Question

when considering two mutally exclusice projects the financial manager should always select the project whose what...

when considering two mutally exclusice projects the financial manager should always select the project whose what is highest?
1. NPV
2. IRR
3. both
4. none

Homework Answers

Answer #1

1 NPV

In Capital Budgeting NPV and IRR conflict refers to a situation in which the NPV method ranks projects differently from the IRR method. In event of such a difference, a company should accept project(s) with higher NPV.

In Case of Mutually exclusive project , acceptance of one project will totally excludes the other project As iRR is given in return percentage term , and NPv give the absolute dollar value of the project and if the IRR is below thr cost of capital then it not acceptable , hence when there is mutually exclusive project and conflict arise Highest NPV should be selected over the IRR

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
When mutually exclusive projects have different lives, a company should select the project with the ____...
When mutually exclusive projects have different lives, a company should select the project with the ____ Highest IRR Longest life Lowest equivalent annual cost Highest NPV discounted at the cost of capital
Nike's management team is considering two projects, a golf club project and a helmet project. A....
Nike's management team is considering two projects, a golf club project and a helmet project. A. Using the table below, calculate firm’s weighted average cost of capital: Nike: % of debt in capital structure 25% % of equity in capital structure 75% Before-tax required cost of debt 6% Tax rate 30% Cost of equity 11% B. Capital Budgeting Project information: Golf club project Helmet project Upfront costs (10,000,000) (8,000,000) Annual cash flows Year 1 $0 $3,000,000 Year 2 $0 $3,000,000...
Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you...
Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 9%. 0 1 2 3 4 Project A...
Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you...
Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 11%. 0 1 2 3 4 Project A...
Langton Inc. is considering Projects S and L, whose cash flows are shown below. These projects...
Langton Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO believes the IRR is the best selection criterion, while the CFO advocates the NPV. If the decision is made by choosing the project with the higher IRR rather than the one with the higher NPV, how much, if any, value will be forgone? In other words, what's the NPV of the chosen project versus...
MIRR and NPV Your company is considering two mutually exclusive projects, X and Y, whose costs...
MIRR and NPV Your company is considering two mutually exclusive projects, X and Y, whose costs and cash flows are shown below: Year X Y 0 -$5,000 -$5,000 1 1,000 4,500 2 1,500 1,500 3 2,000 1,000 4 4,000 500 The projects are equally risky, and their cost of capital is 15%. You must make a recommendation, and you must base it on the modified IRR (MIRR). Calculate the two projects' MIRRs. Do not round intermediate calculations. Round your answers...
You are considering two mutually exclusive projects. Based upon risk, the appropriate discount rate for both...
You are considering two mutually exclusive projects. Based upon risk, the appropriate discount rate for both projects is 10%. The first project has an IRR of 22% and an NPV of $22,432. The second project has an IRR of 12% and an NPV of $24,456. Which project should you select? accept both projects since both are acceptable. pick the project with the shorter payback period. choose the project with the higher NPV. unable to determine due to insufficient information. choose...
When choosing the "best" project from two competing projects, if there is a conflict between the...
When choosing the "best" project from two competing projects, if there is a conflict between the IRR and NPV choice, do you choose the project with the highest IRR or the one with the highest NPV, and why? Consider the different reinvestment rate assumptions.
Quantum Water is considering Projects S and L, whose cash flows are shown below. These projects...
Quantum Water is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO believes the IRR is the best method, while you believe it should be the MIRR. If the decision is made by choosing the project with the higher IRR rather than the one with the higher MIRR, how much, if any, value will be forgone, i.e., what's the NPV of the chosen project versus the...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A...
You've estimated the following cash flows (in $) for two mutually exclusive projects: Year Project A Project B 0 -5,600 -8,400 1 1,325 1,325 2 2,148 2,148 3 4,193 8,192 The required return for both projects is 8%. Part 1 : What is the IRR for project A? 3+ Decimals Part 2 What is the IRR for project B? 3+ Decimals Part 3 Which project seems better according to the IRR method? Project A or Project B Part 4 What...