Question

Theresa is analyzing a project that currently has a projected NPV of zero. Which one of...

Theresa is analyzing a project that currently has a projected NPV of zero. Which one of the following changes that the firm is considering is most likely to make the NPV positive? Consider each change independently

A) Increase the variable cost per unit

B) Increase the amount of the initial investment in net working capital

C) Decrease the fixed cost per period

D) Decrease the sales quantity

E) Decrease the sales price

Homework Answers

Answer #1

Option (C) is correct

For making NPV positive, fixed costs per period should be decreased. NPV is the present value of future cash flows minus initial investment. So, if fixed cost per period is reduced, then it will increase the present value of future cash flows and therrby increasing the NPV.

Option (A) is incorrect as if variable cost per unit is increased then present value of cash flows will be decreased thereby decreasing NPV.

Option (B) is incorrect as if the amount of initial investment is increased then it will decrease the NPV.

Option (D) is incorrect as if sales quantity is decreased, then present value of cash flows will be decreased thereby decreasing NPV.

Option (E) is incorrect as if sales price is decreased, then present value of cash flows will be decreased thereby decreasing NPV.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
λambda Corp. is analyzing a project which has the following estimates: Sales price per unit: $63...
λambda Corp. is analyzing a project which has the following estimates: Sales price per unit: $63 Variable costs per unit: $31.50 Fixed costs: $7,300; Required return: 13% Initial investment: $12,000, with no salvage value Depreciation method: Straight-line Project life: five years. λambda Corp. is a non-profit organization and is not subject to income taxes.       What sales quantity will result in an NPV of zero?
If a project has a net present value equal to zero, then: Group of answer choices...
If a project has a net present value equal to zero, then: Group of answer choices the project earns a return exactly equal to the discount rate. the total of the cash inflows must equal the initial cost of the project. a decrease in the project's initial cost will cause the project to have a negative NPV. any delay in receiving the projected cash inflows will cause the project to have a positive NPV. the project's PI must be also...
We are evaluating a project that costs $719,000, has a life of 15 years, and has...
We are evaluating a project that costs $719,000, has a life of 15 years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 124,000 units per year. Price per unit is $39, variable cost per unit is $20, and fixed costs are $728,347 per year. The tax rate is 22 percent, and we require a return of 17 percent on this project. 2c. What is the sensitivity...
Given the following information and assuming straight-line depreciation to zero, what is the NPV for this...
Given the following information and assuming straight-line depreciation to zero, what is the NPV for this project? Initial investment in fixed assets = $800,000 initial investment in net working capital = $200,000 life = 4 years cost savings = $400,000 per year salvage value = $10,000 tax rate = 35% discount rate = 12%
Your firm currently has an operating cycle of 90 days. You are analyzing some operational changes...
Your firm currently has an operating cycle of 90 days. You are analyzing some operational changes which are expected to decrease the accounts receivable period by 4 days and decrease the inventory period by 5 days. The accounts payable turnover rate is expected to increase from 8 to 9 times per year. If all of these changes are adopted, what will be your firm's new cash cycle?
A suggested project requires initial fixed assets of $227,000, has a life of 4 years, and...
A suggested project requires initial fixed assets of $227,000, has a life of 4 years, and has no salvage value. Assume depreciation is straight-line to zero over the life of the project. Sales are projected at 31,000 units per year, the price per unit is $47, variable cost per unit is $23, and fixed costs are $842,900 per year. The tax rate is 23 percent and the required return is 11.5 percent. Suppose the projections given for price and quantity...
You are considering the following project. What is the NPV of the project? Project life: 3...
You are considering the following project. What is the NPV of the project? Project life: 3 years Equipment:      Cost: $18,000      Economic life: 3 years      Salvage value: $4,000 Initial investment in net working capital: $2,000 Revenue: $13,000 in year 1, with a nominal growth rate of 5% per year Fixed cost: $3,000 in year 1 Variable cost: 30% of revenue Corporate tax rate (T): 40% WACC for the project: 10% This project does not create incidental effect.
XZ Inc. is considering a three-year project. The initial investment on the fixed asset will be...
XZ Inc. is considering a three-year project. The initial investment on the fixed asset will be $900,000. Fixed asset will be depreciated using straight-line method to zero over the life of the project. The net working capital investment will be $250,000. The project is estimated to generate $500,000 in annual sales, with cost of $150,000. Assume the tax rate is 34% and required return is 8%, what is the NPV of this project?
Avis Company is analyzing a proposed 3-year project using standard sensitivity analysis. The company expects to...
Avis Company is analyzing a proposed 3-year project using standard sensitivity analysis. The company expects to sell 15,000 units, ±4 percent. The expected variable cost per unit is $11 and the expected fixed costs are $58,000. The fixed and variable cost estimates are considered accurate within a ±5 percent range. The sales price is estimated at $17 a unit, ±5 percent. The project requires an initial investment of $150,000 for equipment that will be depreciated using the straight-line method to...
We are evaluating a project that costs $683988, has a five-year life, and has no salvage...
We are evaluating a project that costs $683988, has a five-year life, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 42400 units per year. Price per unit is $50, variable cost per unit is $22, and fixed costs are $524439 per year. The tax rate is 30%, and we require a return of 18% on this project. Suppose the projections given for price, quantity, variable costs,...