Question

Two projects have the estimated details as shown in Table 2.2. Construct cash flow diagrams for...

Two projects have the estimated details as shown in Table 2.2. Construct cash flow diagrams for the two projects and use present worth (PW) analysis to determine which project should be selected at the rate of 12% per year

Table 2.2: Details for Project R and Project S

Project R

Project S

Initial cost (RM)

30,000

20,000

Annual cost (RM)

7,000 for first year,

increasing by 1,000 per year for subsequent years

0 for the first 3 year,

5,000 from year 4 to year 7

1,000 for year 8

Special maintenance (RM)

0

5,000 every 2 year

One-off maintenance (RM)

3,000 in year 3

0

Yearly income (RM)

8,500

7500

Salvage Value (RM)

4,000

0

Life (years)

4

8

Homework Answers

Answer #1

Let me know in the comment section in case of any doubt.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A corporation is considering two mutually exclusive projects. The projects have the following cash flows: Project...
A corporation is considering two mutually exclusive projects. The projects have the following cash flows: Project A Project B YEAR 0 <$10,000> <$8,000> 1 1,000 7,000 2 2,000 1,000 3 6,000 1,000 4 6,000 1,000 At what cost of capital do the two projects have the same net present value? (That is, what is the crossover rate?)
1.     Suppose your firm is considering two independent projects with the cash flows shown as follows....
1.     Suppose your firm is considering two independent projects with the cash flows shown as follows. The required rate of return on projects of both of their risk class is 12 percent, and the maximum allowable payback and discounted payback statistic for the projects are two and a half and three years, respectively. Time 0 1 2 3 Project A Cash Flow ?5,000 1,000 3,000 5,000 Project B Cash Flow ?10,000 5,000 5,000 5,000 Use the payback decision rule to...
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown as...
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown as follows. The required rate of return on projects of both of their risk class is 8 percent, and the maximum allowable payback and discounted payback statistic for the projects are two and three years, respectively. Time 0 1 2 3 Project A Cashflow -20,000 10,000 30,000 1,000 Project B Cashflow -30,000 10,000 20,000 50,000 Calculate the NPV and use the NPV decision rule to...
Anderson Associates is considering two mutually exclusive projects that have the following cash flows: Project A...
Anderson Associates is considering two mutually exclusive projects that have the following cash flows: Project A Project B Year Cash Flow Cash Flow 0 -$10,000 -$8,000 1 2,000 7,000 2 2,000 3,000 3 6,000 1,000 4 8,000 3,000 At what cost of capital do the two projects have the same net present value? (That is, what is the crossover rate?) Enter your answer rounded to two decimal places. Do not enter % in the answer box. For example, if your...
1.      Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown...
1.      Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown as follows. The required rate of return on projects of both of their risk class is 8 percent, and the maximum allowable payback and discounted payback statistic for the projects are two and three years, respectively. Time 0 1 2 3 Project A Cash Flow ?20,000 10,000 30,000 1,000 Project B Cash Flow ?30,000 10,000 20,000 50,000 Use the MIRR decision rule to evaluate...
Project P costs $15,000 and is expected to produce benefits (cash flows) of $4,500 per year...
Project P costs $15,000 and is expected to produce benefits (cash flows) of $4,500 per year for five years. Project Q costs $37,500 and is expected to produce cash flows of $11,100 per year for five years. Calculate each project’s (a) net present value (NPV), (b) internal rate of return (IRR), and (c) mod- ified internal rate of return (MIRR). The firm’s required rate of return is 14 percent.  Compute the (a) NPV, (b) IRR, (c) MIRR, and (d) discounted payback...
You have been given the responsibility of deciding between 2 projects. Your company cannot do both...
You have been given the responsibility of deciding between 2 projects. Your company cannot do both of them. The projects both have 4-year lives, no residual value and generate cash flows as per the following table. The cost of capital is 8%. 0 1 2 3 4 Project A ($50,000) $25,000 $20,000 $5,000 $39,000 Project B ($40,000) $10,000 $30,000 $22,000 $7,000 Which of the following statements is true?a) A has a better NPV, IRR and PBPb) A has a better...
1.- You are choosing between two projects. The cash flows for the projects are given in...
1.- You are choosing between two projects. The cash flows for the projects are given in the following table​ ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A −$48 $26 $19 $19 $15 B −$101 $22 $42 $48 $61 a. What are the IRRs of the two​ projects? b. If your discount rate is 5.1%​, what are the NPVs of the two​projects? c. Why do IRR and NPV rank the two projects​ differently? 2.- You...
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows:...
A company is analyzing two mutually exclusive projects, S and L, with the following cash flows: 0 1 2 3 4 5 Project 1 -$200 $50 $50 $50 $205 $205 Project 2 -$400 $300 $300 $110 $110 $110 The company's WACC is 8.0%. What is the IRR of the better project? (Hint: The better project may or may not be the one with the higher IRR.) Round your answer to two decimal places. Project S -$1,000 $870.54 $260 $10 $5...
A firm is considering Projects S and L, whose cash flows are shown below. These projects...
A firm is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the best procedure. If the wrong decision criterion is used, how much potential value would the firm lose? WACC: 6.75% 0 1 2 3 4 CFS -$1,025 $380 $380 $380 $380 CFL -$2,150...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT