Question

Projects T and Q are mutually-exclusive investment alternatives, Each project requires a net investment of $20,000,...

Projects T and Q are mutually-exclusive investment alternatives, Each project requires a net investment of $20,000, followed by a series of positive net cash flows. Both projects have a useful life equal to 10 years. Project T has an NPV of $36,000 at a 0% discount rate, while project Q has an NPV of $30,000 at 0%. Furthermore, at a discount rate of 15 percent, the two projects have identical positive NPVs. Given this, which of the following statements is incorrect?

  1. Project Q has higher a IRR than Project T.

  2. If the cost of capital is greater than the IRR of Project T, reject both projects.

  3. If the cost of capital is 10%, select Project Q.

  4. There are three circumstances that can cause project evaluation technique conflict. Even though the net cash flow stream is not given, the project evaluation technique conflict in this problem must be caused by differences in the magnitude of the cash flows, or cash flow timing differences.

  5. The slope of Project Q's NPV profile is steeper than the slope of Project T's NPV profile.

Homework Answers

Answer #1

If the cost of capital is greater than the IRR of Project T, reject both projects - This statement is incorrect. The IRR of project Q is higher than that of project T. This is because T has a higher NPV at i=0%than 1, but at i=15% both have equal NPV, suggesting than the NPV profile of T is decreasing at a faster pace than Q, and hence the IRR of Q>T. In short, the slope of Project Q's NPV profile is steeper than the slope of Project T's NPV profile. Hence, if IRR >T, then project Q could still have a positive NPV and project Q could still be accepted.

Project Q has higher a IRR than Project T - is correct for reasons mentioned above. If the cost of capital is 10%, select Project Q- This statement is correct as NPV IS equal only at i=15%, and below 15%, Project Q has higher IRR than project T.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
6. Understanding the NPV profile If projects are mutually exclusive, only one project can be chosen....
6. Understanding the NPV profile If projects are mutually exclusive, only one project can be chosen. The internal rate of return (IRR) and the net present value (NPV) methods will not always choose the same project. If the crossover rate on the NPV profile is below the horizontal axis, the methods will agree. Projects Y and Z are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. Year Project Y Project Z 0 –$1,500 –$1,500 1...
If mutually exclusive projects with normal cash flows are being analyzed, the net present value (NPV)...
If mutually exclusive projects with normal cash flows are being analyzed, the net present value (NPV) and internal rate of return (IRR) methods   agree. Projects Y and Z are mutually exclusive projects. Their cash flows and NPV profiles are shown as follows. Year Project Y Project Z 0 –$1,500 –$1,500 1 $200 $900 2 $400 $600 3 $600 $300 4 $1,000 $200    If the weighted average cost of capital (WACC) for each project is 14%, do the NPV and...
Project X and Project Y are two mutually exclusive projects. Project X requires an initial outlay...
Project X and Project Y are two mutually exclusive projects. Project X requires an initial outlay of $38,000 and generates a net cash flow of $14,000 per year for six years. Project Y requires an initial outlay of $52,000, and will generate cash flows of $15,300 per year for eight years. Which project should be chosen and why? (Assume that the discount rate for both projects is 10 percent). A.  Project X because Project X has a larger NPV than Project...
Two mutually exclusive projects each have a cost of $10,000. The total, undiscounted cash flows from...
Two mutually exclusive projects each have a cost of $10,000. The total, undiscounted cash flows from Project L are $15,000, while the undiscounted cash flows from Project S total $13,000. Their NPV profiles cross at a discount rate of 10 percent. Which of the following statements best describes this situation? Please leave an explanation.  a. The NPV and IRR methods will select the same project if the cost of capital is greater than 10 percent; for example, 18 percent. b. The...
A firm must choose between two mutually exclusive projects, A & B. Project A has an...
A firm must choose between two mutually exclusive projects, A & B. Project A has an initial cost of $11000. Its projected net cash flows are $900, $2000, $3000, $4000, and $5000 at the end of years 1 through 5, respectively. Project B has an initial cost of $15000, and its projected net cash flows are $7000, $5000, $3000, $2000, and $1000 at the end of years 1 through 5, respectively. If the firm’s cost of capital is 6.00%: Project...
Consider the following cash flows for two mutually exclusive capital investment projects. The required rate of...
Consider the following cash flows for two mutually exclusive capital investment projects. The required rate of return is 16%. Use this information for the next 3 questions. Year Project A Cash Flow Project B Cash Flow 0 ($50,000) ($20,000) 1 15,000 6,000 2 15,000 6,000 3 15,000 6,000 4 13,500 5,400 5 13,500 5,400 6 6,750 5,400 Which of the following statements is true concerning projects A and B? a) Due to time disparity, IRR indicates that project A should...
The large furniture retailer "Sofa So Good" is evaluating two mutually exclusive projects: NPV versus IRR....
The large furniture retailer "Sofa So Good" is evaluating two mutually exclusive projects: NPV versus IRR. Consider the following projects where the firms may only choose one not both: The firm's cost of capital/required return equals 9%. NOTE: The firm's cost of capital K, acts as a hurdle rate, and is based on the costs involved in financing other firm projects. The Cost of capital allows us to decide to accept or reject an investment, using IRR, which additionally allows...
A firm must choose between two mutually exclusive projects, A & B. Project A has an...
A firm must choose between two mutually exclusive projects, A & B. Project A has an initial cost of $11000. Its projected net cash flows are $900, $2000, $3000, $4000, and $5000 at the end of years 1 through 5, respectively. Project B has an initial cost of $15000, and its projected net cash flows are $7000, $5000, $3000, $2000, and $1000 at the end of years 1 through 5, respectively. If the firm’s cost of capital is 6.00%: The...
A firm needs to decide between two mutually exclusive projects. Project Alpha requires an initial investment...
A firm needs to decide between two mutually exclusive projects. Project Alpha requires an initial investment of $37,000 today and is expected to generate cash flows of $31,000 for the next 4 years. Project Beta requires an initial investment of $92,000 and is expected to generate cash flows of $36,400 for the next 8 years. The cost of capital is 10%. The projects can be repeated with no change in cash flows. What is the NPV of the project that...
A firm needs to decide between two mutually exclusive projects. Project Alpha requires an initial investment...
A firm needs to decide between two mutually exclusive projects. Project Alpha requires an initial investment of 50,000 today and is expected to generate cash flows of 51,000 for the next 3 years. Project Beta requires an intial investment of 85,000 and is expected to generate cash flows of 49,700 for the next 6 years. The cost of capital is 6%. The projects can be repeated with no charge in cash flows. What is the NPV of the project that...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT