Question

If a firm considers two separate projects but is only able to accept one of the...

If a firm considers two separate projects but is only able to accept one of the projects due to the fact that each project would require exclusive use of the Company’s manufacturing machinery, these projects are considered to be:

Select one:

a. Independent

b. Interdependent

c. Mutually exclusive

d. Mutually inclusive

e. Operationally distinct

Internal rate of return (IRR) is defined as the:

Select one:

a. discount rate which causes the net present value of a project to equal zero.

b. rate of return a project will generate if the project in financed solely with internal funds.

c. discount rate that equates the net cash inflows of a project to zero.

d. maximum rate of return a firm expects to earn on a project.

e. discount rate that causes the profitability index for a project to equal zero.

Homework Answers

Answer #1

1. option "C" is correct, i.e., Mutually exclusive.

Independent projects are the projects whose acceptance or rejection is independent of the acceptance or rejection of other projects.

Interdependent Project  is a term used to denote a situation when two or more projects are related to each other in certain ways (they depend on each other somehow).

Mutually inclusive projects allows both projects to occur intogether.

2. Option "A" is correct, i.e, IRR is the discount rate which causes the net present value of a project to equal zero.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Project A Project B Project C Project D Project E Project F Project G NPV= $4,711 ($711) ($657) $334 $9,842 $7,360 ($3,224) IRR= 44.51% 5.47% 8.06% 12.98% 22.56% 17.19% 5.47% MIRR= 25.23% 7.50% 8.97% 11.57% 16.26% 13.70% 7.50% PI= 2.178 0.822 0.945 1.028 1.394 1.294 0.871 The discounting rate (r)...
In mutually exclusive projects, project that is selected for comparison with others must have a. Internal...
In mutually exclusive projects, project that is selected for comparison with others must have a. Internal rate of return greater than zero b. Positive net present value c. Zero net present value d. Highest net present value e. Shortest discounted pay back
30) Internal Rate of Return is a tool Financial Analysts use to determine whether to accept...
30) Internal Rate of Return is a tool Financial Analysts use to determine whether to accept or reject a potential project the firm is considering. It is defined as: Multiple Choice the discount rate that results in a zero net present value (NPV) for the project. the discount rate that results in a net present value (NPV) equal to the project's initial cost. the discount rate that causes a project's after-tax income to equal zero. the rate of return required...
Which of the following statement is correct? a. A firm should never accept the independent projects...
Which of the following statement is correct? a. A firm should never accept the independent projects having NPVs greater than zero. b. All the answers are incorrect. c. Because the net present value method does not factor in the time value of money, nor the cash flows after the payback period, its usefulness is limited. d. Mutually exclusive projects are the projects that do not have the same task and therefore they do not compete with each other. e. The...
Consider the following two mutually exclusive projects: Year Project A Project B 0 -180,000 -18,000 1...
Consider the following two mutually exclusive projects: Year Project A Project B 0 -180,000 -18,000 1 60,000 15,000 2 100,000 15,000 3 150,000 12,000 Calculate the internal rate of return, and net present value. Assume a discount rate of 15%. Which project should be selected?
6. Understanding the NPV profile If projects are mutually exclusive, only one project can be chosen....
6. Understanding the NPV profile If projects are mutually exclusive, only one project can be chosen. The internal rate of return (IRR) and the net present value (NPV) methods will not always choose the same project. If the crossover rate on the NPV profile is below the horizontal axis, the methods will agree. Projects Y and Z are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. Year Project Y Project Z 0 –$1,500 –$1,500 1...
The internal rate of return : (mark all that applies) is the more sound decision rule...
The internal rate of return : (mark all that applies) is the more sound decision rule when dealing with mutually exclusive projects is the rate that causes the net present value of a project to exactly equal zero. does not need a required rate to calculate. can effectively be used to analyze all investment scenarios. rule states that a typical investment project with an IRR that is less than the required rate of return should be accepted.
Which of the following statements is correct: A. projects with unconventional cash flows have multiple internal...
Which of the following statements is correct: A. projects with unconventional cash flows have multiple internal rates of return B. if 2 projects are mutually exclusive, you should select the project with the shortest payback period C. If the IRR exceeds the required return, the profitability index will be less than 1.0 D. the Profitability index will be greater than 1.0 when the net present value is negative E. when the internal rate of return is greater than the required...
Which one of the following is TRUE? The NPV decision rule says to accept an investment...
Which one of the following is TRUE? The NPV decision rule says to accept an investment if the NPV is negative. The IRR decision rule states that a project should be accepted if its IRR exceeds the required return. The discount rate that causes the net present value of a project to equal zero is called the market rate. IRR is superior to NPV for choosing between different projects. Payback ignores the project's cost.
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal...
All projects (A to G) are 7-year projects. NPV = Net present value. IRR = internal rate of return. MIRR = modified internal rate of return. PI = profitability index. Criteria:                Project_A         Project_B             Project_C         Project_D          Project_E               Project_F             Project_G NPV= $137,083 $31,290 $6,016 $7,647 ($584) $12,521 $9,214 IRR= 31.80% 48.34% 12.03% 11.30% 9.94% 26.79% 37.87% MIRR= 18.52% 23.52% 10.62% 10.59% 9.97% 23.53% 20.76% PI= 1.69 2.25 1.040 1.038 1.00 2.25 1.92 The discounting rate...