Question

3. Assume that we are analyzing a positive net present value project. For this project, which...

3. Assume that we are analyzing a positive net present value project. For this project, which measure would be a more conservative measure of the rate of the return – the internal rate of return or the modified internal rate of return?

Homework Answers

Answer #1

IRR :
IRR is the Rate at which PV of Cash Inflows are equal to PV of Cash Outflows. It assumes that intermediary Cfs are reinvested at IRR only.

IRR = Rate at which least +ve NPV + [ NPV at that Rate / Change in NPV due to 1% inc in disc rate ] * 1%

If IRR > Cost of Capital - Project can be accepted
IRR = Cost of Capital - Indifferebce Point - Project will be accepted / Rejected
IRR < Cost of Capital - Project will be erejected

Modified IRR:

It is similar to IRR. In IRR, we are assumed that intermediary cashflows are reinvested at IRR only. In MIRR, we assume that Intermediary CFs are reinvested at Reinvestment Rate rather than at IRR.

Thus MIRR is More conservative Rate of Ret to evalauate NPV.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Which one of the following statements is correct? Net present value is equal to an investment's...
Which one of the following statements is correct? Net present value is equal to an investment's cash inflows discounted to today's dollars. The net present value is positive when the required return exceeds the internal rate of return. The net present value is a measure of profits expressed in today's dollars. If the internal rate of return equals the required return, the net present value will equal zero. If the initial cost of a project is increased, the net present...
explain net present value relative to the internal rate of return is superior measure in project...
explain net present value relative to the internal rate of return is superior measure in project valuation
Project A has a net present value of $1,500, a payback period of 2 years, and...
Project A has a net present value of $1,500, a payback period of 2 years, and an internal rate of return of 12%.  Project B has a net present value of $1,800, a payback period of 4 years, and an internal rate of return of 10%.  Project C has a netpresent value of $1,750, a payback period of 3 years, and an internal rate of return of 11%.  If the projects are mutually exclusive, which project should be undertaken? A. Project A because...
When using the Net Present Value method, A project is acceptable if the present value of...
When using the Net Present Value method, A project is acceptable if the present value of benefits equals the present value of outflows. A project is acceptable if the present value of benefits exceeds a specified minimum value. None of the answers provided is correct A project is acceptable if the required rate of return on the project is equal to the cost of the firm’s capital. Projects with positive net present values increase the value of the firm.
The internal rate of return is the discount rate at which the net present value is...
The internal rate of return is the discount rate at which the net present value is Select one: a. positive. b. There is no relationship between these two concepts. c. equal to zero. d. negative.
Assume the following cash flows for Project A: Year 0 =$(10,000); Year 1 = $4,000; Year...
Assume the following cash flows for Project A: Year 0 =$(10,000); Year 1 = $4,000; Year 2 = $3,500; Year 3 = $1,500; Year 4 = $3,000; and Year 5 = $1,500. The company’s hurdle rate is 9.00%. For Project A, please calculate: 1) the discounted payback period; 2) the net present value; 3) the internal rate of return; and 4) the modified internal rate of return.
13) Assume the following cash flows for Project A: Year 0 =$(10,000); Year 1 = $4,000;...
13) Assume the following cash flows for Project A: Year 0 =$(10,000); Year 1 = $4,000; Year 2 = $3,500; Year 3 = $1,500; Year 4 = $3,000; and Year 5 = $1,500. The company’s hurdle rate is 9.00%. For Project A, please calculate: 1) the discounted payback period; 2) the net present value; 3) the internal rate of return; and 4) the modified internal rate of return. (3 points)
if the internal rate of return on an investment is positive, then the investment's net present...
if the internal rate of return on an investment is positive, then the investment's net present value must be postive. True or false and why?
Drinkable Water System is analyzing a project with project cash inflows of $137,000, $189,300, and -$25,000...
Drinkable Water System is analyzing a project with project cash inflows of $137,000, $189,300, and -$25,000 for 1 to 3, respectively. The project cost $236,000 and has been assigned a discounted rate of 14 percent. Should this project be accepted based on the discounting approach to the modified internal rate or return? Why or why not?
A project has the following total (or net) cash flows.                __________________________________________            &nbs
A project has the following total (or net) cash flows.                __________________________________________               Year          Total (or net) cash flow                _________________________________________ 1 $20,000 2 30,000 3 50,000 4 60,000 _________________________________________ The required rate of return on the project is 15 percent. The initial investment (or initial cost or initial outlay) of the project is $80,000. a) Find the net present value (NPV) of the project. b) Find the profitability index (PI) of the project. c) Calculate the modified internal rate...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT