Question

Q. Consider the following table of cash flows years 0 1 2 3 4 5 6...

Q. Consider the following table of cash flows

years 0 1 2 3 4 5 6 7 8

Interest 4.7% 4.3% 5.5% 5% 4.7% 9% 11% 5.6% 4%

Cash flows -150000 18000 32000 34000 -22000 12000 5000 3500 8000

You are required to calculate

1.     Present value

2.     Future value

3.     Internal rate of return

Cash flows occur at the end of the year

Homework Answers

Answer #1

Formulas Used :-

Present value=B108/(1+C108)^A108

Future Value=B108*(1+C108)^A108

IRR=IRR(B108:B116)

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Metlock Inc. is contemplating a capital investment of $68000. The cash flows over the project’s four...
Metlock Inc. is contemplating a capital investment of $68000. The cash flows over the project’s four years are:Metlock Inc. is contemplating a capital investment of $68000. The cash flows over the project’s four years are: Expected Annual Expected Annual Year Cash Inflows Cash Outflows 1 $38000 $12000 2 33000 18000 3 40000 22000 4 32000 20000 The cash payback period is?
Consider the following cash flows: End of Quarter 1 2 3 4 5 Cash Flow $1,700...
Consider the following cash flows: End of Quarter 1 2 3 4 5 Cash Flow $1,700 $1,700 $1,500 $100 $1,700 If the effective annual rate is 17 percent, what is the present value of the cash flows? Group of answer choices $2,855.67 $7,368.50 $6,022.13 $4,460.17
There are four projects to consider that have the following net yearly cash flows. 0 1...
There are four projects to consider that have the following net yearly cash flows. 0 1 2 3 4 5 6 P1 -3000 -500 1000 2000 4000 P2 -1000 -1000 500 0 400 500 2000 P3 -4000 2000 -3000 5000 7000 1000 P4 -2000 -4000 -1000 8000 1000 The MARR for this company is 12%. a) You can select up to two projects to complete. Which projects would you recommend? b) Management has imposed a time limit of 4 years...
($ thousands) Period 0 1 2 3 4 5 6 7 Net cash flow –12,900 –1,514...
($ thousands) Period 0 1 2 3 4 5 6 7 Net cash flow –12,900 –1,514 2,977 6,353 10,564 10,015 5,787 3,299 Present value at 21% –12,900 –1,251 2,033 3,586 4,928 3,861 1,844 869 Net present value = 2,970 (sum of PVs)     Restate the above net cash flows in real terms. Discount the restated cash flows at a real discount rate. Assume a 21% nominal rate and 9% expected inflation. NPV should be unchanged at +2,970, or $2,970,000. (Negative...
Consider the following cash flows: Year Cash Flow 2 $ 21,200 3 39,200 5 57,200 Assume...
Consider the following cash flows: Year Cash Flow 2 $ 21,200 3 39,200 5 57,200 Assume an interest rate of 8 percent per year. If today is Year 0, what is the future value of the cash flows five years from now? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) Future value            $ If today is Year 0, what is the future value of the cash flows ten years from now? (Do not...
Year Project A Expected Cash Flows ($) 0 (1,250,000) 1 75,000 2 218,750 3 535,000 4...
Year Project A Expected Cash Flows ($) 0 (1,250,000) 1 75,000 2 218,750 3 535,000 4 775,000 5 775,000 Year Project B Expected Cash Flows ($) 0 (1,050,000) 1 650,000 2 500,000 3 226,250 4 137,500 5 62,500 Metrics Payback Period (in years) (A)3.54 (B)1.8 Discounted payback period (in years) (A)4.58 (B)2.72 Net Present Value (NPV) (A)$160,816 (B)$151,742 Internal Rate of Return (A)18.90% (B)23.84% Profitability Index (A)1.13 (B)1.14 Modified Internal Rate of Return (MIRR) (A)17.82% (B)18.15% a). Which of the...
Assuming a project having the following cash flows: Year 0 1 2 3 4 Cash flow...
Assuming a project having the following cash flows: Year 0 1 2 3 4 Cash flow -6000 500 -500 5000 3000 What is the NPV of this project if the discount rate is 5%? Report the answer with 2 numbers after decimal place What is the IRR of this project? Report the answer in percentage term with 2 numbers after decimal place such as 12.43%. What discount rate will make NPV of this project equals to -494.258 Report the answer...
Compute the EUAC for these cash flows. 0 1 2 3 4 5 i = 15%...
Compute the EUAC for these cash flows. 0 1 2 3 4 5 i = 15% 100 100
Assume the following cash flows for Project A: Year 0 =$(10,000); Year 1 = $4,000; Year...
Assume the following cash flows for Project A: Year 0 =$(10,000); Year 1 = $4,000; Year 2 = $3,500; Year 3 = $1,500; Year 4 = $3,000; and Year 5 = $1,500. The company’s hurdle rate is 9.00%. For Project A, please calculate: 1) the discounted payback period; 2) the net present value; 3) the internal rate of return; and 4) the modified internal rate of return.
Consider an asset expected to generate the following finite set of cash flows.             0                 &nbsp
Consider an asset expected to generate the following finite set of cash flows.             0                      1                      2                      3                      4                      5          years             |---------------     |----------------   |----------------   |----------------   |----------------- |             -$11500           $1500              $7500              $1200              $1200              $4800 As shown on the timeline, the cost of the asset is $11,500. Assume a required rate of return of 10% per year, compounded annually. A.        Calculate the net present value (NPV) of this set of cash flows. B.        Calculate the internal rate of return (IRR)...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT