Question

Ralph wants to build a new two (2) car garage. The contractor Ralph hired provided the...

Ralph wants to build a new two (2) car garage. The contractor Ralph hired provided the following schedule and cost estimate. What is the budget at completion (BAC) for Ralph’s garage? At the end of week 1, the contractor completed 80% of the footing, framing, and siding. He spent 3,000 on concrete, lumber and vinyl siding. He also paid 1,500 in wages to laborers to complete the footing, framing, and siding. what is the earned value (EV) for Task A in the garage project, the planned value, the actual cost, the cost variance, the schedule variance? At the end of week 2, the remaining 20% of the footing, framing, and siding has been completed and all of the roofing. An additional $5,500 was spent on labor and material. What is the earned value (EV) of the project at the end of week 2? What is the cost performance index at the end of week 2? What is the schedule performance index at the end of week 2?

Task ID Task Duration (Weeks) Predecessor Budgeted Cost
A Foundation, Framing & Siding 1 Start $5,000
B Roofing 1 A $5,000
C Plumbing & Electrical 1 B $2,000
D Drywall & Painting 1 C $3,000
E Driveway 1 D $5,000

Homework Answers

Answer #1
Task ID Task Duration (Weeks) Predecessor Budgeted Cost
A Foundation, Framing & Siding 1 Start $5,000
B Roofing 1 A $5,000
C Plumbing & Electrical 1 B $2,000
D Drywall & Painting 1 C $3,000
E Driveway 1 D $5,000
Total budgeted Cost $20,000
After Week 1
Planned value $5,000
Earned value (80% of work) $4,000
Actual Cost $4,500
Cost variance = (EV - AC) ($500)
Schedule Variance (EV-PV) ($1,000)
CPI (EV/AC) 0.88889
After week 2
Planned Value $10,000
EV $10,000
Actual costs $10,000
Cost variance $0
Schedule Variance $0
CPI 1
SPI 1
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The figure below depicts the schedule for a small project. The budgeted cost is shown within...
The figure below depicts the schedule for a small project. The budgeted cost is shown within the schedule bar for each activity. For the sake of simplicity, assume costs are distributed evenly throughout an activity's duration. For example, Activity A will take four weeks and has a total budgeted cost of $4,000. Consequently, expected expenditures for A will be $1,000 per week. In contrast, Activity B will cost $2,000 per week. Precedence relationships are as follows: A must precede B...
1.) A project manager is analyzing progress on a project to make a 10-minute documentary. It's...
1.) A project manager is analyzing progress on a project to make a 10-minute documentary. It's the end of week two on this three week project. The actual cost is $72,000. They have 7 minutes of usable film. The budgeted total cost is $100,000. Determine PV,EV,CV,CPI,SV, ans SPI a. First, map each description to an EVA category. Then, fill in the table. Week AC PV EV CV CPI SV SPI 2 72,000 b. What do the SPI and CPI values...
What tools could AA leaders have used to increase their awareness of internal and external issues?...
What tools could AA leaders have used to increase their awareness of internal and external issues? ???ALASKA AIRLINES: NAVIGATING CHANGE In the autumn of 2007, Alaska Airlines executives adjourned at the end of a long and stressful day in the midst of a multi-day strategic planning session. Most headed outside to relax, unwind and enjoy a bonfire on the shore of Semiahmoo Spit, outside the meeting venue in Blaine, a seaport town in northwest Washington state. Meanwhile, several members of...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT