Question

A company s considering a project which requires the initial outlay of $300,000 which includes both...

A company s considering a project which requires the initial outlay of $300,000 which includes both an after-tax salvage from the old asset of $12,000 and an additional working capital investment of $8,000. The 12-year project is expected to generate annual incremental cash flows of $54,000 and have an expected terminal value at the end of the project of $20,000. The cost of capital is 15 percent, and the company's marginal tax rate is 40 percent. Calculate the net present value of this project.

  • -$3,548.43
  • $68,781.83
  • -$6,544.56
  • -$596,451.57
  • $12,713.43

Sue is trying to determine which of two projects to undertake. Both projects have equal initial outlay. Project A has an NPV of $4,392.15, an IRR of 11.33%, and an EAA of $1,158.64. Project B has an NPV of $5,833.73, an IRR of 9.88%, and an EAA of $1,093.50. The cost of capital for both projects is 9%, the projects have different lives, and the projects are repeatable. What should Sue do?

  • You should do neither project because neither of them would add value to your company.
  • You should do Project Adam because it has a higher IRR.
  • You should do Project Adam because it has a higher EAA.
  • You should do both projects because both have positive NPVs.
  • You should do Project Eve because it has a higher NPV.

Homework Answers

Answer #1

1. The cashflows are shown in the below table and for Year12 cashflow we should add salvage value of $20,000 becoming the total cashflow to $74,000

NPV has to be found by using NPV function in EXCEL

=NPV(rate, Year1 to Year12 cashflows)-Year0 cashflow

=NPV(15%,Year1 to Year12 cashflows)-300000

NPV=-$3548.43 (option a is correct)

Cost of capital 15%
Year0 -300000
Year1 54000
Year2 54000
Year3 54000
Year4 54000
Year5 54000
Year6 54000
Year7 54000
Year8 54000
Year9 54000
Year10 54000
Year11 54000
Year12 74000
NPV -3548.43

2. If the projects have different lives and projects are repeatable, Equivalent Annual Annuity (EAA) is the correct measure to accept or reject a project.

Project having higher EAA has to be selected, project Adam has to be selected because of higher EAA

Option C is correct

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
You are trying to determine which of two mutually exclusive projects to undertake. Project Adam has...
You are trying to determine which of two mutually exclusive projects to undertake. Project Adam has an initial outlay of $10,000, an NPV of $4,392.15, an IRR of 11.33%, and an EAA of $1,158.64. Project Eve has an initial outlay of $15,000, an NPV of $5,833.73, an IRR of 9.88%, and an EAA of $1,093.50. The cost of capital for both projects is 9%, and the projects have different lives. If the projects are repeatable, then: You should do both...
You are trying to determine which of two mutually exclusive projects to undertake. Both projects have...
You are trying to determine which of two mutually exclusive projects to undertake. Both projects have the same initial outlay. Project Adam has an NPV of $4,392.15, an IRR of 11.33%, and an EAA of $1,158.64. Project Eve has an NPV of $5,833.73, an IRR of 9.88%, and an EAA of $1,093.50. The cost of capital for both projects is 9%, the projects have different lives, and the projects are not repeatable. What should you do? You should do Project...
Project S requires an initial outlay at t = 0 of $18,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $18,000, and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $43,000, and its expected cash flows would be $12,000 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have NPV's...
Project S requires an initial outlay at t = 0 of $10,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $10,000, and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $50,000, and its expected cash flows would be $13,750 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Project L, since the NPVL > NPVS. b. Project S,...
Project S requires an initial outlay at t = 0 of $10,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $10,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $28,500, and its expected cash flows would be $13,200 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV <...
Project S requires an initial outlay at t = 0 of $12,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $12,000, and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $45,000, and its expected cash flows would be $13,150 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Project L, since the NPVL > NPVS. b. Neither Project...
Project R requires an initial outlay at t = 0 of $14,000, and its expected cash...
Project R requires an initial outlay at t = 0 of $14,000, and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $32,500, and its expected cash flows would be $13,050 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, since each project's NPV <...
Project L requires an initial outlay at t = 0 of $50,000, its expected cash inflows...
Project L requires an initial outlay at t = 0 of $50,000, its expected cash inflows are $15,000 per year for 9 years, and its WACC is 9%. What is the project's MIRR? Do not round intermediate calculations. Round your answer to two decimal places. = % Project S requires an initial outlay at t = 0 of $12,000, and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay...
A firm is considering a replacement project which requires the initial outlay of $300,000 which includes...
A firm is considering a replacement project which requires the initial outlay of $300,000 which includes both an after-tax salvage from the old asset of $12,000 and an additional working capital investment of $8,000. The 12-year project is expected to generate annual incremental cash flows of $54,000 and have an expected terminal value at the end of the project of $20,000. The cost of capital is 15 percent, and its marginal tax rate is 40 percent. Calculate the net present...
Project X and Project Y are two mutually exclusive projects. Project X requires an initial outlay...
Project X and Project Y are two mutually exclusive projects. Project X requires an initial outlay of $38,000 and generates a net cash flow of $14,000 per year for six years. Project Y requires an initial outlay of $52,000, and will generate cash flows of $15,300 per year for eight years. Which project should be chosen and why? (Assume that the discount rate for both projects is 10 percent). A.  Project X because Project X has a larger NPV than Project...