A project has three possible outcomes. The NPV and probabilities for each outcome are shown below:
CASE: |
NPV: |
Probability |
BAD |
-$4,000 |
0.20 |
AVERAGE |
$500 |
0.50 |
GREAT |
$10,000 |
0.30 |
What is the expected NPV for this project if our assumptions are correct?
Question 24 options:
$1,050 |
|
$2,450 |
|
$4,250 |
|
$2,167 |
|
$600 |
What is the expected NPV for this project if our assumptions are correct?
Answer: $2,450
Working
Formula for calculating expected NPV is as follows
Expected NPV = Total of (NPV * Probability)
= (-$4,000 * .20) + ($500 * .50) + ($10,000 * .30)
= -$800 + $250 + $3,000
= $2,450
Get Answers For Free
Most questions answered within 1 hours.