Question

A private equity firm is considering five competing projects in which to invest in the upcoming...

A private equity firm is considering five competing projects in which to invest in the upcoming quarter. The firm needs to decide how to allocate its available capital based upon the combination of projects(denoted as a to e)selected to maximize returns(based upon net present value(npv)).Table 1 below presents the capital requirements and the NPV for each project, along with the associated risk(given as a percentage of the initial investment).The company has $43 million in capital to allocate, with the goal of having an average associated risk of no more than 5%.There are some additional constraints to be met: i) if project B is selected, then project e is also selected;ii) if either project a is selected or project c selected, but not both; iii) at least one of projects a,b,d, is selected.

Table 1. project data

project

Npv(M$)

Risk(%)

Capital(M$)

a

19

4

14

b

22

5

10

c

24

6

12

d

27

7

15

e

21

5

13

Homework Answers

Answer #1
if project B is selected, then project e is also selected
if either project a is selected or project c selected, but not both
at least one of projects a,b,d, is selected.
project Npv(M$) Risk(%) Capital(M$)
a 19 4 14
b 22 5 10
c 24 6 12
d 27 7 15
e 21 5 13
The company should invest in project a, b and e.
The capital investment will be $ 37 million with NPV of 62 and average risk of 4.67%
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Consider a small Oil production firm with 5 competing oil production projects, A - E. The...
Consider a small Oil production firm with 5 competing oil production projects, A - E. The table below shows the estimated long-term profit (Net Present Value) for each project as well as the amount of investment capital required to start the project. You have been contacted to help select the best combination of projects to maximize the Net Present Value subject to the capital investment limit of $32 million. Production Project A B C D E Estimated Profit (millions) 25...
When an analyst arrives at a cost of capital for an upcoming project and that cost...
When an analyst arrives at a cost of capital for an upcoming project and that cost of capital is based on the cost of capital for another firm which operates similarly to your project, the analyst is using the _____ approach. Select one: a. subjective risk b. pure play c. divisional cost of capital d. capital adjustment e. security market line A firm's cost of capital: Select one: a. will decrease as the risk level of the firm increases. b....
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$500 $45 $45 $45 $160 $160 Project 2 -$450 $300 $300 $60 $60 $60 Which project would you recommend? Select the correct answer. a. Both Projects 1 and 2, since both projects have NPV's > 0. b. Project 1, since the NPV1 > NPV2. c. Both Projects 1 and 2, since both...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$350 $40 $40 $40 $215 $215 Project 2 -$650 $200 $200 $70 $70 $70 Which project would you recommend? Select the correct answer. a. Project 1, since the NPV1 > NPV2. b. Both Projects 1 and 2, since both projects have IRR's > 0. c. Project 2, since the NPV2 > NPV1....
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$250 $75 $75 $75 $170 $170 Project 2 -$700 $200 $200 $50 $50 $50 Which project would you recommend? Select the correct answer. a. Neither Project 1 nor 2, since each project's NPV < 0. b. Both Projects 1 and 2, since both projects have NPV's > 0. c. Project 1, since...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$250 $50 $50 $50 $175 $175 Project 2 -$700 $350 $350 $80 $80 $80 Which project would you recommend? Select the correct answer. a. Project 2, since the NPV2 > NPV1. b. Project 1, since the NPV1 > NPV2. c. Both Projects 1 and 2, since both projects have NPV's > 0....
Cowboy Corp. is about to expand its operations and they have several projects with various cash...
Cowboy Corp. is about to expand its operations and they have several projects with various cash flows available in Excel upload file. Each project has an 8-year life and the firm has a cost of capital at 8%. The firm has $15,000 for the expansion and will invest in multiple projects with that capital constraint. 1. Calculate NPV for each project 2. Find the project combination that maximizes total NPV for Cowboy Corp. and calculate total capital spending 3. Find...
An all-equity firm is considering the following projects: Project Beta IRR A 0.75 8.4% B 0.95....
An all-equity firm is considering the following projects: Project Beta IRR A 0.75 8.4% B 0.95. 12.6% C 1.15 13.5% D 1.32 14.5% E 1.45 15.9% The T-bill rate is 3 percent, and the expected return on the market is 12 percent. a. Which projects have a higher expected return than the firm’s 13 percent cost of capital? (5 points) b. Which projects should be accepted? Why? (5 points)
Capital budgeting criteria: mutually exclusive projects A firm with a WACC of 10% is considering the...
Capital budgeting criteria: mutually exclusive projects A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project A -$500 $45 $45 $45 $220 $220 Project B -$600 $300 $300 $50 $50 $50 Which project would you recommend? Select the correct answer. I. Neither A or B, since each project's NPV < 0. II. Both Projects A and B, since both projects have NPV's > 0. III. Both Projects A and...
A firm needs to decide between two mutually exclusive projects. Project Alpha requires an initial investment...
A firm needs to decide between two mutually exclusive projects. Project Alpha requires an initial investment of $37,000 today and is expected to generate cash flows of $31,000 for the next 4 years. Project Beta requires an initial investment of $92,000 and is expected to generate cash flows of $36,400 for the next 8 years. The cost of capital is 10%. The projects can be repeated with no change in cash flows. What is the NPV of the project that...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT