Question

Project B costs $800,000 and was found to have a NPV of $52,995 when using a...

Project B costs $800,000 and was found to have a NPV of $52,995 when using a WACC of 8.28%. Calculate the Productivity Index for Project B.

Homework Answers

Answer #1

Ans 1.07

NPV = Present value of cash inflows - cash outflows
52995= Present value of cash inflows - 800000
52995 + 800000 = Present value of cash inflows
852995 = Present value of cash inflows
Total of PV of Cash Inflows 852995.00
Cash Outflows 800000
Profitability Index = 1.07
Present value of cash Inflow / Initial Investment (Cash Outflows) (852995 /800000)
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
We are evaluating a project that costs $800,000, has a life of 8 years, and has...
We are evaluating a project that costs $800,000, has a life of 8 years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 60,000 units per year. Price per unit is $40, variable cost per unit is $20, and fixed costs are $800,000 per year. The tax rate is 21 percent and we require a return of 11 percent on this project. Suppose the projections given for...
Which one of the following indicates a project should be accepted? A. NPV < 0 B....
Which one of the following indicates a project should be accepted? A. NPV < 0 B. IRR>WACC C. IRR<WACC D. NPV=1
When NPV and IRR rules result in a conflicting decision regarding acceptance of a project managers...
When NPV and IRR rules result in a conflicting decision regarding acceptance of a project managers could use the MIRR. It assumes reinvestment of projects' cash flows at the WACC, so it produces results consistent with NPV method. Let's try to find the MIRR for the project with the following cash flows: Initial cost of -800 at time zero, CF1 = 400, CF 2 = 570, CF3 = -130. Here we have two negative cash flows and two positive cash...
(a) Develop proforma Project Income Statement Using Excel Spreadsheet (b) Compute Net Project Cash flows, NPV,...
(a) Develop proforma Project Income Statement Using Excel Spreadsheet (b) Compute Net Project Cash flows, NPV, IRR and PayBack Period (c) Develop Problem-Solving and Critical Thinking Skills 1) Life Period of the Equipment = 4 years 8) Sales for first year (1) $   200,000 2) New equipment cost $ (200,000) 9) Sales increase per year 5% 3) Equipment ship & install cost $     (35,000) 10) Operating cost: $ (120,000) 4) Related start up cost $       (5,000)     (60 Percent of...
1) What is the NPV of a project that costs $89,000 today and is expected to...
1) What is the NPV of a project that costs $89,000 today and is expected to generate annual cash inflows of $18,000 for the next 8 years. Cost of capital (discount rate) is 13%. Round to the nearest cent. 2) What is the Profitability Index of a project that costs $22,000 today and is expected to generate annual cash inflows of $5,000 for the following 7 years. Cost of capital is 9%. Round to two decimal places. 3) A project...
A project has an NPV of £12,632 when a discount rate of 12% is used and...
A project has an NPV of £12,632 when a discount rate of 12% is used and the same project has an NPV of (£6,935) when a discount rate of 24% is used. The approximate internal rate of return of the project is: Select one: a. 18.5% b. 15.16% c. 20.5% d. 19.75% An investment project costs $10,500 and will generate $4,000 in annual cash flows for five years. What is the exact internal rate of return (IRR)? Select one: a....
Which of the following statements is CORRECT? Assume that the project being considered has normal cash...
Which of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. A: The NPV of a relatively low-risk project should be found using a relatively high WACC B: The lower the WACC used to calculate it, the lower the calculated NPV will be If a project’s NPV is greater than zero, then its IRR must be less than zero C: If a project’s NPV is...
Jella Cosmetics is considering a project that costs $800,000 and is expected to last for 10...
Jella Cosmetics is considering a project that costs $800,000 and is expected to last for 10 years and produce future cash flows of ?$175,000 per year. If the appropriate discount rate for this project is 16 percent, what is the? project's IRR?
Stark Enterprises is considering a new project to defend Earth from future attacks. The Asgardian equipment...
Stark Enterprises is considering a new project to defend Earth from future attacks. The Asgardian equipment called bifrost costs? $2,000,000. The bifrost will produce a stream of future cash flows as follows. ?Year USD ?2019 700,000 ?2020 700,000 ?2021 700,000 ?2022 500,000 ?2023 500,000 ?2024 500,000 ?2025 500,000 ?2026 500,000 ?2027 500,000 ?2028 500,000 ?2029 500,000 ?2030 800,000 ?2031 800,000 ?2032 800,000 ?2033 800,000 Stark Enterprises has following capital structure. ?35% Debt,? 25% preference shares and rest in common equity....
1. Learning Objectives (a)  Develop proforma Project Income Statement Using Excel Spreadsheet (b)  Compute  Net Project Cash flows, NPV,  IRR...
1. Learning Objectives (a)  Develop proforma Project Income Statement Using Excel Spreadsheet (b)  Compute  Net Project Cash flows, NPV,  IRR and PayBack Period 1) Life Period of the Equipment = 4 years 8) Sales for first year (1) $     200,000 2) New equipment cost $          (200,000) 9) Sales increase per year 4% 3) Equipment ship & install cost $            (25,000) 10) Operating cost: $    (120,000) 4) Related start up cost $              (5,000)     (60 Percent of Sales) -60% 5) Inventory increase $             25,000 11) Depreciation (Straight Line)/YR $      (60,000) 6) Accounts Payable...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT