Compute the NPV for Project X and accept or reject the project with the cash flows shown below if the appropriate cost of capital is 10 percent.
Time | 0 | 1 | 2 | 3 | 4 | 5 |
Cash Flow | -1000 | -75 | 100 | 100 | 0 | 2000 |
Group of answer choices
$331.44
$-639.96
$392.44
$486.29