Question

(Capital Budgeting Criteria: Mutually Exclusive Projects) Project S costs $17,000 and its expected cash flows would...

(Capital Budgeting Criteria: Mutually Exclusive Projects)

Project S costs $17,000 and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L costs $28,500 and its expected cash flows would be $11,250 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend?

Select the correct answer.

a. Project L, since the NPVL > NPVS.
b. Both Projects S and L, since both projects have IRR's > 0.
c. Both Projects S and L, since both projects have NPV's > 0.
d. Neither Project S nor L, since each project's NPV < 0.
e. Project S, since the NPVS > NPVL.

Homework Answers

Answer #1

The NPV is computed as shown below:

= Initial investment + Present value of future cash flows

Present value is computed as follows:

= Future value / (1 + r)n

The NPV of Project S is computed as follows:

= - $ 17,000 + $ 4,500 / 1.151 + $ 4,500 / 1.152 + $ 4,500 / 1.153 + $ 4,500 / 1.154 + $ 4,500 / 1.155

= - $ 1,915.30 Approximately

The NPV of Project L is computed as follows:

= - $ 28,500 + $ 11,250 / 1.151 + $ 11,250 / 1.152 + $ 11,250 / 1.153 + $ 11,250 / 1.154 + $ 11,250 / 1.155

= $ 9,211.74 Approximately

Since the NPV of project L is positive and greater than the NPV of project S, hence project L shall be accepted.

So, the correct answer is option a.

Feel free to ask in case of any query relating to this question

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $15,000 and its expected cash flows would...
CAPITAL BUDGETING CRITERIA: MUTUALLY EXCLUSIVE PROJECTS Project S costs $15,000 and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L costs $45,000 and its expected cash flows would be $9,900 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Both Projects S and L, since both projects have NPV's > 0....
Capital budgeting criteria: mutually exclusive projects Project S costs $15,000 and its expected cash flows would...
Capital budgeting criteria: mutually exclusive projects Project S costs $15,000 and its expected cash flows would be $5,500 per year for 5 years. Mutually exclusive Project L costs $40,500 and its expected cash flows would be $10,800 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend? Select the correct answer. I. Both Projects S and L, since both projects have NPV's > 0. II. Project L, since the NPVL > NPVS....
Capital budgeting criteria: mutually exclusive projects Project S costs $11,000 and its expected cash flows would...
Capital budgeting criteria: mutually exclusive projects Project S costs $11,000 and its expected cash flows would be $4,000 per year for 5 years. Mutually exclusive Project L costs $32,000 and its expected cash flows would be $14,700 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend? Select the correct answer. I. Neither S or L, since each project's NPV < 0. II. Project L, since the NPVL > NPVS. III. Project...
10.  Problem 11.11 (Capital Budgeting Criteria: Mutually Exclusive Projects) eBook Project S costs $18,000 and its expected...
10.  Problem 11.11 (Capital Budgeting Criteria: Mutually Exclusive Projects) eBook Project S costs $18,000 and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L costs $39,500 and its expected cash flows would be $7,900 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Both Projects S and L, since both projects have...
Project S costs $19,000 and its expected cash flows would be $6,500 per year for 5...
Project S costs $19,000 and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L costs $32,000 and its expected cash flows would be $8,850 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. a. Project L, since the NPVL > NPVS. b. Both Projects S and L, since both projects have NPV's > 0 . c. Both Projects S and...
Project S costs $12,000 and its expected cash flows would be $5,500 per year for 5...
Project S costs $12,000 and its expected cash flows would be $5,500 per year for 5 years. Mutually exclusive Project L costs $26,000 and its expected cash flows would be $11,500 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have NPV's > 0. b. Project S, since the NPVS > NPVL. c. Neither Project S nor L,...
Project S costs $13,000 and its expected cash flows would be $5,000 per year for 5...
Project S costs $13,000 and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L costs $34,500 and its expected cash flows would be $11,100 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Both Projects S and L, since both projects have NPV's > 0. c. Both Projects S and L,...
Project S costs $14,000 and its expected cash flows would be $6,500 per year for 5...
Project S costs $14,000 and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L costs $37,500 and its expected cash flows would be $14,700 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? a. Project L, since the NPVL > NPVS. b. Both Projects S and L, since both projects have NPV's > 0. c. Neither Project S nor L, since each project's NPV...
Project S costs $19,000 and its expected cash flows would be $6,000 per year for 5...
Project S costs $19,000 and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L costs $38,500 and its expected cash flows would be $14,700 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Project L, since the NPVL > NPVS. c. Both Projects S and L, since both projects have IRR's...
Project S costs $18,000 and its expected cash flows would be $7,000 per year for 5...
Project S costs $18,000 and its expected cash flows would be $7,000 per year for 5 years. Mutually exclusive Project L costs $35,000 and its expected cash flows would be $8,400 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Neither Project S nor L, since each project's NPV < 0. c. Both Projects S and L, since...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT