Question

Which of the following statements is NOT CORRECT? a. The IRR method takes into account the...

Which of the following statements is NOT CORRECT?

a.

The IRR method takes into account the time value of money

b.

The IRR method values a dollar received today greater than a dollar that will be received until sometime in the future

c.

The IRR method takes into account the cash flows over a project’s full life

d.

The IRR method assumes that the cash flows to be received from a project are to be reinvested at the WACC

Homework Answers

Answer #1

IRR is the rate of return earned over the full priject life. In other words, it is the Discount Rate at which NPV i.e. Net Present Value is 0.

As, it considers NET Present Value i.e. Initial Investment and all Future Cash Flows. And, it considers PRESENT VALUE.

It considers Time Value of Money.

It values dollar received today more than received in future.

It takes into account full project life.

It assumes that Cash Flows are reinvested at IRR ITSELF and NOT WACC.

Therefore, Option (d) is Incorrect.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Which of the following statements is CORRECT? A) One defect of the IRR method is that...
Which of the following statements is CORRECT? A) One defect of the IRR method is that it does not take account of cash flows over a project’s full life. B) One defect of the IRR method is that it does not take account of the time value of money. C) One defect of the IRR method is that it does not take account of the cost of capital. D) One defect of the IRR method is that it values a...
1. Which of the following statements is CORRECT? A. One problem of the IRR method is...
1. Which of the following statements is CORRECT? A. One problem of the IRR method is that it does not consider all cash flows of a project. B. One problem of the IRR method is that it does not take into account the time value of money. C. One problem of the IRR method is that it does not consider the reinvestment of cash inflows. D. One problem of the IRR method is that a dollar received today is valued...
You are planning to retire in 17 years and figure you will need $2 million in...
You are planning to retire in 17 years and figure you will need $2 million in your 401K. Your current balance is $300,000 and you plan to make 17 annual contributions of equal size over the next 17 years beginning one year from today. How much does the size of your payment need to be to meet your goals if you expect your 401K to earn 7% per year? Group of answer choices a. $29,001.42 b. $39,958.00 c. None of...
Which of the following statements is CORRECT? Assume that the project being considered has normal cash...
Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. a. The IRR calculation implicitly assumes that all cash flows are reinvested at the WACC. b. If a project has normal cash flows and its IRR exceeds its WACC, then the project’s NPV must be positive. c. If Project A has a higher IRR than Project B, then Project A must also have a...
The IRR evaluation method assumes that cash flows from the project are reinvested at the same...
The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project’s IRR. Consider the following situation: Blue Llama Mining Company is analyzing a project that requires an initial investment of $450,000. The project’s expected cash flows are: Year Cash...
The IRR evaluation method assumes that cash flows from the project are reinvested at a rate...
The IRR evaluation method assumes that cash flows from the project are reinvested at a rate equal to the project’s IRR. However, in reality, the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, using the modified IRR approach, you can make a more reasonable estimate of a project’s rate of return than the project’s IRR can. Consider the following situation: Cold Goose Metal Works Inc. is analyzing a project that requires an initial investment...
Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the...
Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project’s IRR. Consider the following situation: Fuzzy Button Clothing Company is analyzing a project that requires an initial investment of $500,000. The project’s...
Which problem associated with IRR is corrected by using MIRR? A. IRR assumes the cash-flows received...
Which problem associated with IRR is corrected by using MIRR? A. IRR assumes the cash-flows received are reinvested at the WACC B. IRR assumes the cash-flows received are reinvested at the IRR C. IRR assumes the cash-flows received are reinvested at the MIRR D. IRR assumes the cash-flows received are reinvested at the risk-free rate
The IRR evaluation method assumes that cash flows from the project are reinvested at the same...
The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project’s IRR. Consider the following situation: Green Caterpillar Garden Supplies Inc. is analyzing a project that requires an initial investment of $400,000. The project’s expected cash flows are: Year...
4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from...
4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project’s IRR. Consider the following situation: Cold Goose Metal Works Inc. is analyzing a project that requires an initial investment of $500,000....
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT