Question

If the net present value of a project is −$10,000, and the net present value of...

If the net present value of a project is −$10,000, and the net present value of leasing for the project is +$12,000, calculate the APV (adjusted present value) of the project.
Group of answer choices

($10,000)

($2,000)

$2,000

$12,000

Homework Answers

Answer #1

Adjusted present value a variant of DCF, is value of the target company if it were entirely fiananced by equity plus the value of the impact of debt financing in terms of the tax benefits as well as bankruptcy cost.

or

APV is the total of present value of (1) cash flows after taxes, (2) interest tax shields and (3) any concession/subsidies on interest cost.

Adjusted Present value = Net present value of a project + net present value of financing/leasing benefits

= -10000 + 12000

= 2000

so the option (C) should be correct.

Please check with your answer and let me know.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Calculate the net present value ​(NPV​) for a 25​-year project with an initial investment of ​$10,000...
Calculate the net present value ​(NPV​) for a 25​-year project with an initial investment of ​$10,000 and a cash inflow of ​$2,000 per year. Assume that the firm has an opportunity cost of 17​%. Comment on the acceptability of the project. The​ project's net present value is ​?. ​(Round to the nearest​ cent.)
Calculate the net present value ?(NPV?) for a 15?-year project with an initial investment of ?$15,000...
Calculate the net present value ?(NPV?) for a 15?-year project with an initial investment of ?$15,000 and a cash inflow of ?$2,000 per year. Assume that the firm has an opportunity cost of 15?%. Comment on the acceptability of the project. The? project's net present value is $ . ?(Round to the nearest? cent.)
If a project has a net present value equal to zero, then: Group of answer choices...
If a project has a net present value equal to zero, then: Group of answer choices the project earns a return exactly equal to the discount rate. the total of the cash inflows must equal the initial cost of the project. a decrease in the project's initial cost will cause the project to have a negative NPV. any delay in receiving the projected cash inflows will cause the project to have a positive NPV. the project's PI must be also...
All else constant, the net present value of a typical investment project increases when: Group of...
All else constant, the net present value of a typical investment project increases when: Group of answer choices The cost of capital increases. Each cash inflow is delayed by one year. The initial investment of a project increases. The cost of capital decreases. All cash inflows occur during the last year of a project’s life instead of periodically throughout the life of the project.
What is the net present value of the following set of cash flows at a discount...
What is the net present value of the following set of cash flows at a discount rate of 10 percent? Time Period Cash Flow 0 -$16,000 1 4,500 2 8,500 3 12,000 Group of answer choices $4,131 $2,783 $9,000
Calculate the Net Present Value (NPV) applying the valuation techniques for the budget of capital of...
Calculate the Net Present Value (NPV) applying the valuation techniques for the budget of capital of the following two projects, assuming a rate of return of 17% per year, computed annually. Assume an initial investment of $ 33,000 for A and $ 40,000 for B. Then Year Project A Project B 1 $ 15,000 $ 11,000 2 $ 12,000 $ 11,000 3 $ 10,000 $ 11,000 4 $ 10,000 $ 11,000 5 $ 9,000 11,000 NPV
When using the Net Present Value method, A project is acceptable if the present value of...
When using the Net Present Value method, A project is acceptable if the present value of benefits equals the present value of outflows. A project is acceptable if the present value of benefits exceeds a specified minimum value. None of the answers provided is correct A project is acceptable if the required rate of return on the project is equal to the cost of the firm’s capital. Projects with positive net present values increase the value of the firm.
When the present value of the cash inflows exceeds the initial cost of a project, then...
When the present value of the cash inflows exceeds the initial cost of a project, then the project should be Group of answer choices accepted because the internal rate of return is positive accepted because the profitability index is less than 1. accepted because the profitability index is negative. accepted because IRR is higher than the discount rate. rejected because the net present value is negative
What is the net present value of a project that requires a $2,000 investment today and...
What is the net present value of a project that requires a $2,000 investment today and returns $800 at the end of the first year and $1,700 at the end of the second year? Assume a discount rate of 10%
No need to show work, Will thumbs up fast. 1.) What is the net present value...
No need to show work, Will thumbs up fast. 1.) What is the net present value of a project that has an initial cost of $40,000 and produces cash inflows of $8,000 a year for 11 years if the discount rate is 15 percent? Group of answer choices $798.48 $1869.69 $1240.23 $2470.01 2.) The Chicken Basket is considering a project with an initial cost of $20,000. The project will produce cashflows of: $6,700 in year 1, $6,300 in year 2,...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT