Question 1
A company is deciding among two mutually exclusive projects. Project A’s initial cost is $40,000, and Project B’s initial cost is 30,000. The two projects have the following cash flows:
Project A Project B
Year Cash Flow Cash Flow
1 10,000 8,000
2 15,000 12,000
3 20,000 20,000
4 20,000 15,000
The company's weighted average cost of capital is 11 percent. What is the net present value (NPV) of the project A?
1. |
8,982 |
|
2. |
7,090 |
|
3. |
7,450 |
|
4. |
8,630 |
|
5. |
9,155 |
|
1.8,982
Year | Cash Flow | Discount factor | Present Value |
a | b | c=1.11^-a | d=b*c |
0 | -40,000.00 | 1.0000 | -40,000 |
1 | 10,000.00 | 0.9009 | 9,009 |
2 | 15,000.00 | 0.8116 | 12,174 |
3 | 20,000.00 | 0.7312 | 14,624 |
4 | 20,000.00 | 0.6587 | 13,175 |
NPV | 8,982 |
Get Answers For Free
Most questions answered within 1 hours.