Question

A firm is considering Projects S and L, whose cash flows are shown below. These projects...

A firm is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the best procedure. If the wrong decision criterion is used, how much potential value would the firm lose?

WACC: 6.75%
0 1 2 3 4
CFS -$1,025 $380 $380 $380 $380
CFL -$2,150 $765 $765 $765 $765
a. $218.17
b. $182.74
c. $214.44
d. $220.03
e. $186.47

Homework Answers

Answer #1
year Project S Project L
0 -1025 -2150
1 380 765
2 380 765
3 380 765
4 380 765
NPV $269.44 $455.91
IRR 18% 16%

if we consider IRR criterion our decision may go wrong. because according to IRR Project S is better than Project L

mean while In NPV method, Project L is beter than project S

its better to choose NPV method And project L

if we choose project S wrongly instead of project S ,

the potential loss = (difference in NPV)

$455.91- $269.44=
$186.47
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
a firm is considering projects S and L whose cash flows are shown below. these projects...
a firm is considering projects S and L whose cash flows are shown below. these projects are mutually exclusive, equally risky, and not repeatable. the ceo wants to use the IRR criterion, while the cfo favors the npv method. you were hired to advise the firm on the best procedure. if the wrong decision criterion is used, how much potential value would the firm lose? wacc: 7.75% 0. 1. 2. 3. 4. cfs -1,025. 380. 380. 380. 380 cfl -2,150....
A firm is considering Projects S and L, whose cash flows are shown below.  These projects are...
A firm is considering Projects S and L, whose cash flows are shown below.  These projects are mutually exclusive, equally risky, and not repeatable.  The CEO wants to use the IRR criterion, while the CFO favors the NPV method.  You were hired to advise the firm on the best procedure.  If the wrong decision criterion is used, how much potential value would the firm lose? WACC:  4.00% Year                            0                1                2                3                4     CFS                         -$1,025         $380           $380           $380           $380 CFL                         -$2,150         $765           $765           $765           $765 Hint: NPV =  PV inflows – Cost IRR: Internal Rate of Return IRR is the discount...
A firm is considering Projects S and L, whose cash flows are shown below. These projects...
A firm is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method, and you were hired to advise the firm on the best procedure. If the CEO's preferred criterion is used, how much value will the firm lose as a result of this decision? WACC: 13.00% 0 1 2 3 4 CFS -$1,025...
Murray Inc. is considering Projects S and L, whose cash flows are shown below. These projects...
Murray Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise Murray on the best procedure. If the wrong decision criterion is used, how much potential value would Murray lose? r. 6.00% Year 0 1 2 3 4 CFS −$1,025 $380 $380 $380 $380 CFL −$2,150 $765...
A firm is considering to undertake Projects X and Y, whose cash flows are shown below....
A firm is considering to undertake Projects X and Y, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the best procedure. WACC: 6.00% )million of N) Year Year 0 Year 1 Year 2 Year 3 Year 4 CFx -N 1,025 N 380 N 380 N 380 N 380 CFy...
A firm is considering Projects S and L, whose cash flows are shown below. These projects...
A firm is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the best procedure. If the wrong decision criterion is used, how much potential value would the firm lose? WACC: 6.75% 0 1 2 3 4 CFS -$1,025 $380 $380 $380 $380 CFL -$2,150...
Moerdyk & Co. is considering Projects S and L, whose cash flows are shown below. These...
Moerdyk & Co. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under certain conditions choosing projects on the basis of the IRR will not cause any value to be lost because the one with the higher IRR will also have the higher NPV, i.e., no...
Moerdyk & Co. is considering Projects S and L, whose cash flows are shown below. These...
Moerdyk & Co. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under certain conditions choosing projects on the basis of the IRR will not cause any value to be lost because the one with the higher IRR will also have the higher NPV, i.e., no...
Moerdyk & Co. is considering Projects S and L, whose cash flows are shown below. These...
Moerdyk & Co. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under certain conditions choosing projects on the basis of the IRR will not cause any value to be lost because the one with the higher IRR will also have the higher NPV, i.e., no...
Tinner Corp. is considering Projects S and L, whose cash flows are shown below. These projects...
Tinner Corp. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO believes the IRR is the best selection criterion, while the CFO advocates the NPV. If the decision is made by choosing the project with the higher IRR rather than the one with the higher NPV, how much, if any, value will be forgone, i.e., what's the chosen NPV versus the maximum possible NPV?   WACC:...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT