cash flows would have to grow in order for the project’s cash flows to have a positive NPV? a) 2.0% b)2.9% c)2.7% d)3.2%
Ace Inc. is evaluating two mutually exclusive projects—Project A and Project B. The initial cash outflow...
Ace Inc. is evaluating two mutually exclusive projects—Project A and Project B. The initial cash outflow is $50,000 for each project. Project A results in cash inflows of $15,625 at the end of each of the next five years. Project B results in one cash inflow of $99,500 at the end of the fifth year. The required rate of return of Ace Inc. is 10 percent. Ace Inc. should invest in: a. ​Project B because it has no cash inflows...
What is the NPV of a project that costs $83,000 today and is expected to generate...
What is the NPV of a project that costs $83,000 today and is expected to generate annual cash inflows of $19,000 for the next 7 years. Cost of capital (discount rate) is 14%. Round to the nearest cent.
What is the NPV of a project that costs $100,000 today and is expected to generate...
What is the NPV of a project that costs $100,000 today and is expected to generate annual cash inflows of $15,000 for the next 10 years. Cost of capital (discount rate) is 12%. Round to the nearest cent.
Ace Inc. is evaluating two mutually exclusive projects—Project A and Project B. The initial cash outflow...
Ace Inc. is evaluating two mutually exclusive projects—Project A and Project B. The initial cash outflow is $50,000 for each project. Project A results in cash inflows of $15,625 at the end of each of the next five years. Project B results in one cash inflow of $99,500 at the end of the fifth year. The required rate of return of Ace Inc. is 10 percent. Ace Inc. should invest in: a.Project B because it has no cash inflows in...
1) What is the NPV of a project that costs $89,000 today and is expected to...
1) What is the NPV of a project that costs $89,000 today and is expected to generate annual cash inflows of $18,000 for the next 8 years. Cost of capital (discount rate) is 13%. Round to the nearest cent. 2) What is the Profitability Index of a project that costs $22,000 today and is expected to generate annual cash inflows of $5,000 for the following 7 years. Cost of capital is 9%. Round to two decimal places. 3) A project...
Question 2 (25 marks/Investment Decision Rules and Project Cash Flows) Consider a hypothetical economy that has...
Question 2 (25 marks/Investment Decision Rules and Project Cash Flows) Consider a hypothetical economy that has NO tax. ABC Ltd. is considering investing in a 2-year project which is expected to generate the following year-end cash flows: C1 = $110 million, C2 = $115 million. The yearly discount rate for the project is 10%. The initial cost of the project is $200 million. (a) Compute the profit and NPV of the project. (b) Based on the answer of part (a),...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT