Question

A project has three possible outcomes. The NPV and probabilities for each outcome are shown below:...

A project has three possible outcomes. The NPV and probabilities for each outcome are shown below:

CASE:

NPV:

Probability

BAD

-$4,000

0.20

AVERAGE

$500

0.50

GREAT

$10,000

0.30

What is the expected NPV for this project if our assumptions are correct?

Question 24 options:

$1,050

$2,450

$4,250

$2,167

$600

Homework Answers

Answer #1

What is the expected NPV for this project if our assumptions are correct?

Answer: $2,450

Working

Formula for calculating expected NPV is as follows

Expected NPV = Total of (NPV * Probability)

                                = (-$4,000 * .20) + ($500 * .50) + ($10,000 * .30)

                                = -$800 + $250 + $3,000

                                = $2,450

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions