Question

ABC Co is a company with 15 years of experience and currently implementing project A with...

ABC Co is a company with 15 years of experience and currently implementing project A with expected NPV of 155000 USD and standard deviation of 40000 in its operations. Now the company is thinking of implementing an additional project and considering to invest 40% of its resources into it and to choose between projects B and C. These two projects have the following expected probabilities for NPV

Project B Project C
NPV Probability NPV Probability
135000 0,3 157800 0,35
155000 0,4 147523 0,45
-15000 0,3 -20000 0,2

And also the correlation coefficient between the projects ar as follows:
Correlation coefficients:
A&B A&C
0,21 -0,15

What will your recommendation be if the company's policy is to create lower risk portfolio of projects?

Homework Answers

Answer #1

Expected NPV of B=0.3*135000+0.4*155000+0.3*(-15000)=98000

Expected NPV of C=0.35*157800+0.45*147523+0.2*(-20000)=117615.35

Standard deviation of B=sqrt(0.3*(135000-98000)^2+0.4*(155000-98000)^2+0.3*(-15000-98000)^2)=74437.89358

Standard deviation of C=sqrt(0.35*(157800-117615.35)^2+0.45*(147523-117615.35)^2+0.2*(-20000-117615.35)^2)=68958.60666

Standard deviation of portfolio with B=sqrt((60%*40000)^2+(40%*74437.89358)^2+2*60%*40000*40%*74437.89358*0.21)=41984.44458

Standard deviation of portfolio with C=sqrt((60%*40000)^2+(40%*68958.60666)^2+2*60%*40000*40%*68958.60666*(-0.15))=33737.89445

Choose C as it has lower risk

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
ABC Co is a company with 15 years of experience and currently implementing project A with...
ABC Co is a company with 15 years of experience and currently implementing project A with expected NPV of 155000 USD and standard deviation of 40000 in its operations. Now the company is thinking of implementing an additional project and considering to invest 40% of its resources into it and to choose between projects B and C. These two projects have the following expected probabilities for NPV Project B Project C NPV Probability NPV Probability 135000 0,3 157800 0,35 155000...
I am working on the below problem: Problem 11-15 Risky Cash Flows The Bartram-Pulley Company (BPC)...
I am working on the below problem: Problem 11-15 Risky Cash Flows The Bartram-Pulley Company (BPC) must decide between two mutually exclusive investment projects. Each project costs $7,500 and has an expected life of 3 years. Annual net cash flows from each project begin 1 year after the initial investment is made and have the following probability distributions: PROJECT A PROJECT B Probability Net Cash Flows Probability Net Cash Flows 0.2 $7,000 0.2 $        0   0.6 6,750 0.6 6,750 0.2 8,000...
The Bartram-Pulley Company (BPC) must decide between two mutually exclusive investment projects. Each project costs $6,000...
The Bartram-Pulley Company (BPC) must decide between two mutually exclusive investment projects. Each project costs $6,000 and has an expected life of 3 years. Annual net cash flows from each project begin 1 year after the initial investment is made and have the following probability distributions: PROJECT A PROJECT B Probability Net Cash Flows Probability Net Cash Flows 0.2 $5,000 0.2 $        0   0.6 6,750 0.6 6,750 0.2 8,000 0.2 21,000 BPC has decided to evaluate the riskier project at a...
DEPRECIATION METHODS Charlene is evaluating a capital budgeting project that should last for 4 years. The...
DEPRECIATION METHODS Charlene is evaluating a capital budgeting project that should last for 4 years. The project requires $900,000 of equipment. She is unsure what depreciation method to use in her analysis, straight-line or the 3-year MACRS accelerated method. Under straight-line depreciation, the cost of the equipment would be depreciated evenly over its 4-year life (ignore the half-year convention for the straight-line method). The applicable MACRS depreciation rates are 33%, 45%, 15%, and 7%. The company's WACC is 14%, and...
The Bartram-Pulley Company (BPC) must decide between two mutually exclusive investment projects. Each project costs $6,750...
The Bartram-Pulley Company (BPC) must decide between two mutually exclusive investment projects. Each project costs $6,750 and has an expected life of 3 years. Annual net cash flows from each project begin 1 year after the initial investment is made and have the following probability distributions: Project A Project B Probability Cash Flows Probability Cash Flows 0.2 $5,000 0.2 $        0   0.6 6,750 0.6 6,750 0.2 7,000 0.2 20,000 BPC has decided to evaluate the riskier project at an 11% rate...
What tools could AA leaders have used to increase their awareness of internal and external issues?...
What tools could AA leaders have used to increase their awareness of internal and external issues? ???ALASKA AIRLINES: NAVIGATING CHANGE In the autumn of 2007, Alaska Airlines executives adjourned at the end of a long and stressful day in the midst of a multi-day strategic planning session. Most headed outside to relax, unwind and enjoy a bonfire on the shore of Semiahmoo Spit, outside the meeting venue in Blaine, a seaport town in northwest Washington state. Meanwhile, several members of...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT