Question

28. What is the modified internal rate of return (MIRR) for the following project? The cost...

28. What is the modified internal rate of return (MIRR) for the following project? The cost of capital is 10%.

Time

0

1

2

3

Project A

-$350

$300

-$100

$200

a. 10.35%

b. 9.18%

c. 10.25%

d. 8.50%

31. Simkins Renovations Inc. is considering a project that has the following cash flow data. What is the project's IRR?

Year

0

1

2

3

4

Cash flows

-$825

$296

$285

$300

$320

a. 16.65%

b. 14.61%

c. 17.24%

d. 13.59%

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
8. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from...
8. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project's IRR. Consider the following situation : Cute Camel Woodcraft Company is analyzing a project that requires an initial investment of $3,225,000....
What is the Modified Internal Rate of Return (MIRR) for the following cash flows? Assume that...
What is the Modified Internal Rate of Return (MIRR) for the following cash flows? Assume that the required rate of return is 4% Year CFs 0 -1,000 1 100 2 200 3 350 4 800
Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the...
Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project’s IRR. Consider the following situation: Fuzzy Button Clothing Company is analyzing a project that requires an initial investment of $500,000. The project’s...
4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from...
4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project’s IRR. Consider the following situation: Green Caterpillar Garden Supplies Inc. is analyzing a project that requires an initial investment of $2,500,000....
4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from...
4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project’s IRR. Consider the following situation: Green Caterpillar Garden Supplies Inc. is analyzing a project that requires an initial investment of $3,225,000....
4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from...
4. Modified internal rate of return (MIRR) The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the project’s IRR. Consider the following situation: Cold Goose Metal Works Inc. is analyzing a project that requires an initial investment of $500,000....
Sam Corp. is considering a project that has the following cash flow data.  What is the project's...
Sam Corp. is considering a project that has the following cash flow data.  What is the project's IRR (Internal Rate of Return)? Note that a project's projected IRR can be less than the weighted average cost of capital (WACC) or negative, in both cases it will be rejected. Show work. Year                           0                1                2               3           4   Cash flows            -$1,900        $600          $825           $950   -$50 Helmand Inc. is considering a project that has the following cash flow and WACC data.  What is the project's MIRR?  Note that a project's projected MIRR can be less than...
Find the modified internal rate of return (MIRR) for the following series of future cash flows...
Find the modified internal rate of return (MIRR) for the following series of future cash flows if the company is able to reinvest cash flows received from the project at an annual rate of 13.72 percent.The initial outlay is $470,600. Year 1: $185,900 Year 2: $185,100 Year 3: $125,700 Year 4: $183,400 Year 5: $184,100 Round the answer to two decimal places in percentage form. How do I do this in excel?
Find the modified internal rate of return (MIRR) for the following series of future cash flows...
Find the modified internal rate of return (MIRR) for the following series of future cash flows if the company is able to reinvest cash flows received from the project at an annual rate of 12.92 percent. the initial outlay is $439,500. Year 1: $130,600 year 2: 178,600 year3: 147,800 Year 4: 133,600 Year 5: 155,700 Round answer to two decimal places.
Internal rate of return   For the project shown in the following​ table, calculate the internal rate...
Internal rate of return   For the project shown in the following​ table, calculate the internal rate of return ​(IRR). Then​ indicate, for the​ project, the maximum cost of capital that the firm could have and still find the IRR acceptable. Initial investment   $160,000 Year (t)   Cash inflows 1   $35,000 2   $25,000 3   $45,000 4   $45,000 5   $45,000 The​ project's IRR is? The maximum cost of capital that the firm could have and still find the IRR acceptable is?
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT