Question

In cases of mutually exclusive projects, if the decision based on NPV versus IRR differs because...

In cases of mutually exclusive projects, if the decision based on NPV versus IRR differs because of scale differences or cash flow timing differences, which decision rule is best?

Homework Answers

Answer #1

NPV decision rule is always the best.

NPV accounts for the scale differences of the projects.

Eg. Project A Initial investment $100

Expected cash flow of $200

This has an IRR of 100%

and an NPV of $81.81 at 10% discount rate

Say Project B has an initial investment of $1 million and the expected cash flow of $1.2 million in one year.

This has an IRR of 20% and NPV of $90,909.

If the projects are mutually exclusive do you take Project A just because it has a higher IRR of 100% and get only $100 in one year? No! You take project B because it has a higher NPV.

Also, you cannot use IRR when there are multiple sign changes in the cash flows.

Can you please upvote? Thank you :-)

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
NPV versus IRR Consider the following cash flows on two mutually exclusive projects for the Bahamas...
NPV versus IRR Consider the following cash flows on two mutually exclusive projects for the Bahamas Recreation Corporation. Both projects require an annual return of 15 percent. YEAR DEEPWATER FISHING NEW SUBMARINE RIDE 0 −$835,000 −$1,650,000 1 450,000 1,050,000 2 410,000 675,000 3 335,000 520,000 As a financial analyst for the company, you are asked the following questions. If your decision rule is to accept the project with the greater IRR, which project should you choose? Since you are fully...
NPV verses IRR Consider the following cash flows on the two mutually exclusive projects for the...
NPV verses IRR Consider the following cash flows on the two mutually exclusive projects for the Bahamas Recreation Corporations (BRC). Both projects require an annual return on 14% Year Deep Water  Fishing New Submarine Ride 0 -$850,000 -$1,650,000 1 320,000 810,000 2 470,000 750,000 3 410,000 690,000 a) If your decision rile is to accept the project with the greater IRR, which project should you choose? c) To be prudent, you compute the NPV for both projects. Which project should you...
For mutually exclusive projects, the incremental IRR approach to capital budgeting reconciles the IRR and NPV...
For mutually exclusive projects, the incremental IRR approach to capital budgeting reconciles the IRR and NPV methods because this approach overcomes the problems associated with multiple IRRs or no IRRs. true of false
The large furniture retailer "Sofa So Good" is evaluating two mutually exclusive projects: NPV versus IRR....
The large furniture retailer "Sofa So Good" is evaluating two mutually exclusive projects: NPV versus IRR. Consider the following projects where the firms may only choose one not both: The firm's cost of capital/required return equals 9%. NOTE: The firm's cost of capital K, acts as a hurdle rate, and is based on the costs involved in financing other firm projects. The Cost of capital allows us to decide to accept or reject an investment, using IRR, which additionally allows...
When evaluating mutually exclusive capital budgeting projects, the NPV and IRR could conflict with each other...
When evaluating mutually exclusive capital budgeting projects, the NPV and IRR could conflict with each other in the ranking of projects. List and explain three reasons why a conflict could exist. Which technique is best to use in a conflict? Explain.
If mutually exclusive projects with normal cash flows are being analyzed, the net present value (NPV)...
If mutually exclusive projects with normal cash flows are being analyzed, the net present value (NPV) and internal rate of return (IRR) methods   agree. Projects Y and Z are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. Year Project Y Project Z 0 –$1,500 –$1,500 1 $200 $900 2 $400 $600 3 $600 $300 4 $1,000 $200    If the weighted average cost of capital (WACC) for each project is 14%, do the NPV and...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Criteria:                Project_A         Project_B             Project_C         Project_D          Project_E               Project_F             Project_G NPV= $137,083 $31,290 $6,016 $7,647 ($584) $12,521 $9,214 IRR= 31.80% 48.34% 12.03% 11.30% 9.94% 26.79% 37.87% MIRR= 18.52% 23.52% 10.62% 10.59% 9.97% 23.53% 20.76% PI= 1.69 2.25 1.040 1.038 1.00 2.25 1.92 The discounting rate...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Project A Project B Project C Project D Project E Project F Project G NPV= $4,711 ($711) ($657) $334 $9,842 $7,360 ($3,224) IRR= 44.51% 5.47% 8.06% 12.98% 22.56% 17.19% 5.47% MIRR= 25.23% 7.50% 8.97% 11.57% 16.26% 13.70% 7.50% PI= 2.178 0.822 0.945 1.028 1.394 1.294 0.871 The discounting rate (r)...
(Mutually exclusive projects and​ NPV)  You have been assigned the task of evaluating two mutually exclusive...
(Mutually exclusive projects and​ NPV)  You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: Year Project A Cash Flow Project B Cash Flow 0 ​$(90,000​) ​$(90,000​) 1    32,000            0 2    32,000            0 3    32,000            0 4    32,000            0 5    32,000   240,000 If the appropriate discount rate on these projects is 9 ​percent, which would be chosen and​ why? The NPV of Project A is ​$ _______. ​(Round to the nearest​ cent.)
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Criteria:                Project_A         Project_B             Project_C         Project_D          Project_E               Project_F             Project_G NPV= $137,083 $31,290 $6,016 $7,647 ($584) $12,521 $9,214 IRR= 31.80% 48.34% 12.03% 11.30% 9.94% 26.79% 37.87% MIRR= 18.52% 23.52% 10.62% 10.59% 9.97% 23.53% 20.76% PI= 1.69 2.25 1.040 1.038 0.999 2.25 1.92 The discounting rate...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT