Question

A project that provides annual cash flows of $13,738 for eight years costs $84,486 today. What...

A project that provides annual cash flows of $13,738 for eight years costs $84,486 today. What is the NPV for the project if the required return is 7 percent? (Negative amount should be indicated by a minus sign. Round your answer to the nearest dollar. (e.g., 32.16)

Homework Answers

Answer #1

NPV(Net Present Value) is the sum of the cash outflows today and present values of the cash inflows in future

Cash Outflow = - $ 84486 (As cash moves out, hence negative sign)

Cash inflows = 13738 for 8 years

Hence present value of cash inflows will be equal to

in this i will take values from 1 to 8 as project is providing these cash flows for 8 years

Basically we are discounting the future cash flows at the required return to get te present values of cash flows

PV of cash flows = $ 82033.65

Therefore NPV = -84486 + 82033.65 = - $ 2452.35

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A project that provides annual cash flows of $11,700 for nine years costs $63,000 today. What...
A project that provides annual cash flows of $11,700 for nine years costs $63,000 today. What is the NPV for the project if the required return is 8 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) At a required return of 8 percent, should the firm accept this project? Accept Reject What is the NPV for the project if the required return is 20 percent? (A negative answer should be indicated by...
A project that provides annual cash flows of $2,700 for nine years costs $8,800 today. Requirement...
A project that provides annual cash flows of $2,700 for nine years costs $8,800 today. Requirement 1: At a required return of 9 percent, what is the NPV of the project? (Do not round intermediate calculations. Round your answer to 2 decimal places (e.g., 32.16).)   NPV   $    Requirement 2: At a required return of 28 percent, what is the NPV of the project? Use the IRR function. (Do not round intermediate calculations. A negative amount should be indicated by a...
A project that provides annual cash flows of $18,100 for eight years costs $87,000 today. What...
A project that provides annual cash flows of $18,100 for eight years costs $87,000 today. What is the NPV for the project if the required return is 7 percent? What is the NPV for the project if the required return is 19 percent? At what discount rate would you be indifferent between accepting the project and rejecting it?
A project that provides annual cash flows of $20,500 for 7 years costs $82,000 today. a....
A project that provides annual cash flows of $20,500 for 7 years costs $82,000 today. a. If the required return is 10 percent, what is the NPV for this project? Determine the IRR for this project.
34. A project that provides annual cash flows of $17,000 for 6 years costs $60,000 today....
34. A project that provides annual cash flows of $17,000 for 6 years costs $60,000 today. a. If the required return is 10 percent, what is the NPV for this project? a. If the required return is 10 percent, what is the NPV for this project? b. Determine the IRR for this project.
A project that provides annual cash flows of $11,300 for 9 years costs $60,209 today. a....
A project that provides annual cash flows of $11,300 for 9 years costs $60,209 today. a. If the required return is 16 percent, what is the NPV for this project? b. Determine the IRR for this project.
A project that provides annual cash flows of $12,800 for 12 years costs $87,215 today.   ...
A project that provides annual cash flows of $12,800 for 12 years costs $87,215 today.    a. If the required return is 13 percent, what is the NPV for this project?    b. Determine the IRR for this project.
A project that provides annual cash flows of $2,900 for 10 years costs $15,300 today. Required:...
A project that provides annual cash flows of $2,900 for 10 years costs $15,300 today. Required: (a) If the required return is 8 percent, what is the NPV for this project? (b) Determine the IRR for this project.
A project that provides annual cash flows of $17,300 for nine years costs $79,000 today. THREE...
A project that provides annual cash flows of $17,300 for nine years costs $79,000 today. THREE QUESTIONS: What is the NPV for the project if the required return is 8 percent What is the NPV for the project if the required return is 20 percent At what discount rate would you be indifferent between accepting the project and rejecting it ?
A project has the following cash flows: Year Cash Flow 0 $ 72,500 1 –51,500 2...
A project has the following cash flows: Year Cash Flow 0 $ 72,500 1 –51,500 2 –28,000 What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) Internal rate of return             % What is the NPV of this project if the required return is 6 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT