Project S requires an initial outlay at t = 0 of $12,000, and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $45,000, and its expected cash flows would be $13,150 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend?
Select the correct answer.
|
|||
|
|||
|
|||
|
|||
|
The NPV is computed as shown below:
= Initial investment + Present value of future cash flows
Present value is computed as follows:
= Future value / (1 + r)n
The NPV of Project S is computed as follows:
= - $ 12,000 + $ 6,500 / 1.161 + $ 6,500 / 1.162 + $ 6,500 / 1.163 + $ 6,500 / 1.164 + $ 6,500 / 1.165
= $ 9,282.91 Approximately
The NPV of Project L is computed as follows:
= - $ 45,000 + $ 13,150 / 1.161 + $ 13,150 / 1.162 + $ 13,150 / 1.163 + $ 13,150 / 1.164 + $ 13,150 / 1.165
= - $ 1,943.04 Approximately
Since these two projects are mutually exclusive, hence we need to select the one which has the higher NPV. Since the NPV of project S is greater than the NPV of project L, hence Project S shall be accepted.
So, the correct answer is option e.
Feel free to ask in case of any query relating to this question
Get Answers For Free
Most questions answered within 1 hours.